First Notice | | 12/18/2014 | 12/17/2014 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
BLD-Other | 12/8/2014 | 12/8/2014 | 12/8/2014 | P | CANC |
Phil Shearer
|
|
|
Erosion Control Program Final inspection. Building and site work are complete. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Final | 12/5/2014 | 12/8/2014 | 12/8/2014 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
Permanent Occupancy | | | 12/8/2014 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/4/2014 | 12/5/2014 | 12/5/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory. Two non-functional exit signs to be repaired and one EM light to be added per discussion prior to structural final.
|
BLD-Final | 12/2/2014 | 12/4/2014 | 12/4/2014 | A | CANC |
Phil Shearer
|
|
|
Structural and final. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
PubWorks Occupancy Approval | 12/4/2014 | 12/4/2014 | 12/4/2014 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 12/3/2014 | 12/3/2014 | 12/3/2014 | | DONE |
Cody Riddle
|
|
|
|
BLD-Final | 11/20/2014 | 11/20/2014 | 11/20/2014 | P | NR |
Jim Sly
|
|
|
Completion Inspection on remodeled rooms #123,126,128,114,115,116,117,118,101,119,129,133,134,135,136 ; 137 Ceiling Grid inspection in Room #120, 121, 122 Phone #: ###-#### Inspection requested via web by Markus Schlegel
Contractor wants to allow church members to use Kitchen, some class rooms and restooms completed prior to final inspection. Advised to have conference with Fire Inspector.
|
CHANGE STATUS TO (ISS) | | | 11/18/2014 | | DONE |
Christina Prado
|
|
|
Plan mod fees paid
|
OVERRIDE | | | 11/10/2014 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2014 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 11/10/2014 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 11/3/2014 | | 11/10/2014 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 11/3/2014 | | 11/10/2014 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 11/3/2014 | | 11/10/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Mod 11-10-14
|
Routing PW Drainage | 11/5/2014 | | 11/10/2014 | | PASS |
Brian Murphy
|
|
|
SCOPE CHANGED TO TI
|
Routing - PLUMBING | 11/7/2014 | | 11/7/2014 | | PASS |
Bill VanDegrift
|
|
|
remove the kitchen from scope of work
|
Routing PW Solid Waste | 11/5/2014 | | 11/6/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Sewer Rating | 11/5/2014 | | 11/5/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PUBLIC WORKS | 11/3/2014 | | 11/5/2014 | | PASS |
Beverly Mountain
|
|
|
|
Plan Modification Accepted | | | 11/3/2014 | | DONE |
|
|
|
plan mod workflow started to eliminate kitchen portion of work.
|
BLD-Framing/Rough-in | 10/7/2014 | 10/8/2014 | 10/8/2014 | P | PASS |
Phil Shearer
|
|
|
South Storage room addition, would prefer later in the day around 2pm. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 10/6/2014 | 10/6/2014 | 10/6/2014 | P | PART |
Phil Shearer
|
|
|
North addition steel stud framing and south addition wood framing. Early afternoon preferred. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PASS |
Phil Shearer
|
|
|
Truss and roof framing and sheeting on north addition multi use rooms Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | PART |
Phil Shearer
|
|
|
ESC Site Inspection ESC#14-00175 Last performed by Andy Long 7/15/14. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/18/2014 | 9/19/2014 | 9/19/2014 | P | PASS |
Phil Shearer
|
|
|
CMU Rebar and grouting inspection. Grouting to take place at 2pm. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/12/2014 | 9/15/2014 | 9/15/2014 | A | PASS |
Phil Shearer
|
|
|
Rebar and Grout inspection, north CMU walls. Grout time is 8am. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/10/2014 | 9/12/2014 | 9/12/2014 | A | PASS |
Phil Shearer
|
|
|
CMU Rebar and Grout inspection. Grout at 8am. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/8/2014 | 9/10/2014 | 9/10/2014 | A | **** |
Phil Shearer
|
|
|
*****pour time 10:00AM*****Masonry rebar & grout inspection second course, grouting will take on will call and TBD for AM grouting. Phone #: ###-#### >> Inspection requested via web by Markus Schlegel
|
BLD-Framing/Rough-in | 9/9/2014 | 9/9/2014 | 9/9/2014 | P | PASS |
Phil Shearer
|
|
|
