First Notice | | 6/27/2015 | 7/9/2015 | | DONE |
|
|
|
Mailed 7-10-15
|
Permanent Occupancy | | | 6/17/2015 | | DONE |
|
|
|
|
BLD-Final | 6/15/2015 | 6/16/2015 | 6/16/2015 | A | PASS |
Dave Hannah
|
|
|
PLM permit it with a different address. PLM15-01729 // Cody Phone #: ###-####
|
BLD-Final | 6/10/2015 | 6/11/2015 | 6/11/2015 | A | NR |
Jim Sly
|
|
|
Amber Phone #: ###-####// wont be there until 9am Need Plumbing permit and final plumbing approval.
|
BLD-Final | 4/22/2015 | 4/24/2015 | 4/24/2015 | A | FAIL |
Dave Hannah
|
|
|
Call ahead for access - Bobby Phone #: ###-#### sink is in the wrong place ada restroom
|
FIRE-Final Inspection | 4/22/2015 | 4/23/2015 | 4/23/2015 | A | PASS |
Katie Marron
|
|
|
Life Safety Pass. Verified new bathroom hardware exceptable.
|
BLD-Final | 2/27/2015 | 3/2/2015 | 3/3/2015 | P | NR |
Dave Hannah
|
|
|
Gene Phone #: ###-####
|
FIRE-Final Inspection | 2/27/2015 | 3/2/2015 | 3/2/2015 | A | FAIL |
Forrest France
|
|
|
Need to provide approved hardware per approved plans, last inspection activity notes dated 7/29/14 and today's on site discussion with property rep.
|
FIRE-Final Inspection | 7/28/2014 | 7/29/2014 | 7/29/2014 | A | FAIL |
Troy Cobbley
|
|
|
Provide ADA approved hardware, per the approved plans on the Rec Room and the Managers Restroom doors.
|
BLD-Final | 7/28/2014 | 7/28/2014 | 7/29/2014 | P | NR |
Dave Hannah
|
|
|
Joel-please call prior to inspection Phone #: ###-#### needs other trades finaled first
|
BLD-Framing/Rough-in | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PASS |
Jim Sly
|
|
|
Joel-requests as early as possible Phone #: ###-####
|
BLD-Framing/Rough-in | 7/14/2014 | 7/14/2014 | 7/14/2014 | P | PART |
Jim Storey
|
|
|
Joel-Suite 104 please call when you get there Phone #: ###-#### need plm and ele// firestop plm.
|
BLD-Ceiling Grid Inspection | 7/3/2014 | 7/3/2014 | 7/3/2014 | P | NR |
Jim Sly
|
|
|
Joel Phone #: ###-####
|
BLD-Conference | 6/18/2014 | 6/19/2014 | 6/19/2014 | A | PASS |
Jim Storey
|
|
|
Colby Phone #: ###-#### reviewed floor/ceilling protection and fur down.
|
BLD-Framing/Rough-in | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | PART |
Jim Storey
|
|
|
call for access code - Colby Phone #: ###-#### post and beam ok
|
Print Occupancy Form | | | 5/22/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 5/22/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 5/22/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 4/18/2014 | 4/18/2014 | 5/16/2014 | | PASS |
Carl Westfall
|
|
|
MORRISON PARK APARTMENTS - FITNESS FACILITY - Level 3 TI - ePlan Review - (15 days - May 8)
|
Routing - PLAN CHECK | 5/14/2014 | | 5/16/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/14/2014 | | DONE |
|
|
|
|
1st review completed | | | 4/29/2014 | | DONE |
|
|
|
Failed building
|
Plan resubmittals requested | | | 4/29/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/18/2014 | | 4/29/2014 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - FIRE | 4/18/2014 | 4/18/2014 | 4/25/2014 | | PASS |
Craig D. Hanson
|
|
|
See attached report 04-25-14
|
Routing PW Sewer Rating | 4/18/2014 | | 4/21/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 4/18/2014 | | 4/21/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 4/18/2014 | | 4/18/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 4/18/2014 | | FAIL |
|
|
|
Please provide the structural engineers stamp on the structural sheet.
This T.I will be routed as a major tenant improvement.
|
Intake Approval | | | 4/18/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen. Plan review fees paid.
|
Pending Assignment by JCB | 4/18/2014 | | 4/18/2014 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 4/17/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 17 2014 3:12PM
|