Third Notice | | 9/3/2014 | 9/12/2014 | | DONE |
Christina Prado
|
|
|
completed 9-12-14
|
Third Notice | | 7/14/2014 | 8/29/2014 | | DONE |
|
|
|
mailed to Precision Exhaust
|
Second Notice | | 6/21/2014 | 7/9/2014 | | DONE |
|
|
|
|
First Notice | | 5/17/2014 | 6/11/2014 | | DONE |
|
|
|
Faxed 6-11-14
|
Permanent Occupancy | | | 5/7/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 5/5/2014 | 5/6/2014 | 5/6/2014 | A | PASS |
Tom Arcoraci
|
|
|
john Phone #: ###-####
|
FIRE-Final Inspection | 5/6/2014 | 5/6/2014 | 5/6/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 5/2/2014 | 5/5/2014 | 5/5/2014 | P | NR |
Mike Jordan
|
|
|
John Phone #: ###-####
|
FIRE-Final Inspection | 5/5/2014 | 5/5/2014 | 5/5/2014 | P | FAIL |
Craig D. Hanson
|
|
|
1. Range not in correct position yet. 2. Extinguishers not mounted 3. Sprinkler head obstructed
|
BLD-Framing/Rough-in | 5/2/2014 | 5/2/2014 | 5/2/2014 | P | CANC |
Mike Jordan
|
|
|
John-Above ceiling Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/2/2014 | 5/2/2014 | 5/2/2014 | P | PASS |
Mike Jordan
|
|
|
John-Above ceiling Phone #: ###-####
|
BLD-Other | 5/1/2014 | 5/1/2014 | 5/1/2014 | P | FAIL |
Mike Jordan
|
|
|
As late as possible please--Above ceiling mechanical inspection please--ROB Phone #: ###-####. No clips installed, electrical inspection above grid not completed.
|
BLD-Wall cover | 4/3/2014 | 4/4/2014 | 4/4/2014 | A | PASS |
Mike Jordan
|
|
|
please inspect framing Phone #: ###-#### >> Inspection requested via web by Roberts John
|
BLD-Framing/Rough-in | 4/3/2014 | 4/4/2014 | 4/4/2014 | A | PASS |
Mike Jordan
|
|
|
please inspect framing Phone #: ###-#### >> Inspection requested via web by Roberts John
|
Print Occupancy Form | | | 3/20/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 3/20/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 3/20/2014 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/19/2014 | | 3/19/2014 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 3/19/2014 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 3/12/2014 | | 3/19/2014 | | PASS |
Tim L. Woodard
|
|
|
oishii Japan (MALL)
|
Routing - PLAN CHECK | 3/12/2014 | | 3/19/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLUMBING | 3/12/2014 | | 3/13/2014 | | PASS |
Daryl Spivey
|
|
|
RPBP required on cabonated beverage dispenser.
|
Routing - Addressing | 3/12/2014 | | 3/12/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 3/12/2014 | | 3/12/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - MECHANICAL | 3/12/2014 | | 3/12/2014 | | FAIL |
Troy James
|
|
|
eplan see changemarks
|
Routing PW Sewer Rating | 3/12/2014 | | 3/12/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 3/12/2014 | | 3/12/2014 | | PASS |
Walt Baumgartner
|
|
|
food court area tenants on common GI for complex, WBSD
|
Intake Approval | | | 3/12/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 2/25/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Please complete and upload the approval letter form the mall for this renovation.
2. Please complete and upload the 304 form.
3. Please complete and upload the 518 checklist.
4. Please re upload the sheets to read left to right.
5. Please re label the sheet names to meet the conventional naming as shown in the submittal standards.
6. Please provide the required stamping area shown on the submittal standards.
7. Please upload the Central District Health Department approval or application.
8. Please have all sheets shamped. The mechanical hood requires a mechanical engineer stamp the mechancial design.
Once this information is recieved I will begin the pre screen.
Thank you
|
Intake Approval | | | 2/25/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
2/25/14 3:23 pm recieved back for pre screen with none of the items listed below completed. sent back to applicant. Will need all items addressed prior to begining pre screen. Please contact Alex at ###-#### if you have e plan questions. Thank you
1. Please complete and upload the approval letter form the mall for this renovation.
2. Please complete and upload the 304 form.
3. Please complete and upload the 518 checklist.
4. Please re upload the sheets to read left to right.
5. Please re label the sheet names to meet the conventional naming as shown in the submittal standards.
6. Please provide the required stamping area shown on the submittal standards.
7. Please upload the Central District Health Department approval or application.
8. Please have all sheets shamped. The mechanical hood requires a mechanical engineer stamp the mechancial design.
Once this information is recieved I will begin the pre screen.
Thank you
|
Application received | | | 2/20/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 20 2014 6:38PM
|