Permit Information
Permit NumberBLD14-00904
StatusFinaled
Name JORDAN WILCOMB CONSTRUCTION
Site Address 2505 S FEDERAL WAY
Project NameDykman Electric Warehouse
Customer Number 
ePlanReviewYes
Description
Dykman Electric - Warehouse - To construct a new 14,650 square foot, one story warehouse and related site improvements. This building will be constructed of concrete tilt-up exterior walls with steel roof joists and metal roof deck. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  5/15/2015 DONE
Print Statement  5/15/2015 DONE
First Notice 3/16/20155/4/2015 DONE
DetailsCandy A. Nichols
mailed first notice 5-4-15
Permanent Occupancy  3/6/2015 DONE
Zoning Approval3/5/20153/5/20153/5/2015 DONE
DetailsAndrea Tuning
BLD-Aging Inspection3/2/20153/2/20153/2/2015 DEFR
DetailsJim Storey
pending p&z sign off
Temporary Occupancy12/31/20143/31/201512/31/2014 DONE
DetailsChristina Prado
BLD-Final12/30/201412/30/201412/30/2014PPASS
DetailsJim Storey
Jim Phone #: ###-#### pending p&z sign off
Zoning Approval Temp12/30/201412/30/201412/30/2014 DONE
DetailsAndrea Tuning
A bond has been provided for the parking lot striping, landscaping and bike rack. These items must be installed prior to permanent occupancy being issued.
FIRE-Final Inspection12/22/201412/22/201412/22/2014PPASS
DetailsForrest France
Inspection passed. Fire life safety finaled.
FIRE-Final Inspection12/19/201412/19/201412/19/2014PPART
DetailsForrest France
Fire life safety inspection completed- Final pending project related fire sprinkler permit C/N items and final.
BLD-Final12/9/201412/9/201412/9/2014PNR
DetailsJim Storey
sign off card is right inside the building//Jim Phone #: ###-####
FIRE-Final Inspection11/7/201411/7/201411/7/2014PDONE
DetailsForrest France
On site conference regarding project related fire alarm work, knox box, address numbers, outside WF bell and FDC placements.
BLD-Framing/Rough-in10/24/201410/24/201410/24/2014PPASS
DetailsJim Storey
Jim Phone #: ###-####
CHANGE STATUS TO (ISS)  10/6/2014 DONE
DetailsCandy A. Nichols
Routing - PLAN CHECK10/1/2014 10/2/2014 PASS
DetailsJohn Menard
Routing Off Site - STRUCTURAL10/1/2014 10/2/2014 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  10/2/2014 DONE
DetailsJohn Menard
Plan assigned to (JCM)9/16/2014 10/2/2014 PASS
DetailsJohn Menard
Plan Modification for main entry. JCM
Routing Off Site - STRUCTURAL9/25/2014 9/29/2014 FAIL
DetailsJohn Menard
Routing - Design Review9/16/2014 9/25/2014 PASS
DetailsAndrea Tuning
Routing - FIRE9/16/2014 9/22/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 3 09-22-14
Routing Off Site - STRUCTURAL9/16/2014 9/19/2014 FAIL
DetailsJohn Menard
Routing - PLAN CHECK9/16/2014 9/17/2014 PASS
DetailsJohn Menard
BLD-Other8/13/20148/14/20148/14/2014APASS
DetailsJim Storey
rebar .. Jim Phone #: ###-####
BLD-Foundation7/25/20147/28/20147/28/2014APASS
DetailsJim Storey
Jim-rebar Phone #: ###-#### wall panel rebar pending si report
CHANGE STATUS TO (ISS)  7/17/2014 DONE
DetailsTisha Gallop
plan mod approved and paid
BLD-Foundation7/15/20147/15/20147/15/2014PPASS
DetailsJim Storey
after 5:00 vapor barrior in place for slab floor ok to place.
OVERRIDE  7/9/2014  
BLD-Footing7/8/20147/9/20147/9/2014APART
DetailsJim Sly
Jim-###-####-pour time 10:00
90% footing.......Less ramp area and approx 12' section West wall .......OK .Pending MTI special inspection, tests and approvals.
PLANS/APPL TAKEN TO FRONT DESK  7/9/2014 DONE
DetailsJohn Menard
Permit Ready to Issue  7/9/2014 DONE
DetailsTisha Gallop
per JCM no hourly fee for plan modification. There is additional fee due to increased value.
