Permit Information
Permit NumberBLD14-00359
StatusFinaled
Name BRUNO BUILT INC
Site Address 1751 S TOLUKA WAY
Project NameMiller Residence
Customer Number 
ePlanReviewYes
Description
WUI Zone A, Class A Roof, Permit for the construction of a new 3502 sq. ft., two story (first story 2580 sq. ft., second story 922 sq. ft.) single family dwelling with 5 bedrooms, 3 full and 2 half bathrooms, approximately 1353 sq. ft. of covered patio/porch and a 952 sq. ft. attached garage per the approved plans, Rescheck, plan review report and any notations. R-1A/DA zoning and setbacks per planning. JG A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  11/2/2015 DONE
Case Summary (BLD)  11/2/2015 DONE
Case Summary (BLD)  10/29/2015 DONE
BLD-Final12/1/201412/1/201412/1/2014PPASS
DetailsDave Hannah
please call ahead so can meet the inspector there... Jeremy Phone #: ###-####
DOC - Permit Finaled12/1/201412/1/201412/1/2014PPASS
DetailsDave Hannah
BLD-Final11/28/201411/28/201412/1/2014PNR
DetailsJim Storey
45 min call before// Jeremy Phone #: ###-#### no pw sign off
PubWorks Occupancy Approval12/1/201412/1/201412/1/2014 DONE
DetailsJason C. Taylor
Bond in place. Occupancy may be given by Building Department. Jason Taylor ###-####.
BLD-Energy code compliance8/20/20148/21/20148/21/2014APASS
DetailsPhil Shearer
Jeremy Phone #: ###-####
BLD-Framing/Rough-in8/14/20148/15/20148/15/2014PPASS
DetailsPhil Shearer
robert Phone #: ###-####
BLD-Framing/Rough-in8/13/20148/14/20148/14/2014AFAIL
DetailsPhil Shearer
Jeremy Phone #: ###-####
CN written
BLD-Wall Bracing8/11/20148/12/20148/12/2014APASS
DetailsPhil Shearer
Jeremy Phone #: ###-####
Plan Modification Accepted  8/8/2014 DONE
new manual j
Routing - MECHANICAL8/8/2014 8/8/2014 PASS
DetailsTroy James
resubmitted manual j
BLD-Wall Bracing7/11/20147/11/20147/11/2014PPART
DetailsJim Sly
Jeremy Phone #: ###-####
C/N posted.......Missing 2 HD's Marked on Plan.
BLD-Foundation5/8/20145/8/20145/8/2014PPASS
DetailsDave Hannah
Ben Phone #: ###-####
BLD-Footing4/30/20144/30/20144/30/2014APASS
DetailsDave Hannah
Ben Phone #: ###-####
BLD-Footing4/29/20144/29/20144/30/2014PNR
DetailsDave Hannah
Ben Phone #: ###-####
BLD-Footing4/29/20144/29/20144/29/2014ANR
DetailsJim Storey
Ben Phone #: ###-####
BLD-Footing4/28/20144/28/20144/29/2014PNR
DetailsDave Hannah
Ben Phone #: ###-####
PubWorks Subgrade Approval4/21/20144/21/20144/21/2014 DONE
DetailsJason C. Taylor
*NOTE WEST SIDE FOOTING ONLY (See subgrade report for details)* A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
PubWorks Subgrade Approval4/21/20144/21/20144/21/2014 DONE
DetailsJason C. Taylor
* NOTE ALL FOOTINGS FOR RESIDENCE, GARAGE, AND RETAINING WALLS* A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Issue PAID IN FULL permit  4/8/2014 DONE
Inspection Record Card- Bld  4/8/2014 DONE
OVERRIDE  4/7/2014  
Permit Ready to Issue  4/7/2014 DONE
DetailsChristina Prado
Plan assigned to (JG)3/17/20143/17/20144/4/2014 PASS
DetailsJavier Guzman
1st review completed, Due 4/03 L2 Hillside ePlan**
Routing - PLAN CHECK3/26/2014 4/4/2014 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  4/4/2014 DONE
1st review completed  3/26/2014 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK3/17/2014 3/26/2014 FAIL
DetailsJavier Guzman
ePlan review
Route to Impact Fee Review3/17/20143/20/20143/18/2014 PASS
DetailsCindy M. Gould
Sys. assessed fees.
Routing - FIRE3/17/20143/17/20143/18/2014 PASS
DetailsScott Arellano
No comments attached.
Routing PW Grading-Hillside3/17/2014 3/18/2014 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Routing - MECHANICAL3/17/2014 3/18/2014 PASS
DetailsTroy James
Routing - PLANNING3/17/2014 3/17/2014 PASS
DetailsJoshua Johnson
Routing - Addressing3/17/2014 3/17/2014 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS3/17/2014 3/17/2014 PASS
DetailsBeverly Mountain
Routing - Erosion and Sediment3/17/2014 3/17/2014 PASS
DetailsEvan Jenkins
Plans ACCEPTED BY PLAN TECH  3/17/2014 DONE
DetailsChristina Prado
Intake Approval  3/17/2014 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  3/17/2014 DONE
DetailsChristina Prado
Intake Approval  3/12/2014 FAIL
DetailsBarbara Stitt
P& Z appeal period is not up till 3/14/14....BAS
Application received  2/18/2014 DONE
Application submitted via PDS Online on Feb 18 2014 1:12PM