First Notice | | 1/3/2016 | 1/11/2016 | | DONE |
|
|
|
Mailed 1-12-16
|
Permanent Occupancy | | | 12/24/2015 | | DONE |
|
|
|
|
BLD-Final | 4/4/2014 | 4/4/2014 | 4/4/2014 | P | PASS |
Mike Jordan
|
|
|
Please have Mike call Antonio at ###-####. Hand rail corrections from yesterday''s inspection are taking place this morning and we would like to schedule inspection for later in the afternoon to ensure completion prior to re-inspection. Phone #: ###-#### >> Inspection requested via web by Antonio Carone. All issues resolved. ok for perm occ.
|
FIRE-Final Inspection | 4/3/2014 | 4/3/2014 | 4/3/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Verified emergency generator function for the exit signs/emergency lights power source.
|
BLD-Final | 4/3/2014 | 4/3/2014 | 4/3/2014 | A | FAIL |
Mike Jordan
|
|
|
Spoke with Mike yesterday about canceling and re-scheduling for today between 8:00am and 9:00am. He alleviated that this was acceptable. Feel free to notify me if anything changes. Phone #: ###-#### >> Inspection requested via web by Antonio Carone. Provide code comlpiant handrails and provide edge protection at ramps on data floor.
|
BLD-Final | 4/2/2014 | 4/2/2014 | 4/2/2014 | P | CANC |
Mike Jordan
|
|
|
Would like to schedule for late afternoon. Please have inspector contact me direct this morning for scheduling of time if possible. Antonio Carone ###-#### Phone #: ###-#### >> Inspection requested via web by Antonio Carone. Contractor called and cancelled inspection.
|
BLD-Ceiling Grid Inspection | 3/26/2014 | 3/26/2014 | 3/26/2014 | A | PASS |
Tom Arcoraci
|
|
|
Require a re-inspect this morning as soon as possible. Mike attempted preliminary inspection Tuesday March 25 unable to complete, no printed permit plans on site. Phone #: ###-#### >> Inspection requested via web by Antonio Carone
|
BLD-Ceiling Grid Inspection | 3/25/2014 | 3/25/2014 | 3/25/2014 | P | FAIL |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Needs to provide city set of approved plans.
|
BLD-Ceiling Grid Inspection | 3/24/2014 | 3/25/2014 | 3/25/2014 | P | CANC |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Added in error.
|
BLD-Framing/Rough-in | 2/24/2014 | 2/25/2014 | 2/25/2014 | A | PASS |
Jim Sly
|
|
|
Dan MClenna Phone #: ###-####
|
Permit Ready to Issue | | | 2/20/2014 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/20/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/20/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2014 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 1/21/2014 | | 2/7/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 1/21/2014 | | 2/7/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | 1/21/2014 | | 1/30/2014 | | PASS |
Craig D. Hanson
|
|
|
See attached fire plan report
|
Routing PW Sewer Rating | 1/21/2014 | | 1/23/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 1/21/2014 | | 1/23/2014 | | PASS |
Connie Baumgartner
|
|
|
|
1st review completed | | | 1/21/2014 | | DONE |
|
|
|
|
Routing - Addressing | 1/21/2014 | | 1/21/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 1/21/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Prior to the pre screen being completed please upload the completed 518 checklist and 304 design professional form.
Thank you
1/21/14- The information for the initial pre screen was not uploaded in resubmittal. Please complete items above.
Thank you
|
Intake Approval | | | 1/21/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 1/17/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Prior to the pre screen being completed please upload the completed 518 checklist and 304 design professional form.
Thank you
|
Application received | | | 1/16/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 16 2014 3:02PM
|