Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD13-03589
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 11959 W OVERLAND RD
Project NameCantabria Development
Customer Number 
ePlanReviewNo
Description
(CANTABRIA DEVELOPMENT - BLDG 10) - To construct a new 3,668 sq. ft., two story, Four unit, apartment building. Units 'A' have one bedroom, one den, and two bathrooms. Units 'B' have two bedrooms, and two bathrooms. All 4 dwelling units have their own independent exit. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partition separations are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00337 Per Planning and Zoning. See BLD13-03579 for building plan review report. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 5/7/201612/16/2016 DONE
This permit finaled on the web by Ami Tracy
First Notice3/1/20163/1/201612/16/2016 DONE
DetailsMike Jordan
This permit finaled on the web by Ami Tracy
Print Occupancy Form  4/27/2016 DONE
Permanent Occupancy  4/27/2016 DONE
BLD-Aging Inspection2/29/20162/29/20163/1/2016 PASS
DetailsMike Jordan
DOC - Permit Finaled3/1/20163/1/20163/1/2016PPASS
DetailsMike Jordan
Temporary Occupancy2/2/20165/2/20162/2/2016 DONE
DetailsCandy A. Nichols
Jason Blais ok'd extension good thru 4/10/16
BLD-Aging Inspection12/30/201512/30/201512/30/2015 PASS
DetailsMike Jordan
Zoning Approval11/18/201511/18/201511/18/2015 DONE
DetailsAndrea Tuning
BLD-Aging Inspection10/19/201510/19/201510/19/2015 PASS
DetailsMike Jordan
Temporary Occupancy10/14/20151/12/201610/14/2015 DONE
DetailsCandy A. Nichols
extension granted for 90 days
Telephone call  10/12/2015 DONE
called Darren to let know that the temp c of o's expire and he needs to call in the finals or requet an extension today-left message on his phone
PubWorks Occupancy Approval7/16/20157/16/20157/16/2015 DONE
DetailsJason C. Taylor
Drainage completed. Jason Taylor ###-####.
Temporary Occupancy7/14/201510/12/20157/14/2015 DONE
DetailsCarlos Velazquez
BLD-Final7/10/20157/13/20157/13/2015APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand. Ok for temp occ. Will be ok for perm occ. once zoning and public works signs perm.
BLD-Final7/9/20157/10/20157/10/2015AFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand. Provide the required 1hr enclosure at riser rooms and at party walls underneath stairs.
Zoning Approval Temp7/9/20157/9/20157/9/2015 DONE
DetailsAndrea Tuning
FIRE-Final Inspection7/1/20157/2/20157/2/2015APASS
DetailsTroy Cobbley
Life safety passed
BLD-Energy code compliance5/11/20155/12/20155/12/2015APASS
DetailsMike Jordan
insulation inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Framing/Rough-in5/8/20155/11/20155/11/2015APASS
DetailsMike Jordan
rough frame Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Framing/Rough-in5/7/20155/8/20155/8/2015ANR
DetailsMike Jordan
rough frame Phone #: ###-#### Inspection requested via web by Mel Rawlinson. Needs fire sprinkler ri
BLD-Wall Bracing4/17/20154/20/20154/20/2015APASS
DetailsMike Jordan
BLD-Wall Bracing4/8/20154/9/20154/9/2015APASS
DetailsMike Jordan
2nd // Tyler Phone #: ###-####. Interior shear walls.
BLD-Wall Bracing3/26/20153/26/20153/26/2015PPASS
DetailsMike Jordan
first floor // Tyler Phone #: ###-####
BLD-Energy code compliance3/10/20153/10/20153/10/2015APASS
DetailsMike Jordan
Vicky Phone #: ###-####. rigid insulation on interior side of foundation wall under SOG.
BLD-Foundation3/3/20153/4/20153/4/2015APASS
DetailsJim Sly
wall // manuel Phone #: ###-####
BLD-Footing3/2/20153/2/20153/2/2015PPASS
DetailsPhil Shearer
Manuel Phone #: ###-####. per MTI inspection
Fees Due Hold11/14/2014 2/3/2015 DONE
DetailsChristina Prado
Fees Due Hold11/13/2014 11/13/2014 DONE
DetailsChristina Prado
Fees Due Hold11/11/2014 11/12/2014 DONE
DetailsChristina Prado
Issue & PRINT to be Invoiced  11/10/2014 DONE
ok per Jenifer G.
