Second Notice | | 7/26/2014 | 7/17/2014 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Barber
|
First Notice | | 6/30/2014 | 7/16/2014 | | DONE |
|
|
|
Faxed 7-16-14
|
BLD-Final | 6/19/2014 | 6/20/2014 | 6/20/2014 | A | PASS |
Dave Hannah
|
|
|
Darren Phone #: ###-#### as per city aproved plans note handrails on ext stairs are not to todays codes and not on plans to be changed.
|
Permanent Occupancy | | | 6/20/2014 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 6/13/2014 | 6/16/2014 | 6/16/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
FIRE-Conference | 6/10/2014 | 6/10/2014 | 6/10/2014 | P | DONE |
Forrest France
|
|
|
Regarding fire life safety items and project schedule.
|
FIRE-Conference | 5/6/2014 | 5/8/2014 | 5/8/2014 | A | DONE |
Forrest France
|
|
|
On site conference regarding hood suppression permit work and equipment layout.
|
BLD-Framing/Rough-in | 5/6/2014 | 5/7/2014 | 5/7/2014 | A | PASS |
Dave Hannah
|
|
|
darren Phone #: ###-####
|
FIRE-Conference | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding hood suppression system, EM lighting, exit signs, rated stairway, door hardware, fire life safety conditions and project schedule.
|
BLD-Framing/Rough-in | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | PASS |
Dave Hannah
|
|
|
darren Phone #: ###-####
|
BLD-Conference | 4/30/2014 | 5/1/2014 | 5/1/2014 | A | DONE |
Mike Jordan
|
|
|
darrin Phone #: ###-####. Spoke to contractor about concerns for a draft stop in ceiling. One is already present, but concealed area is less than 3000 s.f.
|
Permit Ready to Issue | | | 4/30/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 4/30/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 4/30/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 3/13/2014 | 3/13/2014 | 4/29/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st reiew complete Due 4/9 Level 3 TI - ePlanReview - Juniper
|
Routing - Design Review | 4/22/2014 | | 4/29/2014 | | PASS |
Sarah Schafer
|
|
|
Approved.
|
Routing - PLAN CHECK | 4/22/2014 | | 4/29/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/18/2014 | | 4/22/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
pending sign off from DR.
spoke with Andy he doen not need ESC permit or waiver letter.
|
Plan Reviewer's activity | | | 4/22/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
email string on zoning cert 4/22/14
Adele,
We will get the zoning cert info uploaded right away. Thank you so much for your help on this!
Thanks!
Matt Smith
HC Company, Inc.
www.hcco-inc.com
From: Adele Schaffeld-Griffin [mailto:ASchaffeldGriffin@cityofboise.org]
Sent: Tuesday, April 22, 2014 1:34 PM
To: Matt Smith
Cc: jeremy@watermarkpm.com; dave@alcarchitecture.com; Adele Schaffeld-Griffin; Sarah Schafer
Subject: FW: Juniper, 211 N 8th
Matt, please see the email from Sarah below on the zoning certificate submittal. It looks like she is going to get it turned around ASAP for this project. Planning has up to 15 days to complete zoning certificates so she is really stepping up and taking care of you, she is wonderful.
Please let me know if you would like to pursue the early start permit. I am happy to get that started for you.
I have received the unprotected opening calculation from Dave and uploaded it into the e plan system on our end. Once the zoning certificate is approved I will be able to release the full building permit.
I spoke with Andy Long in our Erosion Sediment Division. Based on the low risk of the scope of exterior work he will not require and ESC permit or waiver letter. He wanted me to remind you to be cautious when you are opening the wall to follow any ESC procedures needed to be in place even though an ESC permit is not required.
Project Time Line-
Project Intake Approval 3/13/14
Project Assigned Level 3 3/13/14
Plan Review Time Frame
20 business day. Project due 4/9/14
1st plan review completed 3/28/14 7 days sooner than scheduled
Revised plans received
From architect 4/17/14
2nd plan review completed 4/22/14
Please let me know if there is anything else I can do to assist you.
Thank you
Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####
From: Sarah Schafer
Sent: Tuesday, April 22, 2014 1:10 PM
To: Adele Schaffeld-Griffin; dave@alcarchitecture.com
Subject: RE: Juniper, 211 N 8th
Dave,
Attached is the link to the electronic application submittal for a zoning certificate. If you can fill out the application and provide me with photographs of the building and an elevation showing the windows you are putting back in, we should be able to get you an approval within 24 hours of application submittal. If you are changing anything else on the exterior, including paint, submit that information with this zoning certificate application as well.
http://pds.cityofboise.org/home/documents/apps/100/
It is application number 123!
Please let me know if you have any questions.
Sarah Schafer
City of Boise
Design Review and Historic
Preservation Manager
150 N. Capitol Blvd.
Boise, ID 83###-####
###-####
From: Adele Schaffeld-Griffin
Sent: Tuesday, April 22, 2014 12:03 PM
To: dave@alcarchitecture.com
Cc: Sarah Schafer; Adele Schaffeld-Griffin
Subject: Juniper, 211 N 8th
Sarah,
Can you please send Dave the forms that will need to be submitted for a zoning certificate for the windows being put back in place that were previously covered with brick at the above address?
Dave was also inquiring on the time frame for the zoning certificate.
Thank you
Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####
|
Routing - FIRE | 4/18/2014 | 4/18/2014 | 4/18/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Ploan Review Rev 1 04-18-14
|
Routing PW Solid Waste | 3/13/2014 | | 3/28/2014 | | PASS |
Peter J. McCullough
|
|
|
signed off in e plan
|
1st review completed | | | 3/28/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 3/13/2014 | | 3/28/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
Plan Reviewer's activity | | | 3/27/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
emailed David the plan review report and permit for the plan review of the previous tenant that wast the change in occupancy and use for this space.
|
Routing - FIRE | 3/13/2014 | 3/13/2014 | 3/17/2014 | | FAIL |
Scott Arellano
|
|
|
See Fire Plan Report 03-17-14
|
Routing PW Sewer Rating | 3/13/2014 | | 3/14/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 3/13/2014 | | 3/13/2014 | | PASS |
Walt Baumgartner
|
|
|
existing GI
|
Routing - PLUMBING | 3/13/2014 | | 3/13/2014 | | PASS |
Bill VanDegrift
|
|
|
May require additional backflow protection on installed equipment.
|
Routing - Addressing | 3/13/2014 | | 3/13/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 3/13/2014 | | 3/13/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 3/13/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Sam Zahorka. Plan Review Fees paid.
|
Pending Assignment by JCB | 3/13/2014 | | 3/13/2014 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 3/11/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 11 2014 9:33AM
|
Intake Approval | | | 3/11/2014 | | FAIL |
Sam Zahorka
|
|
|
|