First Notice | | 8/8/2014 | 8/5/2014 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
BLD-Final | 7/29/2014 | 7/29/2014 | 7/29/2014 | P | PASS |
Jim Sly
|
|
|
Doug-would like as soon as poss. Phone #: ###-####
|
BLD-Final | 7/28/2014 | 7/29/2014 | 7/29/2014 | A | PASS |
Jim Sly
|
|
|
Please call Doug for Access ###-#### Phone #: ###-#### Inspection requested via web by Brian McCoy OK for Perm Occ. Verified with troy C. Alarm Final OK Tamper switches.
|
Permanent Occupancy | | | 7/29/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 7/28/2014 | 7/28/2014 | 7/28/2014 | P | FAIL |
Jim Storey
|
|
|
Please call Doug ###-#### Phone #: ###-#### Inspection requested via web by Brian McCoy override exit doors mag lock.
|
FIRE-Final Inspection | 7/28/2014 | 7/28/2014 | 7/28/2014 | P | PASS |
Craig D. Hanson
|
|
|
pass, no corrections required. racking inspected and pass for fire, bld14-01563
|
BLD-Final | 7/24/2014 | 7/25/2014 | 7/25/2014 | P | NR |
Mike Jordan
|
|
|
Please contact Doug for Access ###-#### Phone #: ###-#### Inspection requested via web by Brian McCoy. fire/life/safety failed.
|
FIRE-Final Inspection | 7/25/2014 | 7/25/2014 | 7/25/2014 | A | FAIL |
Troy Cobbley
|
|
|
Called Doug and left voice message I was on the way. No contact made at project site. Performed quick inspection and found exit signs missing, one missing fire extinguisher and the new wall in the Break Room has cause sprinkler pendants to be overspaced in the Engineering Room
|
BLD-Ceiling Grid Inspection | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Mike Jordan
|
|
|
Please call Doug for access 208 957 1512 Phone #: ###-#### Inspection requested via web by Brian McCoy
|
BLD-Ceiling Grid Inspection | 6/27/2014 | 6/30/2014 | 6/30/2014 | A | FAIL |
Mike Jordan
|
|
|
Please contact Doug for building Access ###-#### Phone #: ###-#### Inspection requested via web by Brian McCoy. New grid patched into exisiting must be same system.
|
BLD-Energy code compliance | 6/9/2014 | 6/9/2014 | 6/9/2014 | P | PASS |
Tom Arcoraci
|
|
|
Please Call Doug for Access ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy
|
BLD-Conference | 6/6/2014 | 6/9/2014 | 6/9/2014 | P | CANC |
Mike Jordan
|
|
|
Please Call Doug For Access ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy Inspection cancelled from web by: Brian McCoy
|
BLD-Framing/Rough-in | 6/5/2014 | 6/5/2014 | 6/5/2014 | P | PASS |
Mike Jordan
|
|
|
Please contact Doug at ###-#### for access. Phone #: ###-#### >> Inspection requested via web by Brian McCoy. Interior steel stud framed walls only ok.
|
Print Occupancy Form | | | 5/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 5/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 5/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 5/1/2014 | 5/1/2014 | 5/6/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Mod 05-06-14
|
Plan assigned to (AJS) | 5/1/2014 | 5/1/2014 | 5/6/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
plan modification
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/1/2014 | | 5/5/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan Modification Accepted | | | 4/29/2014 | | DONE |
Tisha Gallop
|
|
|
started plan mod workflow for applicant to upload changes. Original plans were approved, but permit not issued yet.
|
Plan assigned to (AJS) | 3/31/2014 | 3/31/2014 | 4/9/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Due 4/11 Cradlepoint Expansion
|
Routing - PLAN CHECK | 3/31/2014 | | 4/9/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 4/9/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2014 | | DONE |
|
|
|
|
Routing - FIRE | 3/31/2014 | 3/31/2014 | 4/2/2014 | | PASS |
Craig D. Hanson
|
|
|
See fire plan review
|
Routing - PUBLIC WORKS | 3/31/2014 | | 4/2/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 4/2/2014 | | 4/2/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Design Review | 3/31/2014 | | 3/31/2014 | | PASS |
Sarah Schafer
|
|
|
Approved the roll up door and transformer addition through buidling permit plans.
|
Routing - Addressing | 3/31/2014 | | 3/31/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 3/31/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 3/26/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 26 2014 2:15PM
|