Third Notice | | 4/23/2016 | 5/11/2016 | | DONE |
|
|
|
sent with letter
|
Third Notice | | 3/15/2016 | 4/18/2016 | | DONE |
|
|
|
|
Third Notice | | 2/16/2016 | 3/10/2016 | | DONE |
|
|
|
|
Second Notice | | 1/23/2016 | 2/11/2016 | | DONE |
|
|
|
Mailed 2-12-16
|
First Notice | | 1/9/2016 | 1/13/2016 | | DONE |
|
|
|
Mailed 1-14-16
|
Permanent Occupancy | | | 12/30/2015 | | DONE |
|
|
|
|
BLD-Final | 12/4/2015 | 12/4/2015 | 12/4/2015 | P | PASS |
Mike Jordan
|
|
|
Michael Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 12/3/2015 | 12/4/2015 | 12/4/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per tim frost sprinkler protection not required under the tanks and distillery.
|
BLD-Conference | 11/16/2015 | 11/16/2015 | 11/16/2015 | P | DONE |
Mike Jordan
|
|
|
Tenant needs a final or temp CO (requires permit change for either retail occupancy only or current scope of permit). Spoke to owner, (Mike) noted that A1 will complete the plumbing and install the hood this wednesday 11-18-15. Trying for final inspections this friday and monday.
|
BLD-Conference | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | DONE |
Mike Jordan
|
|
|
Check status of distillery. Brewing?. Not brewing at this time. Per owner, all remaing parts have arived. A1 will be obtaining a mech. permit to install the hood.
|
BLD-Final | 5/20/2015 | 5/21/2015 | 5/21/2015 | P | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Temp occ. ok for the front sales portion only
|
FIRE-Final Inspection | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | PART |
Troy Cobbley
|
|
|
The life safety in the "M" occupancy area of this project is passed. No distilling or "manufacturing" allowed at this time. I went over the life safety requirements as noted on the Fire Dept Plan Review Comments.
|
BLD-Conference | 5/19/2015 | 5/20/2015 | 5/20/2015 | P | DONE |
Mike Jordan
|
|
|
|
BLD-Conference | 5/20/2015 | 5/20/2015 | 5/20/2015 | A | DONE |
Mike Jordan
|
|
|
A correction notice was issued to schedule all required inspections to obtain a cert. of occupancy.
|
Place hold on job | 10/24/2014 | | 11/6/2014 | | DONE |
Christina Prado
|
|
|
No inspections until balance is settled. See Rita or Christina for details///Paid in full 11/5/14
|
Fees Due Hold | 10/25/2014 | | 11/6/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/9/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 10/9/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/9/2014 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 9/9/2014 | | DONE |
Christina Prado
|
|
|
|
Expiration Notice | 8/18/2014 | 9/9/2014 | 8/18/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 7/1/2014 | | 7/2/2014 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 3/17/2014 | | 7/2/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - MECHANICAL | 7/1/2014 | | 7/1/2014 | | PASS |
Troy James
|
|
|
See red notes on plans
|
Routing - MECHANICAL | 6/26/2014 | | 6/26/2014 | | FAIL |
Troy James
|
|
|
I was asked by Jenifer Gililand to provide a letter of mechanical review history. This letter has been submitted as an document.
|
Routing - PLAN CHECK | 6/10/2014 | | 6/25/2014 | | PASS |
Tim L. Woodard
|
|
|
Fire approved as F-1 review now approved. TLW
|
Routing - FIRE | 6/10/2014 | 6/10/2014 | 6/20/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 3 06-19-14
|
Routing - MECHANICAL | 6/10/2014 | | 6/11/2014 | | FAIL |
Troy James
|
|
|
need mechanical engineered plans
|
Plan resubmittals received | | | 6/10/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 5/7/2014 | 5/7/2014 | 5/22/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire PLan Review Rev 2 05-22-14
|
Routing - MECHANICAL | 5/7/2014 | | 5/22/2014 | | FAIL |
Troy James
|
|
|
|
Plan resubmittals received | | | 5/7/2014 | | DONE |
Tim L. Woodard
|
|
|
Recieved new submittal with 70 Gal still. TLW
|
Routing - FIRE | 3/28/2014 | 3/28/2014 | 4/4/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 04-04-14
|
Routing - MECHANICAL | 3/28/2014 | | 4/1/2014 | | FAIL |
Troy James
|
|
|
waiting for question to be answered how the b-vent is to be connected to the kettle.
|
Plan resubmittals received | | | 3/28/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/28/2014 | | 3/28/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 3/17/2014 | 3/17/2014 | 3/26/2014 | | FAIL |
Craig D. Hanson
|
|
|
See attached Fire Plan Review 03-26-14
|
1st review completed | | | 3/26/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Solid Waste | 3/18/2014 | | 3/25/2014 | | PASS |
Peter J. McCullough
|
|
|
Approved in E-Plan Review. TLW
|
Routing - PLAN CHECK | 3/17/2014 | | 3/25/2014 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PLUMBING | 3/17/2014 | | 3/19/2014 | | PASS |
Daryl Spivey
|
|
|
Additional backflow protection may be required.
|
Routing - Erosion and Sediment | 3/17/2014 | | 3/19/2014 | | PASS |
Evan Jenkins
|
|
|
No Review Necessary. No Earth Disturbance or Saw Cutting
|
Routing - PUBLIC WORKS | 3/17/2014 | | 3/18/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - MECHANICAL | 3/17/2014 | | 3/18/2014 | | FAIL |
Troy James
|
|
|
eplan
|
Routing PW Sewer Rating | 3/18/2014 | | 3/18/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Environmental | 3/18/2014 | | 3/18/2014 | | PASS |
Walt Baumgartner
|
|
|
|
Intake Approval | | | 3/17/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - Addressing | 3/17/2014 | | 3/17/2014 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 3/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 10 2014 4:53PM
|