Third Notice | | 6/14/2015 | 6/25/2015 | | DONE |
|
|
|
This permit finaled on the web by Jody Wilson
|
Second Notice | | 5/14/2015 | 6/9/2015 | | DONE |
|
|
|
sent in mail
|
First Notice | | 3/20/2015 | 5/4/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/10/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 3/9/2015 | | DONE |
|
|
|
Called Jody-all inspections have been done-she will be in today to get the perm c of o
|
BLD-Final | 3/5/2015 | 3/6/2015 | 3/6/2015 | P | PASS |
Phil Shearer
|
|
|
Charles Phone #: ###-####
|
Zoning Approval | 3/6/2015 | 3/6/2015 | 3/6/2015 | | DONE |
Andrea Tuning
|
|
|
|
PubWorks Occupancy Approval | 3/4/2015 | 3/4/2015 | 3/4/2015 | | DONE |
Tiffany Lowery
|
|
|
|
Temporary Occupancy | 2/13/2015 | 5/14/2015 | 2/13/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 2/13/2015 | | DONE |
|
|
|
|
BLD-Final | 2/11/2015 | 2/12/2015 | 2/12/2015 | A | PART |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Ok for temp. occ.
|
PubWorks Temp Occupancy Appr | 2/12/2015 | 2/12/2015 | 2/12/2015 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 2/9/2015 | 2/11/2015 | 2/11/2015 | P | NR |
Mike Jordan
|
|
|
Change of day per Charlie 2-10-15 blh Phone #: ###-####. Needs public works and zoning finals.
|
FIRE-Final Inspection | 2/10/2015 | 2/11/2015 | 2/11/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 2/9/2015 | 2/11/2015 | 2/10/2015 | A | FAIL |
Troy Cobbley
|
|
|
Charlie Phone #: ###-####
|
BLD-Framing/Rough-in | 12/23/2014 | 12/24/2014 | 12/24/2014 | A | PASS |
Jim Storey
|
|
|
Charley Phone #: ###-####
|
BLD-Energy code compliance | 12/24/2014 | 12/24/2014 | 12/24/2014 | A | PASS |
Jim Storey
|
|
|
Charley Phone #: ###-####
|
BLD-Framing/Rough-in | 12/12/2014 | 12/15/2014 | 12/15/2014 | P | PASS |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. All previous issues have been resolved. it is ok to cover the exterior of the building.
|
BLD-Wall Bracing | 12/15/2014 | 12/15/2014 | 12/15/2014 | P | PASS |
Mike Jordan
|
|
|
Charlie Phone #: ###-####
|
BLD-Framing/Rough-in | 12/12/2014 | 12/12/2014 | 12/12/2014 | P | FAIL |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Re nail sill plate, provide additional nailing above opening on shear wall type 2. Install nuts on anchor bolts at exterior columns.
|
BLD-Framing/Rough-in | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | PASS |
Mike Jordan
|
|
|
roof//Charley Phone #: ###-####. Roof diaphragm ok to cover, all repairs per engineers RFI for straps that were installed incorrectly. Also miising straps installed per approved plans.
|
FIRE-Conference | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | DONE |
Troy Cobbley
|
|
|
Discussed fire stopping in the exterior columns.
|
BLD-Framing/Rough-in | 11/25/2014 | 12/1/2014 | 12/1/2014 | A | FAIL |
Mike Jordan
|
|
|
Charlie Phone #: ###-####. Roof diaphragm inspection. Edge and field nailing and associated blocking ok. Missing 2 CMSTC40 straps on east and west ends. Also will need engineering on remainder of roof strapping not installed per approved plan. End of straps should have been bent over 2x6 ledger and nailed. In place work, strapping stops at edge of 2x8 and nailed.
|
BLD-Footing | 10/2/2014 | 10/2/2014 | 10/2/2014 | P | PART |
Mike Jordan
|
|
|
Work in progress. Special inspector to reinforcemment in footings.
