FIRE-Final Inspection | 12/2/2015 | 12/4/2015 | 12/4/2015 | A | PASS |
Jim Page
|
|
|
No fire sprinkler inspection, no fire alarm inspection. Life fire safety inspection passed/complete.
|
BLD-Final | 5/6/2014 | 5/7/2014 | 5/7/2014 | A | NR |
Tom Arcoraci
|
|
|
Don Phone #: ###-####
|
FIRE-Final Inspection | 5/6/2014 | 5/7/2014 | 5/7/2014 | A | FAIL |
Troy Cobbley
|
|
|
Provide suite number and install hardware on doors so that single action can be verified.
|
Permit Ready to Issue | | | 4/22/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue PAID IN FULL permit | | | 4/22/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (TLW) | 4/8/2014 | | 4/10/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 4/9/2014 | | 4/10/2014 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 4/10/2014 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 4/10/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Permit Ready to Issue | | | 4/10/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 4/10/2014 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 4/10/2014 | | DONE |
Christina Prado
|
|
|
called Don to advise permit is ready pending GC and gave fees due
|
Routing - Addressing | 4/4/2014 | | 4/8/2014 | | PASS |
Jason C. Taylor
|
|
|
Project submitted as Suite A-D, Changed to Suite 101-202. Jason Talyor ###-####
|
Routing - PUBLIC WORKS | | | 4/8/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 4/8/2014 | | 4/8/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/4/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 4/4/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/4/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | 4/4/2014 | | | |
|
|
|
|