Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD14-00736
StatusFinaled
Name FOOTHILL CONSTRUCTION
Site Address 5488 W ALBATROS LN
Project NameWIRB Building
Customer NumberBLD13-01938
ePlanReviewNo
Description
(WIRB)This permit is to construct a warehouse/office building and associated site work only. This building has 2 building permits associated with it for each of the 2 individual units. The 5,400 square foot pre-engineered metal building with wood framed interior will be separated into 2 tenant spaces. Each TI is required to acquire individual certificates of occupancy. The framed area above the office shall be signed “NO STORAGE”. The ceiling for the office was not designed to support any storage loading. Each tenant space is (2,7010 sq ft, consisting of 563 sq ft office and 2,137 sq ft shop.) This is a VB building of non-separated use. This building is NOT fire sprinklered. All construction per the approved plans and attached comment list. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 11/13/201411/28/2014 DONE
DetailsChristina Prado
First Notice 10/19/201411/3/2014 DONE
Permanent Occupancy  10/9/2014 DONE
DetailsCandy A. Nichols
BLD-Final10/8/201410/8/201410/8/2014PPASS
DetailsJim Storey
FIRE-Final Inspection10/6/201410/7/201410/7/2014PPASS
DetailsTroy Cobbley
Life safety passed. Address and sticker to be mounted prior to a building sign off.
BLD-Conference8/6/20148/7/20148/7/2014PPASS
DetailsJim Storey
Dave-please call 1 hr prior Phone #: ###-####
Issue PAID IN FULL permit  4/22/2014 DONE
DetailsTisha Gallop
Plan assigned to (AJS) 3/28/20144/21/2014 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Western International Recovery Bureau
Routing - PLAN CHECK  4/21/2014 PASS
DetailsAdele J Schaffeld-Griffin
Case Summary (BLD)  4/21/2014 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  4/21/2014 DONE
Print Occupancy Form  4/21/2014 DONE
DetailsTisha Gallop
Permit Ready to Issue  4/21/2014 DONE
DetailsChristina Prado
Routing - FIRE4/14/20144/14/20144/14/2014 PASS
DetailsCraig D. Hanson
See attached Fire Plan Report
Routing - PUBLIC WORKS4/11/2014 4/11/2014 PASS
DetailsConnie Baumgartner
Plan resubmittals received  4/11/2014 DONE
DetailsChristina Prado
Received three set of revised plan sheets marked M-1, M-2 & P-1;Taken to Adele for further review
Routing - FIRE3/31/20143/31/20144/9/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 04-09-14
Routing - PLAN CHECK4/1/2014 4/2/2014 FAIL
DetailsAdele J Schaffeld-Griffin
email sent 4-2-14 see BLD13-01938 for all documents

I have completed the second review for the WIRB building. Please see the attached document. The door hardware was not corrected on the plans and I have red lined them. Please be sure to read the information on the correct door hardware for construction. The only item I am missing is the re submitted mechanical sheet was not stamped by the mechanical engineer of record. Please submit 2 sets of the revised mechanical sheets with the mechanical engineers stamp.

Thank you

Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####

1st review completed  4/2/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Environmental4/2/2014 4/2/2014 PASS
DetailsWalt Baumgartner
Flamm incpt to be installed per plumbing div
Routing - PLUMBING4/1/2014 4/1/2014 PASS
DetailsDaryl Spivey
Need to meet cross sectional area venting requirements and install flammabe liquids interceptor as included diagram in plan.
Routing - PUBLIC WORKS3/31/2014 4/1/2014 FAIL
DetailsConnie Baumgartner
Routing - Addressing3/31/2014 3/31/2014 PASS
DetailsJason C. Taylor
Routing PW Environmental3/31/2014 3/31/2014 FAIL
DetailsWalt Baumgartner
City approved flammable liquids oil/water/sediment separator required.
Plans ACCEPTED BY PLAN TECH  3/28/2014 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  3/28/2014 DONE
DetailsChristina Prado
Need to verify valuation prior to calculating fees. Additional permit created for second space without updated valuation certificate
Application received 3/28/2014