Print Statement | | | 12/22/2015 | | DONE |
|
|
|
sent statement with past due stamp
|
Print Statement | | | 11/9/2015 | | DONE |
|
|
|
sent past due notices
|
Print Statement | | | 9/18/2015 | | DONE |
|
|
|
|
Print Statement | | | 7/29/2015 | | DONE |
|
|
|
|
Second Notice | | 2/12/2015 | 7/9/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed 7-10-15
|
First Notice | | 1/22/2015 | 2/2/2015 | | DONE |
Christina Prado
|
|
|
mailed 2-3-15
|
Print Occupancy Form | | | 1/12/2015 | | DONE |
Christina Prado
|
|
|
|
Permanent Occupancy | | | 1/12/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Sticker installed on door as I waited.
|
BLD-Framing/Rough-in | 8/4/2014 | 8/5/2014 | 8/5/2014 | A | CANC |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/5/2014 | 8/5/2014 | 8/5/2014 | A | DONE |
Mike Jordan
|
|
|
Chris Phone #: ###-####. Grid is existing.
|
BLD-Framing/Rough-in | 6/24/2014 | 6/25/2014 | 6/25/2014 | P | PART |
Mike Jordan
|
|
|
Michael Phone #: ###-####. INterior steel stud framed walls only, pending plumbing rough in inspection. no grid.
|
BLD-Ceiling Grid Inspection | 6/24/2014 | 6/24/2014 | 6/24/2014 | P | NR |
Mike Jordan
|
|
|
Mikael Phone #: ###-####
|
OVERRIDE | | | 5/28/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/28/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 5/28/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 5/28/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 4/14/2014 | 4/14/2014 | 5/27/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed CWI-Surgical Scrub Training
|
Routing - PLAN CHECK | 5/22/2014 | | 5/27/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2014 | | DONE |
|
|
|
|
Place hold on job | 5/27/2014 | | 5/27/2014 | | DONE |
Candy A. Nichols
|
|
|
there are 2 other permits # BLD14-00794 & BLD14-00895. All three need paid before we can issue this one.
|
Place hold on job | 5/27/2014 | | 5/27/2014 | | DONE |
Candy A. Nichols
|
|
|
there are 2 other permits # BLD14-00985 & BLD14-00796. All three need paid before we can issue this one.
|
Routing - Erosion and Sediment | 5/22/2014 | | 5/23/2014 | | PASS |
Evan Jenkins
|
|
|
Waiver Letter Request Submitted and Approved
|
1st review completed | | | 5/7/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 4/14/2014 | | 5/7/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 4/14/2014 | | 4/23/2014 | | PASS |
Scott Arellano
|
|
|
See Fire Plan Review 04-23-14
|
Routing - PLUMBING | 4/14/2014 | | 4/16/2014 | | PASS |
Daryl Spivey
|
|
|
May require additional backflow protection on installed equipment.
|
Routing - Addressing | 4/14/2014 | | 4/16/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - Erosion and Sediment | 4/14/2014 | | 4/15/2014 | | FAIL |
Andy J. Long
|
|
|
Applicant intends to submit ESC plan waiver document, but no document was found uploaded to ePlan. Please upload document for approval. Changemark listed in ePlan.
|
Routing - PUBLIC WORKS | 4/14/2014 | | 4/14/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 4/14/2014 | | 4/14/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 4/14/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 4/3/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 3 2014 3:23PM
|