Third Notice | | 11/8/2014 | 11/25/2014 | | DONE |
Christina Prado
|
|
|
|
Second Notice | | 10/16/2014 | 11/3/2014 | | DONE |
|
|
|
|
First Notice | | 8/25/2014 | 10/6/2014 | | DONE |
Candy A. Nichols
|
|
|
sent in mail 10-6-14
|
PubWorks Occupancy Approval | 9/25/2014 | 9/25/2014 | 8/15/2014 | | DONE |
|
|
|
Brian Murphy inspected.
|
Zoning Approval | 8/15/2014 | 8/15/2014 | 8/15/2014 | | PASS |
Sarah Schafer
|
|
|
Passed both zoning and design review inspection. Requested an "as built" landscape plan as trees were moved and additional vegetation was added.
|
Permanent Occupancy | | | 8/15/2014 | | DONE |
Candy A. Nichols
|
|
|
as per Bill Vandegrift ok to issue C of O with out the back flow final. It will be done next week
|
BLD-Final | 8/13/2014 | 8/14/2014 | 8/14/2014 | P | PASS |
Jim Storey
|
|
|
eric Phone #: ###-####
|
FIRE-Final Inspection | 8/13/2014 | 8/14/2014 | 8/14/2014 | A | PASS |
Forrest France
|
|
|
Life safety inspection passed.
|
BLD-Ceiling Grid Inspection | 7/31/2014 | 7/31/2014 | 7/31/2014 | P | PASS |
Jim Sly
|
|
|
Eric Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | NR |
Mike Jordan
|
|
|
Aaron Phone #: ###-####. Needs trades first.
|
BLD-Framing/Rough-in | 7/7/2014 | 7/7/2014 | 7/7/2014 | P | PASS |
Mike Jordan
|
|
|
Aaron-please go as close to 10 as possible Phone #: ###-####
|
BLD-Energy code compliance | 7/7/2014 | 7/7/2014 | 7/7/2014 | P | PASS |
Mike Jordan
|
|
|
Aaron-please go as close to 10 as possible Phone #: ###-####
|
BLD-Framing/Rough-in | 7/2/2014 | 7/3/2014 | 7/3/2014 | P | FAIL |
Mike Jordan
|
|
|
Eric Phone #: ###-####. Install additionalsquash blocking under 2ply girder truss. Install missing blocking on south shear wall. Justify missing bearing points at North A1 gable end truss. Review truss engineering for additional purlins not installed. Provide addition (2) 2x6 studs entire length of south A1 gable truss,attach to blocking and truss chords w/ 16D nails as per detail 7 A2.1. Provide web stiffmers with simpson DTC to interior wall per detail 8 A2.1. Correction notice posted.
|
BLD-Foundation | 5/6/2014 | 5/6/2014 | 5/6/2014 | P | PASS |
Tom Arcoraci
|
|
|
Rob Phone #: ###-####
|
BLD-Footing | 5/2/2014 | 5/2/2014 | 5/2/2014 | P | PASS |
Mike Jordan
|
|
|
eric Phone #: ###-####
|
Permit Ready to Issue | | | 4/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue PAID IN FULL permit | | | 4/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Bld | | | 4/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Print Occupancy Form | | | 4/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Routing Off Site - STRUCTURAL | 4/21/2014 | | 4/21/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 4/21/2014 | | 4/21/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2014 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 2/19/2014 | | 4/21/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 4/9/2014 | | 4/9/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 4/8/2014 | | 4/8/2014 | | PASS |
David Moser
|
|
|
|
Routing - PLUMBING | 4/8/2014 | | 4/8/2014 | | PASS |
Daryl Spivey
|
|
|
Provide RPBP on filtered water system.
PVC not an apprioved material for potable water inside of building as noted on note 24.
Grease intercepter not installed per public works.
|
1st review completed | | | 3/19/2014 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 2/19/2014 | | 3/19/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 2/19/2014 | | 3/19/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Environmental | 2/20/2014 | | 3/19/2014 | | PASS |
Walt Baumgartner
|
|
|
|
Routing - PLANNING | 2/19/2014 | | 3/18/2014 | | FAIL |
David Moser
|
|
|
Applicant needs to complete ROS14-00013
|
Routing - Design Review | 3/18/2014 | | 3/18/2014 | | PASS |
Josh Wilson
|
|
|
Ok per DRH14-00046
|
Routing - PLANNING Land Div | 2/19/2014 | | 2/24/2014 | | PASS |
Dave Abo
|
|
|
Lot 3, Block 2 of Calderwood West Subdivision
|
Routing PW Sewer Design | 2/20/2014 | | 2/24/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Sewer Rating | 2/20/2014 | | 2/21/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLUMBING | 2/21/2014 | | 2/21/2014 | | FAIL |
Daryl Spivey
|
|
|
Public works grease abatement not requiring a grease intercepter. Resubmit showing changes to plumbing.
|
Routing PW Solid Waste | 2/20/2014 | | 2/20/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - PUBLIC WORKS | 2/19/2014 | | 2/20/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - FIRE | 2/19/2014 | 2/19/2014 | 2/19/2014 | | PASS |
Scott Arellano
|
|
|
No report, subject to field inspection.
|
Routing - Erosion and Sediment | 2/19/2014 | | 2/19/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan and narrative submitted and approved. Valid PD and RP provided.
|
Route to Impact Fee Review | 2/19/2014 | | 2/19/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 2/19/2014 | | 2/19/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 2/13/2014 | | PASS |
|
|
|
There were problems with loading the drawing files. Only a portion of the drawings would load. The rest would be blank. After conciderable effort, the drawings appear to have loaded properly.
|
Intake Approval | | | 2/11/2014 | | FAIL |
|
|
|
The drawings evidently did not upload properly. Several drawings are blank. Other drawings appear to have had some layers turned off. Probably should delete all drawings and start over. All sheets need to be stamped and signed by the Architect or applicable Engineer. All sheets need to be oriented properly.
|
Application received | | | 2/4/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 4 2014 4:07PM
|
Pending Assignment by JCM | 2/19/2014 | | | | |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 2/20/2014 | | | | FAIL |
Brian Murphy
|
|
|
work over property line
|