Third Notice | | 1/7/2015 | 1/13/2015 | | DONE |
|
|
|
This permit finaled on the web by Michael Frazier
|
Third Notice | | 12/6/2014 | 1/2/2015 | | DONE |
|
|
|
sent with letter
|
Third Notice | | 11/15/2014 | 12/1/2014 | | DONE |
|
|
|
|
Third Notice | | 10/11/2014 | 11/10/2014 | | DONE |
|
|
|
mailed
|
Second Notice | | 9/5/2014 | 10/6/2014 | | DONE |
Candy A. Nichols
|
|
|
sent in mail 10-6-14
|
First Notice | | 7/11/2014 | 8/26/2014 | | DONE |
|
|
|
|
BLD-Final | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Mike Jordan
|
|
|
or ###-#### Scott Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Permanent Occupancy | | | 7/1/2014 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | PART |
Troy Cobbley
|
|
|
Life safety in phase 2 and 3 passed.
|
BLD-Framing/Rough-in | 6/12/2014 | 6/13/2014 | 6/13/2014 | P | PASS |
Mike Jordan
|
|
|
Ceiling cover inspection-Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 6/5/2014 | 6/5/2014 | 6/5/2014 | P | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####. Interior steel stud walls only ok, phase 2.
|
BLD-Final | 5/15/2014 | 5/16/2014 | 5/16/2014 | A | PART |
Mike Jordan
|
|
|
. ok to occupy east portion of tje tenant improvement while the existing portion is being remodeled.
|
FIRE-Final Inspection | 5/15/2014 | 5/16/2014 | 5/16/2014 | A | PART |
Troy Cobbley
|
|
|
See the city approved plans for Phase I location where life safety is complete. Panic hardware is to be installed on front door per the door schedule prior to final sign off of whole project. Scott #: ###-####
|
BLD-Final | 5/15/2014 | 5/15/2014 | 5/15/2014 | P | NR |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 5/14/2014 | 5/15/2014 | 5/15/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per scott Phone #: ###-####
|
BLD-Final | 5/14/2014 | 5/15/2014 | 5/15/2014 | A | CANC |
Mike Jordan
|
|
|
scott Phone #: ###-####. Moved to pm.
|
FIRE-Conference | 5/14/2014 | 5/14/2014 | 5/14/2014 | P | DONE |
Troy Cobbley
|
|
|
Went over life safety requirements with Scott. I agreed that since the doors are not here yet if case work was installed I would be ok with a pass on life safety in this phase of work.
|
BLD-Final | 5/13/2014 | 5/14/2014 | 5/14/2014 | P | CANC |
Mike Jordan
|
|
|
Scott Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/14/2014 | 5/14/2014 | 5/14/2014 | P | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 4/24/2014 | 4/25/2014 | 4/25/2014 | P | PASS |
Mike Jordan
|
|
|
scott Phone #: ###-####. Interior steel stud walls, no grid at phase 1 (1500s.f. addition into adjacent tenant space).
|
Issue PAID IN FULL permit | | | 4/15/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 3/19/2014 | | |
|
|
|
|
Telephone call | | | 3/19/2014 | | DONE |
Christina Prado
|
|
|
called Cortland to advise permit is ready pending GC & RP, also gave fees due
|
Permit Ready to Issue | | | 3/19/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 3/4/2014 | | 3/18/2014 | | PASS |
Tim L. Woodard
|
|
|
Eyemart Express
|
Routing - PLAN CHECK | 3/5/2014 | | 3/18/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - Erosion and Sediment | 3/18/2014 | | 3/18/2014 | | PASS |
Tim L. Woodard
|
|
|
Waiver Approved. TLW
|
1st review completed | | | 3/18/2014 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 3/18/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 3/18/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 3/4/2014 | | 3/5/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 3/4/2014 | | 3/5/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 3/5/2014 | | 3/5/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 3/4/2014 | 3/4/2014 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/4/2014 | | DONE |
Tisha Gallop
|
|
|
|