BLD-Final | 11/24/2014 | 11/25/2014 | 11/25/2014 | A | PASS |
Jim Sly
|
|
|
co// Barb Phone #: ###-####
|
DOC - Permit Finaled | 11/25/2014 | 11/25/2014 | 11/25/2014 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 9/4/2014 | 9/5/2014 | 9/4/2014 | A | PASS |
Jim Sly
|
|
|
Barb Phone #: ###-####
|
BLD-Framing/Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | PASS |
Jim Sly
|
|
|
Barb-please call before Phone #: ###-#### Energy OK too.
|
Plan Modification Accepted | | | 8/6/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 8/6/2014 | | 8/6/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Wall Bracing | 7/28/2014 | 7/28/2014 | 7/28/2014 | P | PASS |
Jim Sly
|
|
|
Barbara Phone #: ###-####
|
BLD-Conference | 7/24/2014 | 7/24/2014 | 7/24/2014 | P | DONE |
Jim Sly
|
|
|
Barb-says should only take about 5 min. Phone #: ###-####
|
BLD-Foundation | 7/11/2014 | 7/14/2014 | 7/14/2014 | A | PASS |
Jim Sly
|
|
|
Larry (alt contact is Barb ###-####) Phone #: ###-####
|
BLD-Footing | 6/27/2014 | 6/30/2014 | 7/1/2014 | P | PART |
Tony Young
|
|
|
Joe Phone #: ###-####,, last part of wall,, work in progress
|
BLD-Foundation | 6/26/2014 | 6/26/2014 | 6/26/2014 | P | PART |
Dave Hannah
|
|
|
Joe Phone #: ###-#### north half ok to place concrete
|
BLD-Footing | 6/23/2014 | 6/24/2014 | 6/24/2014 | A | PASS |
Jim Sly
|
|
|
Barb Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/13/2014 | | DONE |
Candy A. Nichols
|
|
|
|
OVERRIDE | | | 5/14/2014 | | |
|
|
|
|
Routing - PLANNING | 5/14/2014 | | 5/14/2014 | | PASS |
Susan Riggs
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/14/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/14/2014 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 5/14/2014 | | DONE |
Christina Prado
|
|
|
called American building to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 5/14/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLANNING | 4/29/2014 | | 5/9/2014 | | FAIL |
Susan Riggs
|
|
|
Susan Riggs CAA14-10
I called the applicant on 4-29-14. They are working on getting the required cross access agrement to me for parking. This has to be reviewed by legal and then recorded.
5-9-14 I called the applicant and they just got the cross access agreements drawn up. They will deliver to me this afternoon and then I have to send them to legal for their approval. This could take a week or so. I’ll ask they to try to get to them asap.
|
Plan assigned to (PEP) | 5/5/2014 | 5/5/2014 | 5/5/2014 | | FAIL |
Perry Paine
|
|
|
|
Plan assigned to (JG) | 4/25/2014 | 4/25/2014 | 5/5/2014 | | DEFR |
Javier Guzman
|
|
|
Due 5/08 TH L1 Duplex
|
Routing - PLAN CHECK | 4/30/2014 | | 5/5/2014 | | PASS |
Perry Paine
|
|
|
need CVA14-00010 approved by Planning & Zoning 5-5-2014 pep
Approved by planning 5-14-2014 pep
|
1st review completed | | | 5/5/2014 | | FAIL |
|
|
|
Need Zoning Signoff for CVA14-00010 5-5-2014 pep
|
Route to Impact Fee Review | 4/25/2014 | 4/28/2014 | 5/1/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 4/29/2014 | | 4/30/2014 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 4/25/2014 | | 4/29/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 4/25/2014 | | 4/28/2014 | | PASS |
Jason C. Taylor
|
|
|
Duplex (2652 & 2654 N Maple Grove)
|
Application received | | 4/21/2014 | 4/25/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/25/2014 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/25/2014 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 4/25/2014 | | PASS |
Tisha Gallop
|
|
|
|
Intake Approval | | | 4/21/2014 | | FAIL |
Christina Prado
|
|
|
Res Check & attic access
|