BLD-Final | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | PART |
Jim Sly
|
|
|
Larry Phone #: ###-#### All interior corrections completed. Waiting for drainage approval.
|
BLD-Final | 8/4/2014 | 8/5/2014 | 8/5/2014 | A | NR |
Tony Young
|
|
|
Late morning - Larry Phone #: ###-####,, walk through only,, needs hillside and handrails,, firecaulk
|
BLD-Energy code compliance | 5/22/2014 | 5/23/2014 | 5/23/2014 | P | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 5/23/2014 | 5/23/2014 | 5/23/2014 | P | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Energy code compliance | 5/22/2014 | 5/23/2014 | 5/23/2014 | A | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 5/20/2014 | 5/21/2014 | 5/21/2014 | A | FAIL |
Tony Young
|
|
|
Larry-Early please Phone #: ###-####,, ok to insulate,, c/n posted
|
BLD-Wall Bracing | 5/7/2014 | 5/8/2014 | 5/8/2014 | A | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, exterior shear ok
|
BLD-Wall Bracing | 5/6/2014 | 5/7/2014 | 5/7/2014 | A | NR |
Tony Young
|
|
|
Larry Phone #: ###-####,, nail per plan
|
BLD-Foundation | 3/17/2014 | 3/18/2014 | 3/18/2014 | P | PART |
Tony Young
|
|
|
alvaro Phone #: ###-####
|
BLD-Footing | 3/14/2014 | 3/14/2014 | 3/14/2014 | P | PASS |
Tony Young
|
|
|
Alvaro Phone #: ###-####,, main level
|
PubWorks Subgrade Approval | 3/14/2014 | 3/14/2014 | 3/14/2014 | | DONE |
Jason C. Taylor
|
|
|
*GARAGE, SLABS, & STRUCTURAL FOOTINGS ONLY** A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Foundation | 3/3/2014 | 3/3/2014 | 3/3/2014 | P | PART |
Tony Young
|
|
|
Advardo Phone #: ###-####,, basement walls ok
|
BLD-Footing | 2/24/2014 | 2/25/2014 | 2/25/2014 | A | PART |
Tony Young
|
|
|
Phone #: ###-####,, basement ftgs ok
|
PubWorks Subgrade Approval | 2/24/2014 | 2/24/2014 | 2/24/2014 | | DONE |
Jason C. Taylor
|
|
|
*BASEMENT FOOTINGS AND SLAB ONLY** A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 2/13/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 2/6/2014 | | |
|
|
|
|
Telephone call | | | 2/6/2014 | | DONE |
Barbara Stitt
|
|
|
Called Larry Christensen and told him that permit is ready & fees due on 2-6-14 @ 11:35am///BAS
|
Inspection Record Card- Bld | | | 2/6/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 2/6/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (JG) | 1/22/2014 | 1/22/2014 | 2/5/2014 | | PASS |
Javier Guzman
|
|
|
Due 2/10 L2 Hillside**
|
Routing - PLAN CHECK | 1/28/2014 | | 2/5/2014 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 2/5/2014 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 2/5/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2014 | | DONE |
|
|
|
|
Routing - MECHANICAL | 2/3/2014 | | 2/3/2014 | | PASS |
Troy James
|
|
|
|
Routing PW Grading-Hillside | 2/3/2014 | | 2/3/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Plan resubmittals received | | | 1/29/2014 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheets marked Grading, 1 of 10, 2 of 10, 3 of 10, 4 of 8 & 6 of 10, as well as one additional grading plan; Taken back to Javier for further review
|
Routing - FIRE | 1/27/2014 | | 1/28/2014 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - Erosion and Sediment | 1/27/2014 | | 1/27/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan and SWPPP submitted and approved. Valid PD and RP provided in application.
|
Routing - MECHANICAL | | | 1/27/2014 | | FAIL |
Troy James
|
|
|
emailed Don- heating supply
|
Route to Impact Fee Review | 1/22/2014 | 1/25/2014 | 1/24/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 1/24/2014 | | 1/24/2014 | | PASS |
Leon Letson
|
|
|
|
Routing - PUBLIC WORKS | 1/23/2014 | | 1/24/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | 1/22/2014 | | 1/23/2014 | | FAIL |
Jason C. Taylor
|
|
|
Grading plan needs revised to show drainage patterns for sunken garden area, detail for inlet at garden area, detail for rip-rap at end of pipe, Foundation drain details and locations. Retaining wall calculations also needed for walls over 4ft tall. Jason Taylor ###-####.
|
Routing - Addressing | 1/22/2014 | | 1/23/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 1/22/2014 | 1/22/2014 | | DONE |
|
|
|
|
Intake Approval | | | 1/22/2014 | | FAIL |
Christina Prado
|
|
|
Missing ESC narrative, ICC-ES report for spray foam, tempered window detail and garage door/dwelling seperation
|
Plans ACCEPTED BY PLAN TECH | | | 1/22/2014 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/22/2014 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 1/22/2014 | | PASS |
Tisha Gallop
|
|
|
|