Permit Information
Permit NumberBLD14-00490
StatusFinaled
Name STRUCTRUAL INTEGRITY
Site Address 416 S 9TH ST Unit: 106
Project NameThe Knitting Factory Mezzanine
Customer Number 
ePlanReviewNo
Description
(THE KNITTING FACTORY - MEZZANINE ADDITION) Fire sprinklers used for story and area increases. To expand the existing 1,712 square foot mezzanine by 180 square feet to a total area of 1,892 square feet. Work is to include a floor system constructed of steel beams, wood joists, 1-1/8” structural floor sheathing, and threaded rods and clevises. A 4 riser stairway with handrails and 42 inch high guards will also be constructed. Special inspection is required for welding and bolting. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The total occupant load of this tenant space is not allowed to exceed 999 or the occupant load established by previously approved occupancy scenarios. The maximum occupant load of the mezzanine shall be maintained at 192. The existing exit signs and emergency light fixtures are required to be maintained. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/2/201410/6/2014 DONE
mailed to Structural Integrity
Second Notice 7/27/20148/28/2014 DONE
First Notice7/1/20147/1/20147/17/2014 DONE
DetailsDave Hannah
Mailed 7-17-14
BLD-Conference7/1/20147/1/20147/1/2014APASS
DetailsDave Hannah
DOC - Permit Finaled7/1/20147/1/20147/1/2014APASS
DetailsDave Hannah
BLD-Final4/11/20144/11/20144/11/2014PPASS
DetailsDave Hannah
Please call to coordinate inspection time. Final fire inspection scheduled for today as well.

Thanks, Phone #: ###-#### >> Inspection requested via web by Chris Palmer
FIRE-Final Inspection4/11/20144/11/20144/11/2014PPASS
DetailsTroy Cobbley
Life safety passed. It appears the115cd fire alarm strobe on the north wall will provide coverage for this new area.
BLD-Framing/Rough-in4/4/20144/4/20144/6/2014PPASS
DetailsDave Hannah
New balcony joist framing above existing lower bar. Drawings are on the bar top. Please call with any questions. Thank You. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Framing/Rough-in4/3/20144/4/20144/4/2014ACANC
DetailsDave Hannah
Joist framing at new sound control booth. Plans and permit located on bar top. Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
Permit Ready to Issue  4/1/2014 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  4/1/2014 DONE
DetailsTisha Gallop
Plan assigned to (CJW)3/5/20143/5/20143/28/2014 PASS
DetailsCarl Westfall
THE KNITTING FACTORY - MEZZANINE EXPANSION - Level 3 TI - (20 days - Mar 31)
Routing - PLAN CHECK3/27/2014 3/28/2014 PASS
DetailsCarl Westfall
Drawings approved
Routing Off Site - STRUCTURAL3/27/2014 3/28/2014 PASS
DetailsCarl Westfall
(3-27-14) Emailed Supplemental Structural Calculations to the Consultant Structural Engineer for his review.

(3-28-14) Approved by the consultant structural engineer.
PLANS/APPL TAKEN TO FRONT DESK  3/28/2014 DONE
Print Occupancy Form  3/28/2014 DONE
DetailsTisha Gallop
Telephone call  3/28/2014 DONE
DetailsBarbara Stitt
Called and left a voice mesage for Scott that the permit is ready & fees due on 3/28/14 @ 4:22pm///BAS
Plan resubmittals received  3/27/2014 DONE
DetailsChristina Prado
Received two sets of revised plan sheets marked G102, two revised calcs as well as one transmittal;Taken back to Carl Westfall for review
Routing Off Site - STRUCTURAL3/21/2014 3/26/2014 FAIL
DetailsCarl Westfall
Emailed the plan review report to the Architect.
1st review completed  3/26/2014 FAIL
Failed; Plan Check
Routing - PLAN CHECK3/24/2014 3/26/2014 DONE
DetailsCarl Westfall
Structural review completed. Structural analysis of existing columns required.
Plan resubmittals requested  3/26/2014 DONE
Route to Impact Fee Review3/22/20143/27/20143/25/2014 PASS
DetailsCindy M. Gould
Tenant improvement
Routing - FIRE3/22/2014 3/24/2014 PASS
DetailsCraig D. Hanson
See IFC review 03-24-14
Routing - PLAN CHECK3/5/2014 3/22/2014 FAIL
DetailsCarl Westfall
Revised drawings required
Plan resubmittals received  3/21/2014 DONE
DetailsTisha Gallop
received third set of structural calcs and plan sheets G101, G102, S101; taken to Carl Westfall.
Telephone call  3/21/2014 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Pending Assignment by JCB3/4/2014 3/5/2014 DONE
DetailsJason Blais
Plans ACCEPTED BY PLAN TECH  3/4/2014 DONE
DetailsChristina Prado
Intake Approval  3/4/2014 PASS
DetailsAdele J Schaffeld-Griffin
Recd Pcfee & Taken To Pln CK  3/4/2014 DONE
DetailsChristina Prado
Application received 3/4/2014