Plan assigned to (JCM)7/7/2014 7/9/2014 PASS
DetailsJohn Menard
Routing - PLAN CHECK7/7/2014 7/9/2014 PASS
DetailsJohn Menard
Routing - Design Review7/7/2014 7/7/2014 PASS
DetailsAndrea Tuning
Plan Modification Accepted  7/7/2014 DONE
started workflow
BLD-Conference6/24/20146/25/20146/25/2014APASS
DetailsJim Storey
Jim Phone #: ###-####
BLD-Conference6/24/20146/24/20146/24/2014PDEFR
DetailsJim Storey
Jim Phone #: ###-####
OVERRIDE  6/12/2014  
Issue PAID IN FULL permit  6/12/2014 DONE
DetailsChristina Prado
Print Occupancy Form  6/12/2014 DONE
DetailsChristina Prado
Permit Ready to Issue  6/12/2014 DONE
DetailsTisha Gallop
Routing - FIRE6/11/20146/11/20146/11/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 2 06-11-14. Removed Spec warehouse requirement
PLANS/APPL TAKEN TO FRONT DESK  6/10/2014 DONE
DetailsJohn Menard
Routing - PLAN CHECK6/4/2014 6/10/2014 PASS
DetailsJohn Menard
Routing Off Site - STRUCTURAL6/4/2014 6/10/2014 PASS
DetailsJohn Menard
Plan assigned to (JCM)4/21/2014 6/10/2014 PASS
DetailsJohn Menard
1st Review Complete 5/12/2014
Routing - PLANNING Land Div6/4/2014 6/4/2014 PASS
DetailsDave Abo
Routing Off Site - STRUCTURAL5/19/2014 5/27/2014 FAIL
DetailsJohn Menard
Routing - PLAN CHECK5/19/2014 5/21/2014 PASS
DetailsJohn Menard
Routing - FIRE5/19/2014 5/21/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 05-21-14
Routing - PLANNING Land Div5/19/2014 5/19/2014 FAIL
DetailsDave Abo
1st review completed  5/12/2014 DONE
DetailsJohn Menard
1st review completed  5/12/2014 FAIL
DetailsJohn Menard
Routing - PLAN CHECK4/21/2014 5/12/2014 FAIL
DetailsJohn Menard
Routing PW Drainage4/21/2014 5/5/2014 PASS
DetailsBrian Murphy
Routing PW Solid Waste4/21/2014 5/5/2014 PASS
DetailsPeter J. McCullough
Routing Off Site - STRUCTURAL4/21/2014 5/2/2014 FAIL
DetailsJohn Menard
Routing PW Street Lights4/21/2014 5/1/2014 PASS
DetailsMike D Hedge
No lights required
Routing - FIRE4/21/20144/21/20144/28/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 04-28-14
Routing PW Sewer Design4/21/2014 4/23/2014 PASS
DetailsKyle S. Rosenmeyer
Routing - Erosion and Sediment4/21/2014 4/22/2014 PASS
DetailsEvan Jenkins
Routing - PLUMBING4/21/2014 4/22/2014 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - PLANNING Land Div4/21/2014 4/22/2014 FAIL
DetailsTodd Tucker
ROS14-00020 must be recorded prior to issuance of the Building Permit.
Routing PW Environmental4/21/2014 4/22/2014 PASS
DetailsWalt Baumgartner
Route to Impact Fee Review4/21/20144/24/20144/21/2014 PASS
DetailsCindy M. Gould
Routing PW Sewer Rating4/21/2014 4/21/2014 PASS
DetailsConnie Baumgartner
Routing - PUBLIC WORKS4/21/2014 4/21/2014 PASS
DetailsConnie Baumgartner
Routing - Design Review4/21/2014 4/21/2014 PASS
DetailsAndrea Tuning
Intake Approval  4/21/2014 PASS
DetailsTim L. Woodard
Approved. Legal Lot form not signed. OK by Todd to take in; however, project cannot be issued until complete. TLW
Pending Assignment by JCM4/21/2014 4/21/2014 DONE
DetailsJohn Menard
Routing - Addressing4/21/2014 4/21/2014 PASS
DetailsEmily Dixon
Application received  4/15/2014 DONE
Application submitted via PDS Online on Apr 15 2014 8:45AM