Second Notice | | 9/16/2014 | 10/23/2014 | | DONE |
Candy A. Nichols
|
|
|
|
First Notice | | 9/21/2014 | 10/6/2014 | | DONE |
|
|
|
|
BLD-Final | 9/9/2014 | 9/11/2014 | 9/11/2014 | A | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####-no mechanical work done
|
Permanent Occupancy | | | 9/11/2014 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 9/9/2014 | 9/10/2014 | 9/10/2014 | A | PASS |
Forrest France
|
|
|
Phase four fire life safety completed satisfactory. Scope of work finished. Inspection passed.
|
FIRE-Conference | 9/9/2014 | 9/9/2014 | 9/9/2014 | P | DONE |
Forrest France
|
|
|
Regarding inspection schedule and project related permit work
|
BLD-Framing/Rough-in | 8/18/2014 | 8/19/2014 | 8/19/2014 | A | PART |
Tony Young
|
|
|
mike - phase 4 Phone #: ###-####,, walls ok
|
BLD-Final | 8/4/2014 | 8/6/2014 | 8/6/2014 | A | PART |
Tony Young
|
|
|
Mike-phase 2 & 3 Phone #: ###-####,, phase 2 and 3 final ok
|
FIRE-Final Inspection | 8/4/2014 | 8/5/2014 | 8/5/2014 | A | PART |
Forrest France
|
|
|
Fire life safety at the second floor phases two and three completed satisfactory.
|
BLD-Framing/Rough-in | 6/12/2014 | 6/13/2014 | 6/13/2014 | P | PASS |
Tony Young
|
|
|
Mike-phase 3 area Phone #: ###-####
|
BLD-Framing/Rough-in | 6/10/2014 | 6/11/2014 | 6/11/2014 | A | PASS |
Jim Sly
|
|
|
Phase 1 - Mike Phone #: ###-####
|
FIRE-Final Inspection | 6/5/2014 | 6/5/2014 | 6/5/2014 | P | PART |
Forrest France
|
|
|
"Phase one" area fire life safety inspection completed acceptable.
|
BLD-Framing/Rough-in | 5/21/2014 | 5/22/2014 | 5/22/2014 | A | PASS |
Tony Young
|
|
|
mike - 2nd phase on the 2nd floor Phone #: ###-####
|
BLD-Framing/Rough-in | 5/5/2014 | 5/6/2014 | 5/6/2014 | A | PASS |
Tony Young
|
|
|
Mike-Phase 3 Phone #: ###-####
|
BLD-Framing/Rough-in | 4/29/2014 | 4/30/2014 | 4/30/2014 | P | PASS |
Tony Young
|
|
|
Mike Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/29/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | 4/18/2014 | 4/28/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/28/2014 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/28/2014 | | DONE |
Tisha Gallop
|
|
|
called Sam Burrows and left vm permit is ready, fee due and need GC.
|
Plan assigned to (CDM) | 4/18/2014 | 4/18/2014 | 4/25/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 4/18/2014 | | 4/25/2014 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 4/25/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/25/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/25/2014 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/18/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 4/18/2014 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/18/2014 | | DONE |
Christina Prado
|
|
|
|