OVERRIDE  6/6/2014  
Extend Review Timeline  6/6/2014 DONE
DetailsChristina Prado
Permit Ready to Issue  6/6/2014 DONE
DetailsChristina Prado
CHANGE STATUS TO (FEE)  5/30/2014 DONE
DetailsSam Zahorka
CHANGE STATUS TO (REV)  5/23/2014 DONE
DetailsSam Zahorka
OVERRIDE  3/24/2014  
Permit Ready to Issue  3/24/2014 DONE
DetailsTisha Gallop
Plan assigned to (SRZ)1/23/20141/23/20143/21/2014 PASS
DetailsSam Zahorka
Routing - PLAN CHECK3/19/2014 3/21/2014 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  3/21/2014 DONE
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  3/21/2014 DONE
DetailsSam Zahorka
Case Summary (BLD)  3/21/2014 DONE
DetailsSam Zahorka
Print Occupancy Form  3/21/2014 DONE
DetailsTisha Gallop
Routing - PLANNING Land Div3/20/2014 3/20/2014 PASS
DetailsDave Abo
Routing - FIRE3/18/2014 3/19/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 attached to BLD-03602 dated 03-19-14
Routing - PLUMBING3/18/2014 3/18/2014 PASS
DetailsBill VanDegrift
see bld13-03579
Plan resubmittals received  3/14/2014 DONE
DetailsChristina Prado
Routing Off Site - STRUCTURAL2/27/2014 3/6/2014 PASS
DetailsSam Zahorka
1st review completed  2/28/2014 DONE
DetailsSam Zahorka
Routing - FIRE  2/28/2014 FAIL
See Fire plan Report attached to BLD13-03602 dated 02-28-14
Case Summary (BLD)  2/26/2014 DONE
Plan resubmittals received  2/25/2014 DONE
received response and three copies of structural calcs and plan sheets S1.0 & S2.0; taken back to Fire Review.
Routing - MECHANICAL2/21/2014 2/24/2014 PASS
DetailsTroy James
see bld13-03579 for acca reports
Routing - PLAN CHECK  2/21/2014 FAIL
DetailsSam Zahorka
Routing PW Street Lights2/6/2014 2/6/2014 PASS
DetailsMike D Hedge
Routing - PLUMBING  2/5/2014 FAIL
Plumbing plans are required to be approved and stamped by an Idaho licensed engineer. Plumbing plan not drawn to ISPC.
Routing - PLANNING2/5/2014 2/5/2014 PASS
DetailsAndrea Tuning
Routing - PUBLIC WORKS  1/31/2014 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment1/31/2014 1/31/2014 PASS
DetailsAndy J. Long
Approved with Cantabria Sub ESC plan (reference BLD13-03579/ESC13-01323)
Routing Off Site - STRUCTURAL1/23/2014 1/31/2014 FAIL
DetailsSam Zahorka
Routing PW Sewer Rating  1/31/2014 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste1/28/2014 1/28/2014 PASS
DetailsPeter J. McCullough
Routing PW Sewer Design1/28/2014 1/28/2014 PASS
DetailsKyle S. Rosenmeyer
Routing - Addressing1/23/2014 1/27/2014 PASS
DetailsEmily Dixon
Application received 12/31/20131/23/2014 DONE
Pending Assignment by JCB  1/23/2014 DONE
Routing - PLANNING Land Div1/23/2014 1/23/2014 FAIL
DetailsDave Abo
Telephone call  1/23/2014 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Intake Approval  1/23/2014 PASS
DetailsSam Zahorka
Plans ACCEPTED BY PLAN TECH  12/31/2013  
Recd Pcfee & Taken To Pln CK  12/31/2013  
BLD-Wall Bracing4/17/20154/17/2015 P 
DetailsMike Jordan
exterior shear Phone #: ###-#### >> Inspection requested via web by Mel Rawlinson