Second Notice | | 10/16/2014 | 10/24/2014 | | DONE |
|
|
|
|
Print Statement | | | 10/24/2014 | | DONE |
Tisha Gallop
|
|
|
e-mailed to Duel Christensen at Anderson Construction
|
First Notice | | 9/27/2014 | 10/6/2014 | | DONE |
|
|
|
e-mailed to Duel Christensen at Anderson Construction
|
Permanent Occupancy | | | 9/24/2014 | | DONE |
|
|
|
|
BLD-Final | 9/16/2014 | 9/16/2014 | 9/17/2014 | P | PASS |
Dave Hannah
|
|
|
Duel Phone #: ###-####
|
Permanent Occupancy | | | 9/17/2014 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 9/16/2014 | 9/16/2014 | 9/16/2014 | P | PASS |
Forrest France
|
|
|
Verified noted correction items. Contractor to include EM lighting inside the exit stairway at the SE.
|
BLD-Final | 7/15/2014 | 7/17/2014 | 7/17/2014 | P | PART |
Bob Archibald
|
|
|
inspection for temp CO // Jim (or Patrick ###-####) Phone #: ###-####. ok for temp occupancy, CN issued- need exterior handrail south exit, panic hardware west door and permanant exit signs.
|
FIRE-Final Inspection | 7/16/2014 | 7/17/2014 | 7/17/2014 | A | PART |
Craig D. Hanson
|
|
|
Temp CO good for 2 weeks (ending 7/31) for delivery and instilation of new exit signs. Temp exit signage good. All emergency lighting tested.
|
Temporary Occupancy | 7/17/2014 | 7/31/2014 | 7/17/2014 | | DONE |
Tisha Gallop
|
|
|
fire approved temp to 7/31/14. structrual temp
|
FIRE-Final Inspection | 7/14/2014 | 7/14/2014 | 7/14/2014 | P | CANC |
Craig D. Hanson
|
|
|
Not a final inspection. This was a pre-final walk thru. exit signs and emergency lighting yet to be installed.
|
FIRE-Conference | 7/14/2014 | 7/14/2014 | 7/14/2014 | P | DONE |
|
|
|
Pre-final walk through. No temp CO. Exit signage and emergency lighting not installed.
|
Permit Ready to Issue | | | 4/21/2014 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/21/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/21/2014 | | DONE |
|
|
|
|
Routing - Addressing | 4/15/2014 | | 4/16/2014 | | PASS |
Emily Dixon
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 3/12/2014 | | 4/16/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 4/1/2014 | | 4/15/2014 | | PASS |
Tim L. Woodard
|
|
|
Approved with comments on Plan Sheets. TLW
|
Routing - FIRE | 4/1/2014 | 4/1/2014 | 4/3/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Rev 1 04-03-14
|
Plan resubmittals received | | | 4/1/2014 | | DONE |
Tim L. Woodard
|
|
|
|
1st review completed | | | 3/25/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/12/2014 | | 3/25/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing Off Site - C.D.H | 3/12/2014 | | 3/25/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 3/12/2014 | | 3/18/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 03-18-14
|
Intake Approval | | | 3/12/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 3/12/2014 | | 3/12/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 3/12/2014 | | 3/12/2014 | | FAIL |
Emily Dixon
|
|
|
Address needs suite number.
|
Routing PW Sewer Rating | 3/12/2014 | | 3/12/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 3/12/2014 | | 3/12/2014 | | PASS |
Walt Baumgartner
|
|
|
|
Application received | | | 3/11/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 11 2014 8:24AM
|