Second Notice | | 9/25/2014 | 9/15/2014 | | DONE |
Christina Prado
|
|
|
completed 9-15-14
|
First Notice | | 7/20/2014 | 8/26/2014 | | DONE |
|
|
|
|
BLD-Final | 7/9/2014 | 7/10/2014 | 7/10/2014 | P | PASS |
Mike Jordan
|
|
|
Frank Phone #: ###-####. ok for perm occ.
|
Permanent Occupancy | | | 7/10/2014 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 7/2/2014 | 7/7/2014 | 7/7/2014 | A | PART |
Mike Jordan
|
|
|
Frank Phone #: ###-####. Ok for temp occ. Main doors were wrong size and are using temp. doors until perm. doors are installed.
|
BLD-Final | 7/1/2014 | 7/2/2014 | 7/2/2014 | P | CANC |
Mike Jordan
|
|
|
Lyle Phone #: ###-####
|
FIRE-Final Inspection | 7/1/2014 | 7/2/2014 | 7/2/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 6/30/2014 | 7/1/2014 | 7/1/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. Main entrance door has not been installed
|
BLD-Ceiling Grid Inspection | 6/20/2014 | 6/20/2014 | 6/20/2014 | P | PASS |
Mike Jordan
|
|
|
Drew-t-bar ceiling Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/17/2014 | 6/17/2014 | 6/17/2014 | P | NR |
Mike Jordan
|
|
|
Drew Phone #: ###-####. Needs trades rough in insp[ections.
|
BLD-Other | 6/2/2014 | 6/2/2014 | 6/2/2014 | P | PASS |
Mike Jordan
|
|
|
bracing insp // Drew Phone #: ###-####
|
BLD-Framing/Rough-in | 5/29/2014 | 5/30/2014 | 5/30/2014 | P | PASS |
Mike Jordan
|
|
|
Drew Phone #: ###-####. Framing for storefront ok.
|
BLD-Framing/Rough-in | 5/22/2014 | 5/23/2014 | 5/23/2014 | A | PART |
Jim Sly
|
|
|
Drew Phone #: ###-#### All OK except for store front.
|
Print Occupancy Form | | | 4/30/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 4/30/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 4/30/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 4/21/2014 | | 4/21/2014 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 2/24/2014 | | 4/21/2014 | | PASS |
Tim L. Woodard
|
|
|
Lane Bryant
|
Plan resubmittals received | | | 4/18/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Sewer Rating | 2/24/2014 | | 3/14/2014 | | PASS |
Connie Baumgartner
|
|
|
Approved in E-Plan.
|
1st review completed | | | 3/14/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 2/24/2014 | | 3/14/2014 | | FAIL |
Tim L. Woodard
|
|
|
Change Marks in E-Plan. TLW
|
Routing - FIRE | 2/24/2014 | | 3/4/2014 | | PASS |
Craig D. Hanson
|
|
|
See attached Fire Plan Report
|
Routing - Addressing | 2/24/2014 | | 2/25/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 2/24/2014 | | 2/24/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 2/24/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | | 1/28/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 28 2014 1:35PM
|
Intake Approval | | | 1/28/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Before a pre screen can begin please
1-re upload the drawings under the drawing folder.
2-provide the required stamping area as per the electronic submittal standards
3-complete and upload the 518 checklist and required documents from the checklist
4-complete and upload the 304 design professional or record form
5-Upload letter of approval from the mall for this project.
Once all of the items above have been addressed as I will be able to complete the pre screen.
Thank you
|