BLD-Final | 6/19/2014 | 6/19/2014 | 6/19/2014 | P | PASS |
Dave Hannah
|
|
|
Garage code is 2224 Phone #: ###-#### >> Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 6/19/2014 | 6/19/2014 | 6/19/2014 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 6/17/2014 | 6/18/2014 | 6/18/2014 | P | NR |
Mike Jordan
|
|
|
Garage code is 2224 Phone #: ###-#### >> Inspection requested via web by Braxton Hansen. Needs plumbing final.
|
BLD-Wall cover | 4/10/2014 | 4/11/2014 | 4/11/2014 | A | PASS |
Dave Hannah
|
|
|
Insulation inspection so we can sheetrock please. Phone #: ###-#### >> Inspection requested via web by Joshua Edwards
|
BLD-Framing/Rough-in | 4/9/2014 | 4/9/2014 | 4/9/2014 | A | PASS |
Dave Hannah
|
|
|
Framing insp. so we can insulate please. Phone #: ###-#### >> Inspection requested via web by Joshua Edwards
|
BLD-Framing/Rough-in | 4/4/2014 | 4/8/2014 | 4/8/2014 | A | NR |
Dave Hannah
|
|
|
Framing inspection so we can insulate please. Thanks Phone #: ###-#### >> Inspection requested via web by Joshua Edwards no air seal installed
|
BLD-Wall Bracing | 3/26/2014 | 3/26/2014 | 3/26/2014 | P | PASS |
Dave Hannah
|
|
|
Sheer inspection please. Thanks Phone #: ###-#### >> Inspection requested via web by Joshua Edwards
|
BLD-Wall Bracing | 3/25/2014 | 3/26/2014 | 3/26/2014 | A | FAIL |
Dave Hannah
|
|
|
Sheer inspection please. Phone #: ###-#### >> Inspection requested via web by Joshua Edwards needs to nail shear panels
|
BLD-Foundation | 2/26/2014 | 2/26/2014 | 2/27/2014 | P | PASS |
Dave Hannah
|
|
|
Doug Phone #: ###-####
|
BLD-Footing | 2/25/2014 | 2/25/2014 | 2/25/2014 | P | PASS |
Dave Hannah
|
|
|
Doug Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/31/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 1/28/2014 | | |
|
|
|
|
Telephone call | | | 1/28/2014 | | DONE |
Barbara Stitt
|
|
|
Left a voice message for Seth that permit is ready & fees due on 1-28-14 @ 12:10pm
|
Inspection Record Card- Bld | | | 1/28/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/28/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (JG) | 1/16/2014 | 1/16/2014 | 1/27/2014 | | PASS |
Javier Guzman
|
|
|
Due 1/29 L1**
|
Routing - PLAN CHECK | 1/24/2014 | | 1/27/2014 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 1/16/2014 | | 1/27/2014 | | PASS |
Javier Guzman
|
|
|
signed off per PW review report by CB
|
1st review completed | | | 1/27/2014 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 1/27/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2014 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/16/2014 | 1/19/2014 | 1/24/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | | | 1/24/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/17/2014 | | 1/17/2014 | | PASS |
Leon Letson
|
|
|
|
Application received | | 1/16/2014 | 1/16/2014 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/16/2014 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/16/2014 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 1/16/2014 | | PASS |
Tisha Gallop
|
|
|
|
Routing - Addressing | 1/16/2014 | | 1/16/2014 | | PASS |
Jason C. Taylor
|
|
|
|