First Notice | | 6/23/2014 | 7/15/2014 | | DONE |
|
|
|
Faxed 7-15-14
|
FIRE-Final Inspection | 6/13/2014 | 6/13/2014 | 6/13/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled. Inspection passed.
|
BLD-Final | 6/12/2014 | 6/13/2014 | 6/13/2014 | A | PART |
Dave Hannah
|
|
|
Jason Phone #: ###-#### needs plumbing and fire life safety ok to final after that.
|
Permanent Occupancy | | | 6/13/2014 | | DONE |
Barbara Stitt
|
|
|
Shouldn't have issued this should have issued a letter of compliance
|
Letter of compliance/Occupancy | | | 6/13/2014 | | DONE |
Barbara Stitt
|
|
|
Shouldn't have issued cert of occ should have issued a letter of compliance
|
BLD-Conference | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | PART |
Dave Hannah
|
|
|
Phone #: 5710308 >> Inspection requested via mobile web by Jason Schwenson 2nd floor elec closet and 3rd floor copy room ok to cover
|
Permit Ready to Issue | | | 4/14/2014 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/14/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/14/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/14/2014 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 2/18/2014 | 2/18/2014 | 3/4/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 2/24 Boise Library Upgrade
|
Routing - PLAN CHECK | 2/27/2014 | | 3/4/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/18/2014 | | 2/24/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
1st review completed | | | 2/24/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 2/18/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PUBLIC WORKS | 2/18/2014 | | 2/18/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 2/18/2014 | | 2/18/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 2/3/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Please re upload the 304 document. The document did not upload and will not open.
2. Please complete and upload the 518 checklist.
Once the check list is uploaded I will begin the pre screen.
Thank you
|
Application received | | | 1/27/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 27 2014 5:16PM
|