Permit Information
Permit NumberBLD14-00124
StatusFinaled
Name BRED INC
Site Address 3317 W CRESCENT RIM DR
Project Name 
Customer Number 
ePlanReviewNo
Description
This project is in two phases, the first phase is extensive demolition of the existing structure including all interior finishes and wall coverings. All plaster is to be removed. Razing of the carport in its entirety, front bay window wall and roof structure. Demolition will include the removal of the basement walls and add structural support as needed for the extensive remodel of the basement including select floor work to add ceiling height and new plumbing to reflect the extensive remodel. There will be a new 1200s.f. 3-car garage, new entry stoop and addition of 1669s.f. of living space that includes extension of the front main level wall and a new upper level. Separate electrical, plumbing and mechanical permits are required. All per the approved plans as maarked and the plan review notes. pep
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/11/20153/12/20153/12/2015APASS
DetailsDave Hannah
Anthony Phone #: ###-####
DOC - Permit Finaled3/12/20153/12/20153/12/2015PPASS
DetailsDave Hannah
Letter of compliance/Occupancy  3/12/2015 DONE
BLD-Final3/10/20153/10/20153/10/2015PFAIL
DetailsDave Hannah
Anthony Phone #: ###-#### c/n on site
BLD-Final3/6/20153/9/20153/10/2015ANR
DetailsDave Hannah
Anthony Phone #: ###-#### needs mec final
BLD-Final1/22/20151/23/20151/23/2015ANR
DetailsDave Hannah
Call prior to going Phone #: 2088701943 >> Inspection requested via mobile web by Kyle Cooper needs other trades to final
BLD-Energy code compliance6/18/20146/19/20146/19/2014APASS
DetailsTom Arcoraci
Anthony Phone #: ###-####
BLD-Framing/Rough-in6/16/20146/17/20146/17/2014APASS
DetailsTom Arcoraci
anthony Phone #: ###-####
Routing - MECHANICAL5/28/2014 5/28/2014 PASS
DetailsTroy James
Plan Modification Accepted  5/23/2014 DONE
new manual j
Routing - MECHANICAL5/23/2014 5/23/2014 FAIL
DetailsTroy James
resubmitted manual j
BLD-Wall Bracing5/19/20145/19/20145/19/2014PPASS
DetailsTom Arcoraci
Anothony Phone #: ###-####
BLD-Footing3/31/20143/31/20143/31/2014PPASS
DetailsTom Arcoraci
pat Phone #: ###-####
CHANGE STATUS TO (ISS)  3/26/2014 DONE
DetailsTisha Gallop
plan mod
OVERRIDE  3/10/2014  
Routing Walk-In (BLD)2/13/20142/13/20143/10/2014PDONE
DetailsTroy James
route to Troy for acca report approval 2-13-2014 pep
Inspection Record Card- Bld  3/10/2014  
PLANS/APPL TAKEN TO FRONT DESK  3/10/2014 DONE
Permit Ready to Issue  3/10/2014 DONE
DetailsTisha Gallop
per PEP not need to call applicant, they will be here in AM.
Routing - MECHANICAL3/5/2014 3/5/2014 PASS
DetailsTroy James
Routing - MECHANICAL2/18/2014 2/18/2014 FAIL
DetailsTroy James
emailed correction to cameron brown
Routing Walk-In (Zoning)2/13/20142/13/20142/13/2014APASS
DetailsLeon Letson
modify permit to add 2nd phase which is total remodel and addition
Routing Walk-In (BLD)2/13/20142/13/20142/13/2014AFAIL
DetailsPerry Paine
OVERRIDE  1/31/2014  
Routing Walk-In (BLD)1/21/20141/21/20141/21/2014PDONE
DetailsPerry Paine
Plan assigned to (PEP)1/21/20141/21/20141/21/2014 PASS
DetailsPerry Paine
Inspection Record Card- Bld  1/21/2014  
1st review completed  1/21/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/21/2014 DONE
Issue PAID IN FULL permit  1/21/2014 DONE
DetailsBarbara Stitt
Permit Ready to Issue  1/21/2014 DONE
DetailsBarbara Stitt
CHANGE STATUS TO (ISS)  1/21/2014 DONE
DetailsBarbara Stitt
Application received 1/21/2014