Description
***4-16-2014 THIS PROJECT IS MODIFIED TO REFLECT THE EXPANSION OF THE GARAGE AREA BY 172S.F. NO ADDED VALUE TO THIS PROJECT. 4-16-2014 pep*** This project is for the remodel and addition to an existing 2506s.f. 2-story single family dwelling. the addition will include 422s.f. of basement area and a new stair to the basement. The main level addition will include 1327s.f. to the entire back of the dwelling that will create a new master suite, kitchen dining area and one bedroom aditions. The garage will be enlarged from 456s.f. to 800s.f. with 360s.f. of bonus storage above it. R-1B ok per Leon Letsen. Separate electrical, plumbing, mechanical and ESc permits are required. All per the approved plans as marked, energy prescriptive method, engineer's details and calculations along with the plan review notes pep
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  10/17/2016 DONE
Case Summary (BLD)  7/21/2016 DONE
Letter of compliance/Occupancy  3/27/2015 DONE
Routing Walk-In (BLD)3/19/20153/19/20153/19/2015PPASS
DetailsPerry Paine
BLD-Final11/19/201411/19/201411/20/2014PPASS
DetailsTony Young
Aaron Phone #: ###-####
DOC - Permit Finaled11/20/201411/20/201411/20/2014PPASS
DetailsTony Young
done
BLD-Ceiling Grid Inspection11/18/201411/19/201411/19/2014ACANC
DetailsTony Young
Aaron Phone #: ###-####
BLD-Final11/17/201411/18/201411/18/2014PCANC
DetailsTony Young
aaron Phone #: ###-####
BLD-Final10/27/201410/28/201410/28/2014AFAIL
DetailsJim Sly
Aaron Megee Phone #: ###-####
Handrail not continuous.
BLD-Energy code compliance6/26/20146/27/20146/27/2014APASS
DetailsTony Young
Aaron Phone #: ###-####
BLD-Other6/26/20146/26/20146/27/2014PNR
DetailsTony Young
David Phone #: ###-####
BLD-Framing/Rough-in6/20/20146/23/20146/23/2014APART
DetailsTony Young
Aaron Phone #: ###-####,, ok to insulate
BLD-Framing/Rough-in6/20/20146/20/20146/20/2014PPART
DetailsTony Young
Aaron Phone #: ###-####,, ok to insulate,, need to verify seal pack,, need soffit inspection
BLD-Wall Bracing6/10/20146/11/20146/11/2014APASS
DetailsTony Young
aaron Phone #: ###-####
Routing - MECHANICAL5/29/2014 5/29/2014 PASS
DetailsTroy James
BLD-Foundation4/18/20144/21/20144/21/2014APART
DetailsTony Young
Shawn Phone #: ###-####,, work in progress,, ok
BLD-Footing4/16/20144/17/20144/17/2014APASS
DetailsTony Young
Pouring at 12 - Shawn Phone #: ###-####
Routing Walk-In (PW Hillside)4/16/20144/16/20144/16/2014APASS
DetailsJason C. Taylor
extended garage addition
Routing Walk-In (Zoning)4/16/20144/16/20144/16/2014APASS
DetailsLeon Letson
extended garage footprint
Routing Walk-In (BLD)4/16/20144/16/20144/16/2014APASS
DetailsPerry Paine
modified permit...no added value
Case Summary (BLD)  4/16/2014  
Inspection Record Card- Bld  4/16/2014  
PubWorks Subgrade Approval4/14/20144/14/20144/14/2014 DONE
DetailsJason C. Taylor
*ALL RESIDENCE FOOTINGS & COLUMN* A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
BLD-Conference4/10/20144/10/20144/10/2014PPEND
DetailsTony Young
Aaron Phone #: ###-####,, ?s on tall wall.. will call in when working on it
OVERRIDE  3/18/2014  
Issue PAID IN FULL permit  3/18/2014 DONE
DetailsChristina Prado
Inspection Record Card- Bld  3/18/2014  
Telephone call  3/18/2014 DONE
DetailsChristina Prado
called Aaron to advise permit is ready and gave fees due
Permit Ready to Issue  3/18/2014 DONE
DetailsChristina Prado
Plan assigned to (PEP)3/14/20143/14/20143/17/2014 PASS
DetailsAndy J. Long
Routing - Erosion and Sediment3/14/2014 3/17/2014 PASS
DetailsAndy J. Long
for Plan waiver Request.

Waiver request approved. Area of disturbance is surrounded by vegetative buffer. Will need to designate an RP to get ESC permit.
PLANS/APPL TAKEN TO FRONT DESK  3/17/2014  
Routing Walk-In (PW Hillside)3/14/20143/14/20143/14/2014PPASS
DetailsJason C. Taylor
Subgrade inspection, with setback requirements required prior to scheduling building department for footing inspections. Jason Taylor ###-####.
Routing Walk-In (Zoning)3/14/20143/14/20143/14/2014PDONE
DetailsLeon Letson
Routing Walk-In (BLD)3/14/20143/14/20143/14/2014PPASS
DetailsPerry Paine
1st review completed  3/14/2014 FAIL
need ESC plan Waiver
Application received 3/14/2014