First Notice | | 5/4/2014 | 4/30/2014 | | DONE |
Christina Prado
|
|
|
completed 4-30-14
|
Print Statement | | | 4/30/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/24/2014 | 4/24/2014 | 4/24/2014 | P | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 4/24/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/22/2014 | 4/23/2014 | 4/23/2014 | P | FAIL |
Mike Jordan
|
|
|
call 1/2 hr before // Mike Phone #: ###-####. Provide ada compliant lav, provide transitions at doorways from concrete to tile.
|
FIRE-Final Inspection | 4/22/2014 | 4/23/2014 | 4/23/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
FIRE-Final Inspection | 4/14/2014 | 4/15/2014 | 4/15/2014 | A | CANC |
Troy Cobbley
|
|
|
Per mike project is not ready
|
FIRE-Conference | 4/4/2014 | 4/7/2014 | 4/7/2014 | A | DONE |
Craig D. Hanson
|
|
|
|
BLD-Framing/Rough-in | 3/28/2014 | 3/31/2014 | 3/31/2014 | P | PASS |
Jim Sly
|
|
|
Mike-Ceiling grid inspection please Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/27/2014 | 3/28/2014 | 3/28/2014 | P | NR |
Mike Jordan
|
|
|
mike Phone #: ###-####. No approved plans on site. Needs electrical rough inspection.
|
Place hold on job | 3/5/2014 | | 3/10/2014 | | DONE |
Tisha Gallop
|
|
|
must issue Bld14-00496 with this permit
|
Permit Ready to Issue | | | 3/10/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 3/10/2014 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 3/10/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (AJS) | 2/21/2014 | 2/21/2014 | 3/5/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 3/7 Florida Tile
|
Routing - PLAN CHECK | 3/5/2014 | | 3/5/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2014 | | DONE |
|
|
|
|
Routing - FIRE | 2/21/2014 | 2/21/2014 | 3/4/2014 | | PASS |
Craig D. Hanson
|
|
|
See attached Fire Plan Review
|
1st review completed | | | 3/4/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 2/21/2014 | | 3/4/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PUBLIC WORKS | 2/21/2014 | | 2/24/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 2/24/2014 | | 2/24/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 2/21/2014 | | 2/21/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 2/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 2/12/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 12 2014 11:43AM
|