Second Notice | | 7/25/2014 | 8/26/2014 | | DONE |
|
|
|
|
First Notice | | 7/3/2014 | 7/15/2014 | | DONE |
|
|
|
Faxed 7-15-14
|
Permanent Occupancy | | | 6/23/2014 | | DONE |
|
|
|
|
BLD-Final | 6/20/2014 | 6/20/2014 | 6/20/2014 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 6/19/2014 | 6/20/2014 | 6/20/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 5/2/2014 | 5/2/2014 | 5/2/2014 | A | PASS |
Mike Jordan
|
|
|
ok to cover.
|
BLD-Framing/Rough-in | 5/1/2014 | 5/1/2014 | 5/1/2014 | P | PART |
Mike Jordan
|
|
|
jim Phone #: ###-####. No approved plans on site. reviewed plan that was on site and inspected the interior non bearing steel stud walls. ok to on side and insulate only. Contractor to call another framing inspection for friday in the am and will review approved plans prior to cover.
|
CHANGE STATUS TO (ISS) | | | 5/1/2014 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 4/24/2014 | 4/24/2014 | 4/29/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
waiting on plan mod to be uploaded
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/23/2014 | | 4/29/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
plan modification
|
Permit Ready to Issue | | | 4/24/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 4/24/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 4/24/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 4/23/2014 | 4/23/2014 | 4/23/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Ron requested plan mod - permits not issued yet so no need for plan mod app
|
Plan Modification Accepted | | | 4/23/2014 | | DONE |
Tisha Gallop
|
|
|
plan mod workflow started for misc arch, elec, mech changes to tenant space
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/2014 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 2/3/2014 | 2/3/2014 | 3/7/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed CWIRout to addressing and PW
|
Routing - PLAN CHECK | 3/7/2014 | | 3/7/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/3/2014 | | 2/4/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan will need to route to PW when re submitted
|
1st review completed | | | 2/4/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 2/4/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 2/1/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 1 2014 10:16AM
|