Permit Information
Permit NumberBLD14-00151
StatusFinaled
Name JARVIS ENTERPRISES INC
Site Address 1124 W FRONT ST
Project NameBoise Art Glass - Fire Fusion
Customer Number 
ePlanReviewYes
Description
(BOISE ART GLASS - FIRE FUSION STUDIO) Fire sprinklers used for story increase. To convert a former 8,445 square foot bar/lounge/nightclub (5,795 square foot 1st story, 180 square foot mezzanine, and 2,470 square foot 2nd story) to a glass art studio and a metal art studio. Metal artwork will be created within the metal studios. One metal studio will be enclosed for noise isolation. Glass artwork will be created within the glass studios. Completed artwork will be displayed for sale within the retail areas. Metal working tools and activities will include enameling kilns, a pottery kiln, welding, soldering, grinding, sanding, drilling, fusing, cutting, and casting. Glass working tools and activities will include kilns, an annealer, and a furnace. Hoods shall be provided at equipment if required by the 2009 IMC. If hoods are provided, hoods and make-up air shall comply with the 2009 IMC. Demolition work includes removing a stairway and a portion of the mezzanine/balcony. Work includes a new storefront entry, new exterior windows, new overhead doors, interior nonbearing walls, a stairway, and accessible upgrades. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. All equipment shall be listed and labeled per the adopted Electrical Code with approval from the PDS Electrical Inspection Section. The design for the new stairway that will serve the mezzanine is a deferred submittal item. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 6/10/20146/16/2014 DONE
DetailsChristina Prado
completed 6-16-14
Second Notice 5/17/20146/5/2014 DONE
DetailsChristina Prado
First Notice 4/21/20145/7/2014 DONE
Mailed 5-7-14
BLD-Final4/9/20144/10/20144/11/2014APASS
DetailsDave Hannah
Brandon Boomgarden Phone #: ###-####
BLD-Final4/10/20144/11/20144/11/2014APASS
DetailsDave Hannah
Brandon-Please call at least 30 mins prior to inspection Phone #: ###-####
Zoning Approval4/11/20144/11/20144/11/2014 PASS
DetailsJosh Wilson
Permanent Occupancy  4/11/2014 DONE
DetailsChristina Prado
FIRE-Final Inspection4/9/20144/9/20144/9/2014PPASS
DetailsForrest France
Fire life safety inspection passed.
FIRE-Conference4/9/20144/9/20144/9/2014ADONE
DetailsForrest France
On site conference regarding fire life safety inspection items and conditions for final.
BLD-Framing/Rough-in3/10/20143/11/20143/11/2014APART
DetailsJim Sly
Brandon Phone #: ###-####
Small wall in restroom OK.
Permit Ready to Issue  3/3/2014 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  3/3/2014 DONE
DetailsChristina Prado
Print Occupancy Form  3/3/2014 DONE
DetailsChristina Prado
Plan assigned to (CJW)1/27/20141/27/20142/28/2014 PASS
DetailsCarl Westfall
BOISE ART GLASS - FIRE FUSION STUDIO - ePlanReview - Level 3 TI (20 days - Feb 21)
Routing - PLAN CHECK2/27/2014 2/28/2014 DONE
DetailsCarl Westfall
Routing completed
Routing - FIRE2/27/2014 2/28/2014 PASS
DetailsCraig D. Hanson
See attached Revision 2 report 02-27-14
PLANS/APPL TAKEN TO FRONT DESK  2/28/2014 DONE
Plan resubmittals received  2/27/2014 DONE
No added documents or drawings by the Architect.
Routing - FIRE2/20/2014 2/24/2014 FAIL
DetailsCraig D. Hanson
See attached report
Plan resubmittals received  2/20/2014 DONE
Workflow came back from the Architect on 2-19-14 but he added more documents on 2-20-14.
Routing - PLAN CHECK2/19/2014 2/20/2014 PASS
DetailsCarl Westfall
Drawings approved with "red lines".
Routing PW Solid Waste1/27/2014 2/19/2014 PASS
DetailsPeter J. McCullough
1st review completed  2/19/2014 DONE
Failed Fire and Building
Plan resubmittals requested  2/19/2014 DONE
Routing - PLAN CHECK1/27/2014 2/19/2014 FAIL
DetailsCarl Westfall
Revised drawings required.
Routing - FIRE1/27/20141/27/20141/30/2014 FAIL
DetailsScott Arellano
See Fire Plan Report 01-30-14
Routing - Design Review1/27/2014 1/29/2014 PASS
DetailsJosh Wilson
Ok per CZC14-00007
Routing PW Environmental1/27/2014 1/29/2014 PASS
DetailsWalt Baumgartner
TI in old food service space will house glass blowing operation. Plans show existing floor sinks in old walkin coolers, etc. Facility will be subject to post opening pretreatment inspection to evaluate for accidental spill protection plan. Operator may be required to plug floor drains at a later date.
Plan Reviewer's activity  1/27/2014 DONE
DetailsAdele J Schaffeld-Griffin
The zoning certificate uploaded did not include a description of the exterior work. I spoke with Josh Wilson and he is in the process of putting in the description but has already sent them the approved zoning certificate. He was okay with taking the plans in and he will get the description put in.
Intake Approval  1/27/2014 PASS
DetailsJason Blais
Prescreen approved by Adele Schaffeld-Griffin. Plan Review Fees paid.
Pending Assignment by JCB1/27/2014 1/27/2014 DONE
DetailsJason Blais
Plan Reviewer's activity  1/27/2014 DONE
DetailsJason Blais
Emailed architect to have him contact ACHD to evaluate if any additional impact fees are due. Written verification from ACHD is required to be provided to the Permit Counter prior to the building permit being issued.
Routing PW Sewer Rating1/27/2014 1/27/2014 PASS
DetailsConnie Baumgartner
Routing - Addressing1/27/2014 1/27/2014 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS1/27/2014 1/27/2014 PASS
DetailsBeverly Mountain
Application received  1/23/2014 DONE
Application submitted via PDS Online on Jan 23 2014 12:58PM