Third Notice | | 2/16/2016 | 3/10/2016 | | DONE |
|
|
|
|
Second Notice | | 1/23/2016 | 2/11/2016 | | DONE |
|
|
|
Mailed 2-12-16
|
First Notice | | 1/3/2016 | 1/13/2016 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/24/2015 | | DONE |
|
|
|
|
BLD-Final | 2/5/2015 | 2/6/2015 | 2/6/2015 | A | CANC |
Mike Jordan
|
|
|
Nick Phone #: ###-####
|
BLD-Final | 2/6/2015 | 2/6/2015 | 2/6/2015 | P | PASS |
Mike Jordan
|
|
|
Nick Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 2/6/2015 | 2/6/2015 | 2/6/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Framing/Rough-in | 11/21/2014 | 11/24/2014 | 11/24/2014 | A | PASS |
Mike Jordan
|
|
|
Joe Phone #: ###-####
|
Plan assigned to (AJS) | 11/18/2014 | 11/18/2014 | 11/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Plan modification
|
Routing - PLAN CHECK | 11/19/2014 | | 11/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
plan modification
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2014 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/21/2014 | | DONE |
|
|
|
paid for plan modification
|
BLD-Energy code compliance | 11/18/2014 | 11/18/2014 | 11/18/2014 | P | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####. exterior walls only ok to cover.
|
Plan Modification Accepted | | | 11/18/2014 | | DONE |
Christina Prado
|
|
|
Plan modification workflow started per Architects request
|
BLD-Framing/Rough-in | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PART |
Mike Jordan
|
|
|
Interior steel stud framed walls. ok to insulate. Waiting for resubmittal for the two additional noffices that have been added.
|
BLD-Framing/Rough-in | 11/14/2014 | 11/17/2014 | 11/17/2014 | A | NR |
Mike Jordan
|
|
|
Dan Phone #: ###-####. No approved plans on site. No inspection.
|
BLD-Framing/Rough-in | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | NR |
Mike Jordan
|
|
|
Dan Phone #: ###-####. Needs mep rough in inspections first.
|
Permit Ready to Issue | | | 9/18/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue PAID IN FULL permit | | | 9/18/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Print Occupancy Form | | | 9/18/2014 | | |
Candy A. Nichols
|
|
|
|
Extend Review Timeline | | | 7/22/2014 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 6/30/2014 | 7/22/2014 | 6/30/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 1/27/2014 | 1/27/2014 | 2/7/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Ameriprise Due 1/31
|
Routing - PLAN CHECK | 2/7/2014 | | 2/7/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/27/2014 | | 1/31/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Ameriprise Due 1/31
see change marks in e plan
|
1st review completed | | | 1/31/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Addressing | 1/27/2014 | | 1/27/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 1/27/2014 | | 1/27/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 1/27/2014 | | 1/27/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 1/27/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 1/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 22 2014 10:40AM
|