Second Notice | | 9/7/2014 | 9/18/2014 | | DONE |
Christina Prado
|
|
|
completed 9-18-14
|
Print Statement | | | 9/18/2014 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 7/20/2014 | 8/28/2014 | | DONE |
|
|
|
|
BLD-Final | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
Permanent Occupancy | | | 7/10/2014 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 7/3/2014 | 7/7/2014 | 7/8/2014 | P | PART |
Dave Hannah
|
|
|
Mike Phone #: ###-#### ok for temp needs to change door hardwear install a grab bar in restroom
|
FIRE-Final Inspection | 7/3/2014 | 7/7/2014 | 7/7/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed. Contractor to provide single action hardware at the new restroom prior to structural final.
|
Temporary Occupancy | 7/7/2014 | 10/5/2014 | 7/7/2014 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Conference | 6/12/2014 | 6/12/2014 | 6/12/2014 | P | DONE |
Forrest France
|
|
|
On site conference with contractor regarding remodel work and existing fire sprinkler coverage.
|
BLD-Framing/Rough-in | 6/11/2014 | 6/12/2014 | 6/12/2014 | A | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
Permit Ready to Issue | | | 5/2/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 5/2/2014 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 5/2/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (AJS) | 4/15/2014 | 4/15/2014 | 4/30/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 4-28 Tonic Hair and Skin Bar
|
Routing - PLAN CHECK | 4/29/2014 | | 4/30/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 4/29/2014 | | 4/30/2014 | | PASS |
Troy James
|
|
|
approved with notes
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2014 | | DONE |
|
|
|
|
1st review completed | | | 4/28/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 4/15/2014 | | 4/28/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
need mechanical corrections
|
Routing - Addressing | 4/15/2014 | | 4/16/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PLUMBING | 4/15/2014 | | 4/16/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 4/15/2014 | | 4/16/2014 | | FAIL |
Troy James
|
|
|
eplan
|
Routing PW Sewer Rating | 4/15/2014 | | 4/16/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 4/15/2014 | | 4/15/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 4/15/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 4/10/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
I have not received notice from Bill Vandegrift that he has approved this design to be submitted without the stamp of a mechanical engineer for the plumbing and mechanical design. If Bill accepts this design please submit proof of his approval on the re submittal.
|
Application received | | | 4/9/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2014 3:11PM
|