Letter of compliance/Occupancy | | | 6/30/2014 | | DONE |
Barbara Stitt
|
|
|
|
DOC - L/C Approved | | | 6/30/2014 | | DONE |
|
|
|
|
BLD-Final | 6/17/2014 | 6/17/2014 | 6/17/2014 | P | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####
|
BLD-Final | 6/10/2014 | 6/11/2014 | 6/12/2014 | P | PEND |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
FIRE-Final Inspection | 6/10/2014 | 6/11/2014 | 6/11/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety passed. Structural inspector to verify pocket door install prior to final as discussed.
|
BLD-Conference | 6/6/2014 | 6/9/2014 | 6/9/2014 | A | PASS |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/28/2014 | 5/28/2014 | 5/28/2014 | P | PASS |
Dave Hannah
|
|
|
mark Phone #: ###-####
|
BLD-Framing/Rough-in | 5/13/2014 | 5/13/2014 | 5/13/2014 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Ceiling Grid Inspection | 5/12/2014 | 5/13/2014 | 5/13/2014 | P | PASS |
Dave Hannah
|
|
|
Mark-drywall ceiling Phone #: ###-####
|
BLD-Conference | 4/30/2014 | 4/30/2014 | 4/30/2014 | P | PASS |
Dave Hannah
|
|
|
mark Phone #: ###-####
|
Plan assigned to (AJS) | 4/3/2014 | 4/3/2014 | 4/28/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Due 4-29 Level 3 TI - ePlanReview - Chandlers
|
Routing - PLAN CHECK | 4/3/2014 | | 4/28/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 4/28/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/28/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 4/28/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 4/28/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 4/3/2014 | 4/3/2014 | 4/8/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 04-08-14
|
Routing - PLUMBING | 4/3/2014 | | 4/7/2014 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing PW Sewer Rating | 4/3/2014 | | 4/7/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 4/3/2014 | | 4/3/2014 | | PASS |
Walt Baumgartner
|
|
|
|
Routing - Addressing | 4/3/2014 | | 4/3/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 4/3/2014 | | 4/3/2014 | | PASS |
Beverly Mountain
|
|
|
|
Pending Assignment by JCB | 4/3/2014 | | 4/3/2014 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 4/2/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin. Plan Review Fees paid.
|
Intake Approval | | | 4/1/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Please re name the drawing files to meet the electronic submittal conventional naming. A.0- Cover Sheet.
2. Please provide the minimum stamping area on the sheets the trade sheets are missing the stamping area.
|
Application received | | | 3/28/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 28 2014 2:03PM
|