Print Statement | | | 7/11/2014 | | DONE |
Christina Prado
|
|
|
|
Second Notice | | 6/20/2014 | 7/9/2014 | | DONE |
|
|
|
|
First Notice | | 5/23/2014 | 6/10/2014 | | DONE |
|
|
|
Faxed 6-10-14
|
Permanent Occupancy | | | 5/13/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 5/12/2014 | 5/12/2014 | 5/12/2014 | P | PASS |
Mike Jordan
|
|
|
Odie Phone #: ###-####. ok for perm. occ.
|
FIRE-Final Inspection | 5/7/2014 | 5/8/2014 | 5/9/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
Issue & PRINT permit | | | 5/8/2014 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/7/2014 | 4/8/2014 | 4/8/2014 | A | PASS |
Tom Arcoraci
|
|
|
Odie Phone #: ###-####
|
Routing - PLAN CHECK | 4/4/2014 | | 4/8/2014 | | PASS |
Carl Westfall
|
|
|
Reviewed the structural analysis of the roof and its ability to support the addedd roof top HVAC units. Added "red lines" to a drawing within structural calculations.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/4/2014 | | DONE |
|
|
|
Deferred submittal received for the roof structure analysis
|
Issue PAID IN FULL permit | | | 3/31/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 3/31/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 3/28/2014 | | |
|
|
|
|
Plan assigned to (CJW) | 2/18/2014 | 2/18/2014 | 3/28/2014 | | PASS |
Carl Westfall
|
|
|
CRAIG STEIN BEVERAGE - Level 3 TI - ePlanReview (20 days - March 13)
|
Routing - PLAN CHECK | 3/26/2014 | | 3/28/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines".
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/28/2014 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 3/26/2014 | | DONE |
|
|
|
|
Routing Off Site - C.D.H | | | 3/26/2014 | | PASS |
|
|
|
Not routed the 1st time. Waiting to determine for sure whether it is a regulated facility.
(3-26-14) According to Tammie McCarter, this facility is not regulated by CDHD.
|
Telephone call | | | 3/14/2014 | | DONE |
|
|
|
Left a message for Wes Steele. Asked for status update.
|
1st review completed | | | 3/3/2014 | | DONE |
|
|
|
Failed Building
|
Plan resubmittals requested | | | 3/3/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/18/2014 | | 3/3/2014 | | FAIL |
Carl Westfall
|
|
|
Resubmittals required
|
Routing - FIRE | 2/18/2014 | 2/18/2014 | 2/28/2014 | | PASS |
Scott Arellano
|
|
|
See attached Review
|
Routing PW Sewer Rating | 2/20/2014 | | 2/20/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 2/20/2014 | | 2/20/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 2/18/2014 | | 2/19/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver submitted and approved. Steed Construction needs to designate an RP for project.
|
Pending Assignment by JCB | 2/18/2014 | | 2/18/2014 | | DONE |
Jason Blais
|
|
|
|
Routing - PUBLIC WORKS | 2/18/2014 | | 2/18/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - Addressing | 2/18/2014 | | 2/18/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 2/14/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen and plan review fees paid.
|
Application received | | | 2/12/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 12 2014 11:40AM
|