ADA restrooms
|
BLD-Framing/Rough-in | 9/9/2014 | 9/9/2014 | 9/9/2014 | A | NR |
Phil Shearer
|
|
|
Framing inspection in the mechanical/pantry room can be do the same time as grout and rebar for masonry at 11am. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Other | 9/8/2014 | 9/9/2014 | 9/9/2014 | A | PASS |
Phil Shearer
|
|
|
Masonry rebar ; grout inspection second course, grouting will take place at 11am. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Conference | 9/5/2014 | 9/8/2014 | 9/8/2014 | A | PASS |
Phil Shearer
|
|
|
inspection will include 1st course of masonry and rebar on the north and south addition prior to grouting. Grouting is scheduled for 7am pending inspection. Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Foundation | 8/19/2014 | 8/20/2014 | 8/20/2014 | P | PASS |
Phil Shearer
|
|
|
rebar and stem wall inspection Phone #: ###-#### Inspection requested via web by Markus Schlegel
|
BLD-Foundation | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | PASS |
Phil Shearer
|
|
|
Footing and rebar inspection on north and south foundation additions. Phone #: ###-#### Inspection requested via web by Markus Schlegel Footings
|
BLD-Conference | 7/15/2014 | 7/16/2014 | 7/16/2014 | P | PASS |
Jim Storey
|
|
|
Marcus-would like a call with an approx meet time Phone #: ###-####
|
OVERRIDE | | | 7/7/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/7/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 7/7/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 7/7/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 5/20/2014 | | 5/20/2014 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 5/20/2014 | | PASS |
John Menard
|
|
|
Reviewed and approved final structural comment. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2014 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 4/10/2014 | | 5/20/2014 | | PASS |
John Menard
|
|
|
1st Review Completed 5/9/2014
|
Routing Off Site - STRUCTURAL | 5/12/2014 | | 5/19/2014 | | FAIL |
John Menard
|
|
|
|
Routing - PLAN CHECK | 5/12/2014 | | 5/14/2014 | | PASS |
John Menard
|
|
|
with red lined notes. JCM
|
Routing - FIRE | 5/12/2014 | | 5/13/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 2 05-13-14
|
1st review completed | | | 5/9/2014 | | FAIL |
John Menard
|
|
|
|
Routing - PLAN CHECK | 4/29/2014 | | 5/9/2014 | | FAIL |
John Menard
|
|
|
|
Routing PW Drainage | 4/10/2014 | | 4/30/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 4/29/2014 | | 4/30/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - FIRE | 4/29/2014 | | 4/30/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 04-30-14
|
1st review completed | | | 4/29/2014 | | DONE |
John Menard
|
|
|
Major change required to building design. 1st review completed without comment to allow applicant to upload revised building design. JCM
|
Routing - PLAN CHECK | 4/10/2014 | | 4/29/2014 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 4/10/2014 | | 4/25/2014 | | FAIL |
John Menard
|
|
|
|
Routing PW Sewer Rating | 4/10/2014 | | 4/21/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 4/10/2014 | 4/15/2014 | 4/16/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 4/10/2014 | | 4/14/2014 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 4/10/2014 | 4/10/2014 | 4/11/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 04-11-14
|
Routing - PLANNING Land Div | 4/10/2014 | | 4/11/2014 | | PASS |
Dave Abo
|
|
|
|
Routing - PUBLIC WORKS | 4/10/2014 | | 4/10/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 4/10/2014 | | 4/10/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - PLUMBING | 4/10/2014 | | 4/10/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING | 4/10/2014 | | 4/10/2014 | | PASS |
Joshua Johnson
|
|
|
|
Pending Assignment by JCM | 4/10/2014 | | 4/10/2014 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 4/10/2014 | | PASS |
John Menard
|
|
|
|
Intake Approval | | | 3/28/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Chad I sent you an email in regards to the missing sheet G0.02 but I also need the completed check list so that I can beging the pre screen. Can you upload them?
Thank you
|
Application received | | | 3/12/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 12 2014 3:49AM
|