Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD14-00256
StatusFinaled
Name TBL CONSTRUCTION
Site Address 1509 N 7TH ST
Project Name 
Customer Number 
ePlanReviewNo
Description
***12-29-14 This permit is modified to reflect that the bonus room area is not being finished or heated at this time and a separate permit will be required to complete the bonus room area above the garage CDM*** ***9-30-2014 THIS PERMIT IS MODIFIED TO REFLECT THE RAZING OF AN EXISTING 336 S.F. DETACHED GARAGE AND THE CONSTRUCTION OF A NEW 484 S.F. 2-CAR GARAGE WITH 308 S.F. OF HABITABLE SPACE ABOVE BY USING BONUS ROOM TRUSSES. ACCESSED BY A FULLY COMPLYING EXTERIOR STAIRWAY. ADDED VALUE $30,000.00. pep 9-26-2014 *** Permit for the construction of a 1,510 sq. ft. basement beneath an existing structure, removal of 460 sq of existing structure and the construction of a 704 sq. ft. additions as well as the interior remodel of the existing structure to include all interior and exterior finishes. All work per the approved plans and the attached engineering. THE CONTRACTOR HAS INDICATED THAT THE CURRENT HEATING SYSTEM IS TO BE UTILIZED. IF A NEW SYSTEM WITH DUCTING IS INSTALLED MANUAL J,D&S WILL BE REQUIRED PRIOR TO INSTALLATION OF THE SYSTEM. R-1CH zoning and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/29/20151/30/20151/30/2015APASS
DetailsTony Young
###-####-Tim,, bond is in place for historical window in rear of house
DOC - Permit Finaled1/30/20151/30/20151/30/2015PPASS
DetailsTony Young
c of o/c issued
BLD-Final1/29/20151/29/20151/30/2015PPART
DetailsTony Young
###-####-Tim
BLD-Final1/28/20151/29/20151/29/2015ANR
DetailsTony Young
###-####-Tim,, need historical
Zoning Approval Temp1/29/20151/29/20151/29/2015 DONE
DetailsMatthew A Halitsky
Pending approval of casement window on rear elevation.
Override - Parcel Holds  1/29/2015  
BLD-Final1/27/20151/28/20151/28/2015PNR
DetailsTony Young
###-####-Tim
BLD-Final1/26/20151/27/20151/27/2015PNR
DetailsTony Young
###-####-Tim
BLD-Conference1/26/20151/26/20151/26/2015PPEND
DetailsTony Young
###-####-Tim
BLD-Conference1/23/20151/26/20151/26/2015APEND
DetailsTony Young
###-####-Tim
BLD-Conference1/23/20151/23/20151/23/2015PPART
DetailsTony Young
###-####-Tim,, walk through for final.. needs historical final
Override - Parcel Holds  1/23/2015  
BLD-Wall cover12/29/201412/29/201412/29/2014PPASS
DetailsMike Jordan
Approve to Cover please. Call Tim with any problems.

Thank you much. Phone #: ###-#### Inspection requested via web by Timothy Beaudoin. Habitable space above garage not being competed at this time per contractor. A seperate permit is required to complete this portion. The floor of the habitable space has been insulated prior to sheet rock.
BLD-Framing/Rough-in12/26/201412/26/201412/26/2014PPASS
DetailsJim Storey
Garage. Approve to insulate

Call Tim with any questions

Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
BLD-Wall Bracing11/3/201411/4/201411/4/2014APASS
DetailsTony Young
tim Phone #: ###-####,, ok after re nailing some
CHANGE STATUS TO (ISS)  11/3/2014 DONE
DetailsTisha Gallop
OVERRIDE  10/8/2014  
Routing Walk-In (BLD)9/23/20149/23/201410/8/2014ADONE
DetailsPerry Paine
Case Summary (BLD)  10/8/2014  
Inspection Record Card- Bld  10/8/2014  
PLANS/APPL TAKEN TO FRONT DESK  10/8/2014 DONE
Permit Ready to Issue  10/8/2014 DONE
DetailsCandy A. Nichols
Telephone call  10/8/2014 DONE
DetailsCandy A. Nichols
Tisha talked to Tim and let him know his permit is ready and how much is owed
BLD-Foundation9/23/20149/24/20149/24/2014ADONE
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Footing9/23/20149/23/20149/23/2014PPEND
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron,, need permit modified
Routing Walk-In (Zoning)9/23/20149/23/20149/23/2014APASS
DetailsColleen T Carroll
BLD-Energy code compliance7/19/20147/21/20147/21/2014APART
DetailsTony Young
Tim Phone #: ###-#### Inspection requested via web by Timothy Beaudoin,, need fire blocks at entry,, then ok to cover
BLD-Framing/Rough-in7/15/20147/16/20147/16/2014APART
DetailsTony Young
Call tim Phone #: ###-#### Inspection requested via web by Timothy Beaudoin,, need roof rafter tail support,, straps,, fire blocking
BLD-Wall Bracing6/17/20146/18/20146/18/2014APART
DetailsTony Young
Tim Phone #: ###-####,, see marks,,fix,, then ok
BLD-Wall Bracing6/16/20146/17/20146/17/2014AFAIL
DetailsTony Young
Tim Phone #: ###-####,, need to do as the plan shows
Routing - MECHANICAL5/19/2014 5/19/2014 PASS
DetailsTroy James
BLD-Foundation3/19/20143/19/20143/20/2014PPART
DetailsTony Young
Pat Phone #: ###-####,, basement wall ok
BLD-Footing3/7/20143/10/20143/10/2014APEND
DetailsTony Young
late pm // Pat Phone #: ###-####,, pour called off due to the soil under the supports that are holding up the house appear to be cracking/deteriorating and with it raining it looks too dangerous to be under..
BLD-Footing3/6/20143/7/20143/7/2014PNR
DetailsTony Young
late pm // Pat Phone #: ###-####
Issue PAID IN FULL permit  2/28/2014 DONE
DetailsChristina Prado
OVERRIDE  2/7/2014  
Routing Walk-In (BLD)2/6/20142/6/20142/7/2014PPASS
DetailsCarl D Madsen
1st review completed  2/7/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  2/7/2014 DONE
Case Summary (BLD)  2/7/2014 DONE
Telephone call  2/7/2014 DONE
DetailsChristina Prado
called Tim to advise permit is ready and gave fees due
Permit Ready to Issue  2/7/2014 DONE
DetailsChristina Prado
Inspection Record Card- Bld  2/7/2014 DONE
DetailsChristina Prado
Routing Walk-In (Zoning)2/6/20142/6/20142/6/2014PPASS
DetailsMatthew A Halitsky
Application received 2/6/2014