Second Notice | | 9/5/2014 | 9/18/2014 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 7/28/2014 | 8/26/2014 | | DONE |
|
|
|
|
Permanent Occupancy | | | 7/18/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 7/16/2014 | 7/16/2014 | 7/16/2014 | P | PASS |
Mike Jordan
|
|
|
Alissa Phone #: ###-####. ok for perm occ.
|
BLD-Final | 6/25/2014 | 6/26/2014 | 6/26/2014 | A | PART |
Mike Jordan
|
|
|
Alissa Phone #: ###-####. All life safety issues ok, trades signed off except for mech. Needs to verify adequate ventilation for the A occupancy. Discussed this with owner. Ok to sign off after mech. has passed.
|
FIRE-Final Inspection | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed. Need to post max occupant load signage per plan review at the A-3 area prior to structural final.
|
Issue & PRINT permit | | | 5/14/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (AJS) | 3/25/2014 | 3/25/2014 | 4/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 4/24 Boise Fitness Equipment
|
Routing - PLAN CHECK | 4/17/2014 | | 4/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 4/21/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/21/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 4/21/2014 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 4/17/2014 | | FAIL |
|
|
|
Failed; Plan Check
|
Routing - FIRE | 4/16/2014 | | 4/17/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plans Review 04-17-14
|
Routing - PLAN CHECK | 3/25/2014 | | 4/16/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
sent Brock an email to revise the plumbing fixture table to include the difference between the womans and mens WC in the A3 portion of the table
|
Routing - Addressing | 3/25/2014 | | 3/27/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 3/25/2014 | | 3/27/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 3/27/2014 | | 3/27/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 3/25/2014 | 3/25/2014 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/25/2014 | | DONE |
Tisha Gallop
|
|
|
|