CHANGE ISSUED DATE | | | 4/22/2015 | | DONE |
Jason Blais
|
|
|
|
Print Statement | | | 11/24/2014 | | DONE |
Christina Prado
|
|
|
|
Print Statement | | | 9/24/2014 | | DONE |
Christina Prado
|
|
|
|
Second Notice | | 9/5/2014 | 9/23/2014 | | DONE |
Christina Prado
|
|
|
Completed 9-23-14
|
Print Statement | | | 9/23/2014 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 7/19/2014 | 8/26/2014 | | DONE |
|
|
|
|
BLD-Final | 7/8/2014 | 7/9/2014 | 7/9/2014 | A | PASS |
Tony Young
|
|
|
Colby Phone #: ###-####
|
Permanent Occupancy | | | 7/9/2014 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 7/2/2014 | 7/3/2014 | 7/3/2014 | P | FAIL |
Mike Jordan
|
|
|
MIke Phone #: ###-####. Remove keyed locks and thumb tirns on interior glass doors downstairs. Remove thumb turn from upstairs exit and provide egress type hardware. Lower conduit fromrear confreance room exit. Correction notice issued.
|
FIRE-Final Inspection | 7/2/2014 | 7/3/2014 | 7/3/2014 | A | PASS |
Craig D. Hanson
|
|
|
Pass
|
Zoning Approval | 7/2/2014 | 7/2/2014 | 7/2/2014 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Framing/Rough-in | 6/10/2014 | 6/11/2014 | 6/11/2014 | A | PASS |
Tony Young
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 6/9/2014 | 6/10/2014 | 6/10/2014 | P | PART |
Tony Young
|
|
|
Mike Phone #: ###-####,, need fire blocks,, plumbing pass
|
BLD-Footing | 5/28/2014 | 5/28/2014 | 5/28/2014 | P | PART |
Tony Young
|
|
|
Rebar - Mike Phone #: ###-####
|
BLD-Footing | 5/27/2014 | 5/27/2014 | 5/28/2014 | P | PEND |
Tony Young
|
|
|
Rebar - Mike Phone #: ###-####.. ok pending special inspection report
|
CHANGE STATUS TO (ISS) | | | 5/20/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan Modification Accepted | | | 5/16/2014 | | DONE |
Candy A. Nichols
|
|
|
started workflow (struc beans new confr room)
|
Plan Modification Accepted | | | 5/16/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 5/16/2014 | | 5/16/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
structural plan modifications
|
Print Occupancy Form | | | 5/2/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 4/22/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue PAID IN FULL permit | | | 4/22/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Print Occupancy Form | | | 4/22/2014 | | DONE |
Candy A. Nichols
|
|
|
|
CHANGE STATUS TO (FEE) | | | 4/22/2014 | | DONE |
Candy A. Nichols
|
|
|
Issued by mistake
|
Plan assigned to (AJS) | 3/11/2014 | 3/11/2014 | 4/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 3/24 LHTAC TI
|
Routing - PLAN CHECK | 4/21/2014 | | 4/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/11/2014 | | 3/25/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
1st review completed | | | 3/25/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Design Review | 3/11/2014 | | 3/12/2014 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PUBLIC WORKS | 3/11/2014 | | 3/11/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 3/11/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Sewer Rating | 3/11/2014 | | 3/11/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 3/11/2014 | | 3/11/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 3/5/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
This structure is located in Zone C-2D. Any changes made to the exterior even minor changes must have planning approval. Please contact Sara Schafer at ###-#### if you have questions. Thank you
|
Application received | | | 3/4/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 4 2014 1:21PM
|