Second Notice | | 9/6/2014 | 9/8/2014 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 7/20/2014 | 8/27/2014 | | DONE |
|
|
|
|
BLD-Final | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | PASS |
Dave Hannah
|
|
|
call before to meet // Renny Phone #: ###-####
|
Permanent Occupancy | | | 7/10/2014 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 7/8/2014 | 7/9/2014 | 7/9/2014 | A | PASS |
Craig D. Hanson
|
|
|
building and spray booth pass. Spray booth was inspected for all iFC related requirements. Electrical and mechanical inspections for spray booth completed by related trades.
|
FIRE-Final Inspection | 7/7/2014 | 7/8/2014 | 7/8/2014 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for a final yet. Renny and I discussed general life safety requirements and walked the job.
|
Zoning Approval | 6/18/2014 | 6/18/2014 | 6/18/2014 | | PASS |
Sarah Schafer
|
|
|
|
Zoning Approval | 6/11/2014 | 6/11/2014 | 6/11/2014 | | PASS |
Sarah Schafer
|
|
|
|
OVERRIDE | | | 6/5/2014 | | |
|
|
|
|
BLD-Concrete | 5/14/2014 | 5/15/2014 | 5/15/2014 | P | PASS |
Mike Jordan
|
|
|
Jon Phone #: ###-####
|
Plan assigned to (AJS) | 5/1/2014 | 5/1/2014 | 5/7/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
deferred submittal for paint booth
|
Routing - PLAN CHECK | 5/1/2014 | | 5/7/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
paint booth deferred submittal
|
CHANGE STATUS TO (ISS) | | | 5/7/2014 | | DONE |
Tisha Gallop
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/7/2014 | | DONE |
Tisha Gallop
|
|
|
deferred submittal for paint booth approved and batch stamped, no fees due.
|
Routing - FIRE | 5/1/2014 | 5/1/2014 | 5/6/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 Mod 05-06-14
|
Issue PAID IN FULL permit | | | 5/2/2014 | | DONE |
Tisha Gallop
|
|
|
issued permit for scope of work not including plan mod(paint booth)
|
Print Occupancy Form | | | 5/2/2014 | | DONE |
Tisha Gallop
|
|
|
|
CHANGE STATUS TO (REV) | | | 5/2/2014 | | DONE |
Tisha Gallop
|
|
|
change status back to REV for plan mod in process
|
Routing - MECHANICAL | 5/1/2014 | | 5/1/2014 | | PASS |
Troy James
|
|
|
|
Plan assigned to (AJS) | 3/7/2014 | 3/7/2014 | 4/25/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 3/20 First Choice collision repair
|
Routing - FIRE | 4/21/2014 | | 4/25/2014 | | PASS |
Craig D. Hanson
|
|
|
Spray Booth to be a Plan Modification. See Frie Plan Review Rev 1 04-25-14
|
Telephone call | | | 4/25/2014 | | DONE |
|
|
|
Call with Jerrod Wallgreen explaining that spray booth can be a plan mod
|
Routing - PLAN CHECK | 4/25/2014 | | 4/25/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/25/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Erosion and Sediment | 4/21/2014 | | 4/22/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection and Approval needs to occur prior to any Earth Disturbance
|
Routing - PLAN CHECK | 4/15/2014 | | 4/21/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLUMBING | 4/15/2014 | | 4/16/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 4/15/2014 | | 4/16/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 3/7/2014 | | 3/20/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please see change marks in e plan
|
Routing - PLANNING | 3/7/2014 | | 3/20/2014 | | PASS |
Cody Riddle
|
|
|
|
1st review completed | | | 3/20/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Erosion and Sediment | 3/7/2014 | | 3/17/2014 | | PASS |
Evan Jenkins
|
|
|
Approved: Site Prep Inspection and Approval needed prior to any Earth Disturbance
|
Routing - Design Review | 3/7/2014 | | 3/17/2014 | | PASS |
Sarah Schafer
|
|
|
signed off in e plan
|
Routing - FIRE | 3/7/2014 | 3/7/2014 | 3/12/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Report 03-12-14. Resubmittal items communicated through e-plan review with architect.
|
Routing - PLUMBING | 3/10/2014 | | 3/12/2014 | | FAIL |
Daryl Spivey
|
|
|
Install flammable liquids interceptor per approved sent attachment to architect and vent tank seperately.
|
Routing - MECHANICAL | 3/7/2014 | | 3/10/2014 | | FAIL |
Troy James
|
|
|
eplan
|
Routing - Addressing | 3/7/2014 | | 3/7/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 3/7/2014 | | 3/7/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 3/7/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Environmental | 3/7/2014 | | 3/7/2014 | | PASS |
Walt Baumgartner
|
|
|
1000 gal vault ok, utilize approved design flammable vented headspace vault per plumbing code
|
Routing PW Sewer Rating | 3/7/2014 | | 3/7/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 3/5/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please re upload the drawings individualy.
Thank you
|
Application received | | | 2/28/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 28 2014 10:10AM
|