Second Notice | | 12/20/2015 | 1/4/2016 | | DONE |
|
|
|
This permit finaled on the web by Kirk Ledbetter
|
First Notice | | 11/16/2015 | 12/10/2015 | | DONE |
|
|
|
Mailed 12-11-15
|
Permanent Occupancy | | | 11/6/2015 | | DONE |
|
|
|
|
BLD-Final | 11/4/2015 | 11/5/2015 | 11/5/2015 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. Ok to occ. 1st. floor.
|
BLD-Final | 10/15/2014 | 10/15/2014 | 10/16/2014 | P | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### ok for temp occ ok for perm occ after mec gos perm
|
FIRE-Final Inspection | 10/14/2014 | 10/15/2014 | 10/15/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection okay for final pending directional arrows as discussed at two exit signs, remove keyed locking hardware at the conference room door. Items to be finished prior to structural final as agreed. Inspection passed.
|
BLD-Ceiling Grid Inspection | 9/15/2014 | 9/16/2014 | 9/16/2014 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
Print Occupancy Form | | | 9/15/2014 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 9/15/2014 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/15/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 9/4/2014 | | 9/10/2014 | | PASS |
Carl Westfall
|
|
|
PLAN MODIFICATION
|
Routing - PLAN CHECK | 9/4/2014 | | 9/10/2014 | | PASS |
Carl Westfall
|
|
|
Plan mod approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2014 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 9/4/2014 | | |
|
|
|
|
Plan Modification Accepted | | | 9/2/2014 | | DONE |
Candy A. Nichols
|
|
|
per applicant started plan mod
|
BLD-Framing/Rough-in | 8/14/2014 | 8/15/2014 | 8/15/2014 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
BLD-Framing/Rough-in | 8/12/2014 | 8/13/2014 | 8/15/2014 | P | PASS |
Dave Hannah
|
|
|
John Hare Phone #: ###-####
|
OVERRIDE | | | 6/4/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/4/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 6/4/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/4/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 4/24/2014 | 4/24/2014 | 5/21/2014 | | PASS |
Carl Westfall
|
|
|
WASHINGTON FEDERAL - 1ST STORY - Level 3 TI - ePlanReview (15 days - May 13)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2014 | | DONE |
|
|
|
|
Routing - FIRE | 5/16/2014 | | 5/20/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 05-20-14
|
Routing - PLUMBING | 5/16/2014 | | 5/19/2014 | | PASS |
Bill VanDegrift
|
|
|
Added drinking fountains
|
Routing PW Sewer Rating | 5/16/2014 | | 5/19/2014 | | PASS |
Connie Baumgartner
|
|
|
Added drinking fountains
|
Routing - PLAN CHECK | 5/14/2014 | | 5/16/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines".
|
Plan resubmittals received | | | 5/14/2014 | | DONE |
|
|
|
|
1st review completed | | | 5/8/2014 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/8/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/24/2014 | | 5/8/2014 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - Erosion and Sediment | 4/24/2014 | | 5/5/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - FIRE | 4/24/2014 | 4/24/2014 | 4/28/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 04-28-14
|
Routing - PLUMBING | 4/24/2014 | | 4/25/2014 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing PW Sewer Rating | 4/24/2014 | | 4/25/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 4/24/2014 | | 4/24/2014 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 4/24/2014 | | 4/24/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 4/24/2014 | | 4/24/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 4/23/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Application received | | | 4/16/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2014 12:31PM
|