BLD-Final | 4/14/2015 | 4/15/2015 | 4/15/2015 | A | PASS |
Dave Hannah
|
|
|
Clive Phone #: ###-####-please call 30 minutes prior
|
DOC - Permit Finaled | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 4/7/2015 | 4/7/2015 | 4/8/2015 | P | PEND |
Dave Hannah
|
|
|
Clive Phone #: ###-#### needs temp glassing at stairs and rest rooms fix windows to stop at 4" work out room energy cert on elec pannel
|
BLD-Final | 4/6/2015 | 4/7/2015 | 4/7/2015 | A | CANC |
Dave Hannah
|
|
|
Clive// please call before Phone #: ###-####
|
BLD-Final | 4/3/2015 | 4/6/2015 | 4/6/2015 | A | NR |
Phil Shearer
|
|
|
Clive-please call 1 hr prior to meet for access Phone #: ###-####
|
PubWorks Occupancy Approval | 4/3/2015 | 4/3/2015 | 4/3/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | PASS |
Dave Hannah
|
|
|
Clive Phone #: ###-####
|
BLD-Framing/Rough-in | 11/24/2014 | 11/25/2014 | 11/25/2014 | P | PASS |
Dave Hannah
|
|
|
Clive Phone #: ###-####
|
BLD-Framing/Rough-in | 11/21/2014 | 11/24/2014 | 11/24/2014 | P | CANC |
Dave Hannah
|
|
|
Clive Phone #: ###-####
|
BLD-Other | 11/19/2014 | 11/20/2014 | 11/20/2014 | P | PASS |
Dave Hannah
|
|
|
Air seal - Clive Phone #: ###-####
|
Routing - MECHANICAL | 11/13/2014 | | 11/13/2014 | | PASS |
Troy James
|
|
|
|
BLD-Wall Bracing | 10/10/2014 | 10/10/2014 | 10/10/2014 | P | PASS |
Dave Hannah
|
|
|
Clive Phone #: ###-####
|
BLD-Footing | 9/2/2014 | 9/2/2014 | 9/2/2014 | P | PASS |
Dave Hannah
|
|
|
PAT Phone #: ###-####
|
PubWorks Subgrade Approval | 9/2/2014 | 9/2/2014 | 9/2/2014 | | DONE |
Jason C. Taylor
|
|
|
* FOOTINGS ONLY ***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 8/27/2014 | 8/28/2014 | 8/28/2014 | P | CANC |
Dave Hannah
|
|
|
Pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/19/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 8/19/2014 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 8/8/2014 | 8/29/2014 | 8/8/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 6/18/2014 | | |
|
|
|
|
Plan assigned to (JG) | 4/2/2014 | 4/2/2014 | 6/18/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, Due 4/18 L2 Hillside ePlan**
|
Routing - PLAN CHECK | 6/17/2014 | | 6/18/2014 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/18/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 4/28/2014 | | 5/21/2014 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing PW Grading-Hillside | 5/21/2014 | | 5/21/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLAN CHECK | 4/17/2014 | | 4/28/2014 | | FAIL |
Javier Guzman
|
|
|
previous corrections not made
|
1st review completed | | | 4/17/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 4/2/2014 | | 4/17/2014 | | FAIL |
Javier Guzman
|
|
|
ePlan review
|
Route to Impact Fee Review | 4/2/2014 | 4/5/2014 | 4/7/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 4/2/2014 | 4/2/2014 | 4/7/2014 | | PASS |
Scott Arellano
|
|
|
No comments. Approved as shown.
|
Routing PW Grading-Hillside | 4/2/2014 | | 4/4/2014 | | FAIL |
Jason C. Taylor
|
|
|
Applicant needs to submit a shallow injection well application per IDWR requirements. House application cannot be approved until retaining walls application has been approved. Jason Taylor ###-####.
|
Recd Pcfee & Taken To Pln CK | | | 4/2/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 4/2/2014 | | 4/2/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/2/2014 | | 4/2/2014 | | PASS |
Leon Letson
|
|
|
|
Routing - Addressing | 4/2/2014 | | 4/2/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 4/2/2014 | | 4/2/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 4/2/2014 | | 4/2/2014 | | PASS |
Andy J. Long
|
|
|
Valid ESC plan submitted and approved. RP and PD for project have been designated.
|
Plans ACCEPTED BY PLAN TECH | | | 4/2/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 4/1/2014 | | PASS |
Tisha Gallop
|
|
|
|
Intake Approval | | | 3/27/2014 | | FAIL |
Christina Prado
|
|
|
Need to seperate plan sheets, enlarge two engineered mark up sheets, upload stamped foundation sheet and show CO detectors
|
Application received | | | 3/7/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 7 2014 12:19PM
|