|
BLD-Foundation | 10/1/2014 | 10/2/2014 | 10/2/2014 | A | NR |
Mike Jordan
|
|
|
Late AM - Charlie Phone #: ###-####. work in progress. Will have special inspection
|
Issue PAID IN FULL permit | | | 9/5/2014 | | DONE |
Candy A. Nichols
|
|
|
|
OVERRIDE | | | 8/22/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 8/22/2014 | | DONE |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 8/21/2014 | 8/26/2014 | 8/21/2014 | | PASS |
James McMahon
|
|
|
Fire and Police IF's added.
|
Extend Review Timeline | | | 7/17/2014 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 7/8/2014 | 7/29/2014 | 7/8/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 3/10/2014 | | 3/11/2014 | | PASS |
John Menard
|
|
|
|
Routing - Design Review | 3/11/2014 | | 3/11/2014 | | PASS |
Andrea Tuning
|
|
|
There is a red line on the site lighting plan. Pole lighting may not be placed in teh required planter island and should be relocated.
|
Routing - PLAN CHECK | 3/11/2014 | | 3/11/2014 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2014 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 2/3/2014 | | 3/11/2014 | | PASS |
John Menard
|
|
|
1st Review completed 2/5/2014
|
Routing - Design Review | 3/10/2014 | | 3/10/2014 | | FAIL |
Andrea Tuning
|
|
|
The applicant has not installed the required Class II tree located within the terminus planter in the parking area. This was a condition of approval of the design review approval.
|
Plan Reviewer's activity | | | 3/7/2014 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and nonstructural revisions. JCM
|
Routing - PLAN CHECK | 3/4/2014 | | 3/7/2014 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 3/4/2014 | 3/4/2014 | 3/5/2014 | | PASS |
Craig D. Hanson
|
|
|
See Attached Fire Plan Review 03-05-14
|
Routing - Design Review | 3/4/2014 | | 3/4/2014 | | FAIL |
Andrea Tuning
|
|
|
The applicant is required to provide 5 trees along Cole Road and one treet within the terminus planter within the parking field per the Conditions of Approval of DRH13-00383.
|
1st review completed | | | 2/14/2014 | | DONE |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 2/3/2014 | | 2/14/2014 | | FAIL |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 2/3/2014 | | 2/7/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 2/3/2014 | | 2/7/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 2/3/2014 | 2/3/2014 | 2/6/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Report 02-06-14
|
Routing - PLAN CHECK | 2/3/2014 | | 2/5/2014 | | FAIL |
John Menard
|
|
|
|
Routing - PLUMBING | 2/3/2014 | | 2/4/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 2/3/2014 | | 2/4/2014 | | FAIL |
Andrea Tuning
|
|
|
The applicant is required to:
Install five Class II or Class III street trees along Cole Road.
Install five Class II or Class III street trees along the I-84 connector off ramp.
Install a Class II tree in all interior planter islands on the site.
|
Routing PW Street Lights | 2/3/2014 | | 2/4/2014 | | PASS |
Mike D Hedge
|
|
|
|
Routing PW Solid Waste | 2/3/2014 | | 2/4/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Sewer Design | 2/3/2014 | | 2/3/2014 | | CANC |
Kyle S. Rosenmeyer
|
|
|
Project is in West Boise Sewer District.
|
Routing - Erosion and Sediment | 2/3/2014 | | 2/3/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep inspection Required prior to earth disturbance/construction
|
Routing PW Sewer Rating | 2/3/2014 | | 2/3/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCM | 2/3/2014 | | 2/3/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 2/3/2014 | | 2/3/2014 | | PASS |
Dave Abo
|
|
|
Parcel D of ROS 9592.
|
Routing - Addressing | 2/3/2014 | | 2/3/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 2/3/2014 | | PASS |
John Menard
|
|
|
|
Application received | | | 1/30/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 30 2014 4:49PM
|
Zoning Approval Temp | 2/13/2015 | 2/13/2015 | | | PASS |
|
|
|
|