Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD14-00735
StatusFinaled
Name PRISTINE POOLS AND SPAS
Site Address 1875 S CENTURY WAY
Project NameWINGS CENTER POOL
Customer Number 
ePlanReviewNo
Description
(WINGS CENTER POOL) The fire sprinkler system is used for building area increase. To construct a new 1,159 square foot swimming pool to be used for swimming instruction classes. The pool will have a perimeter dimension of 151 lineal feet and a volume of 34,630 gallons. The pool room shell expansion will be constructed under permit BLD14-00719. A separate tenant improvement permit is required to establish a Certificate of Occupancy. Work is to include a reinforced concrete gunite swimming pool (pool walls and pool floor), a concrete stairway to serve the pool, a pool ladder, handrails, a pool lift for the disabled, and pool equipment. Only one accessible entry is required for the disabled. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. Compliance with the 2012 ISPSC is allowed in lieu of the 2012 IBC where the requirements are different. This permit does not establish a Certificate of Occupancy for any tenant. Site plans and floor plans submitted with the pool drawings do not accurately represent what will be constructed and are for reference only. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/9/20151/12/20151/12/2015APASS
DetailsPhil Shearer
Mike Phone #: ###-####
Permanent Occupancy  1/12/2015 DONE
Print Occupancy Form  1/12/2015 DONE
DetailsCandy A. Nichols
Print Occupancy Form  1/12/2015 DONE
DetailsCandy A. Nichols
BLD-Foundation6/16/20146/17/20146/17/2014APASS
DetailsTom Arcoraci
Christian Phone #: ###-####
Issue PAID IN FULL permit  5/16/2014 DONE
DetailsChristina Prado
Plan assigned to (CJW)4/21/20144/21/20145/14/2014 PASS
DetailsCarl Westfall
WINGS CENTER POOL - Level 3 TI (15 days - May 8)
Routing - PLAN CHECK5/12/2014 5/14/2014 DONE
DetailsCarl Westfall
Routing completed
PLANS/APPL TAKEN TO FRONT DESK  5/14/2014 DONE
Permit Ready to Issue  5/14/2014 DONE
DetailsBarbara Stitt
Inspection Record Card- Bld  5/14/2014 DONE
DetailsBarbara Stitt
Telephone call  5/14/2014 DONE
DetailsChristina Prado
called jamie to advise permit is ready for pick and gave fees due
Routing - PLUMBING5/7/2014 5/12/2014 PASS
DetailsDaryl Spivey
Per plan and ISPC>
Routing - PLAN CHECK5/6/2014 5/7/2014 DONE
DetailsCarl Westfall
(5-6-14) Waiting for Plumbing to call the plans back.

(5-7-14) Resubmittals received. Routed back to plumbing.
Plan resubmittals received  5/7/2014 DONE
DetailsChristina Prado
Received two revised sets of plans marked P-1 & P-2; plans inserted by rep and taken back to Carl Westfall for review
Routing - FIRE5/5/2014 5/6/2014 PASS
DetailsCraig D. Hanson
No Report
1st review completed  5/6/2014 DONE
Failed plumbing
Routing - PLAN CHECK4/24/2014 5/6/2014 PASS
DetailsCarl Westfall
Drawings approved with "red lines".
Routing - Design Review4/23/2014 4/24/2014 PASS
DetailsJosh Wilson
Josh Wilson - DRH14-00133
Routing - PLUMBING4/22/2014 4/23/2014 FAIL
DetailsBill VanDegrift
1. Page A 2.1 does not match P-1.
2. RPBP required on pool equipment makeup water.
3. Deck drain cannot directly drain to sanitary sewer. Pool drains to be indirectly wasted only.
Routing - Erosion and Sediment4/21/2014 4/22/2014 PASS
DetailsAndy J. Long
Reference ESC14-00093. Previously issued for pool excavation/shell by TK Construction. Fees added to transfer permit and RP for Pristine Pools and allow plan waiver so the $78.75 waiver and modification fee was added to permit fees of ESC14-00093. AJL
Routing - Addressing4/21/2014 4/21/2014 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS4/21/2014 4/21/2014 PASS
Pending Assignment by JCB4/18/2014 4/21/2014 DONE
DetailsJason Blais
Plans ACCEPTED BY PLAN TECH  4/18/2014  
Intake Approval  4/18/2014 PASS
DetailsJason Blais
Prescreen passed by plans examiner and plan review fees paid.
Application received 3/28/20143/28/2014 DONE
DetailsTisha Gallop
Plan Reviewer's activity  3/28/2014 DONE
DetailsAdele J Schaffeld-Griffin
email sent to Jamie 3/28/14

Jamie,

I have attached the check list that was scanned in from the pool intake, sorry the items that I highlighted for you are dark in the scan. I have discovered that you will need to provide some additional information than noted on this check list. The only permits that are submitted are the grading, demo and a shell only.

We have not received a tenant improvement permit and plan set. In addition to the highlighted items all of the information on the check list that you have indicated “by GC” will need to be provided with your submittal in order for us to accept it, or you have the option of submitting after the architect has submitted the tenant improvement to address the code required information.

Sorry for the confusion but the information needed to make a complete submittal has not been received as you indicated.


Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####

Intake Approval  3/28/2014 FAIL
DetailsAdele J Schaffeld-Griffin
see check list and email in plan reviewer activity for items needed
First Notice 1/22/2015