Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD14-00532
StatusFinaled
Name INTERIOR SYSTEMS INC
Site Address 7210 W BARRISTER DR
Project NameAda Co Jail Pod D Ceiling Mod
Customer Number 
ePlanReviewYes
Description
(ADA COUNTY JAIL - POD D-Dayroom) This permit is to replace a portion of the suspended ceiling system with suspended gypsum board per the approved plans. Scope of work to include minor mechanical, electrical and fire sprinkler adjustments for new ceiling. The suspended ceiling was installed under BLD11-03019. The fire sprinkler system is required because this building is an I-3 Occupancy. The work is required to comply with the approved drawings, with the specifications, and with all applicable codes and ordinances. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 5/17/20146/5/2014 DONE
This permit finaled on the web by Tammy Worwood
First Notice4/14/20144/14/20145/7/2014 DONE
DetailsTom Arcoraci
Mailed 5-7-14
BLD-Final4/14/20144/14/20144/14/2014PPASS
DetailsTom Arcoraci
DOC - Permit Finaled4/14/20144/14/20144/14/2014PPASS
DetailsTom Arcoraci
FIRE-Final Inspection4/14/20144/14/20144/14/2014PPASS
DetailsTroy Cobbley
life safety passed
BLD-Framing/Rough-in4/4/20144/7/20144/7/2014APASS
DetailsTom Arcoraci
Herb Stywig or ###-#### or ###-#### Mickey Phone #: ###-####
Issue PAID IN FULL permit  3/27/2014 DONE
DetailsTisha Gallop
Inspection Record Card- Bld  3/27/2014 DONE
DetailsTisha Gallop
Permit Ready to Issue  3/26/2014 DONE
DetailsTisha Gallop
Plan assigned to (AJS)3/11/20143/11/20143/17/2014 PASS
DetailsAdele J Schaffeld-Griffin
ADA county jail
Routing - PLAN CHECK3/11/2014 3/17/2014 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed  3/17/2014 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  3/17/2014 DONE
Intake Approval  3/11/2014 PASS
DetailsAdele J Schaffeld-Griffin
Application received  3/7/2014 DONE
Application submitted via PDS Online on Mar 7 2014 4:51PM