Second Notice | | 5/15/2014 | 5/20/2014 | | DONE |
|
|
|
|
First Notice | | 4/18/2014 | 5/5/2014 | | DONE |
|
|
|
|
BLD-Final | 4/7/2014 | 4/8/2014 | 4/8/2014 | A | PASS |
Mike Jordan
|
|
|
Javier Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 4/8/2014 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 4/4/2014 | 4/7/2014 | 4/7/2014 | P | PASS |
Forrest France
|
|
|
Verified previous inspection items. Fire life safety passed.
|
FIRE-Final Inspection | 4/4/2014 | 4/4/2014 | 4/4/2014 | P | FAIL |
Troy Cobbley
|
|
|
Install and provide testing for all of the exit signs and emergency lights as per the approved plans
|
FIRE-Conference | 3/12/2014 | 3/12/2014 | 3/12/2014 | P | DONE |
Troy Cobbley
|
|
|
The existing fire alarm panel which was monitoring the fire sprinkler system has been removed without a permit. I notified scott and romeo about the situation. I requested romeo to sent the fire prevention officer for this area to meet with the owners representative and the job superintendant about a solution such as a fire watch until the fire alarm system is made operational again.
|
BLD-Framing/Rough-in | 3/7/2014 | 3/10/2014 | 3/10/2014 | A | PASS |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Framing for hardlids ok.
|
BLD-Framing/Rough-in | 2/26/2014 | 2/27/2014 | 2/27/2014 | A | PART |
Mike Jordan
|
|
|
doug Phone #: ###-####. Interior steel stud demissing wall for backroom storage area. Double door to receove exit sign. No cover at this area until electrical rough in is completed.
|
Permit Ready to Issue | | | 2/20/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 2/20/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 2/20/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 2/11/2014 | | 2/11/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2014 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 1/14/2014 | | 2/11/2014 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 1/14/2014 | | 2/7/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/7/2014 | | 2/7/2014 | | FAIL |
Carl D Madsen
|
|
|
Engineers calculations are required for the new door opening. Sent E-Mail to Sanjiv. 2-7-13 CDM
|
Routing - FIRE | 2/5/2014 | 2/5/2014 | 2/5/2014 | | PASS |
Craig D. Hanson
|
|
|
Approved with red lines. see Fire Report Rev 1
|
Routing - Design Review | 1/29/2014 | | 1/29/2014 | | PASS |
Josh Wilson
|
|
|
OK per CZC14-00014
|
1st review completed | | | 1/29/2014 | | FAIL |
|
|
|
|
Routing - FIRE | 1/14/2014 | | 1/15/2014 | | FAIL |
Craig D. Hanson
|
|
|
See fire plan report
|
Intake Approval | | | 1/6/2014 | | FAIL |
Sam Zahorka
|
|
|
See Notes under ePlanReview Case
|
Application received | | | 1/3/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 3 2014 10:54AM
|
Pending Assignment by JCM | 1/14/2014 | | | | |
John Menard
|
|
|
|