BLD-Final | 6/25/2015 | 6/25/2015 | 6/25/2015 | P | PASS |
Tony Young
|
|
|
Dave Phone #: ###-####
|
DOC - Permit Finaled | 6/25/2015 | 6/25/2015 | 6/25/2015 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 6/24/2015 | 6/25/2015 | 6/25/2015 | A | DEFR |
Tony Young
|
|
|
Dave Phone #: ###-####,, moved to pm
|
PubWorks Occupancy Approval | 4/22/2015 | 4/22/2015 | 4/22/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Wall cover | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PASS |
Phil Shearer
|
|
|
Soffit firewall inspection for WUI Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Energy code compliance | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Framing/Rough-in | 10/17/2014 | 10/17/2014 | 10/17/2014 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper,, ok to insulate
|
BLD-Framing/Rough-in | 10/16/2014 | 10/17/2014 | 10/17/2014 | A | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Framing/Rough-in | 10/16/2014 | 10/16/2014 | 10/16/2014 | P | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper,, need electrical 1st,, dont insulate
|
BLD-Wall Bracing | 9/30/2014 | 9/30/2014 | 9/30/2014 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Foundation | 8/28/2014 | 8/29/2014 | 8/29/2014 | P | PART |
Tony Young
|
|
|
Adam-concrete set for 3:30 Phone #: ###-####,, work in progress,, ok to pour when ready
|
BLD-Footing | 8/28/2014 | 8/28/2014 | 8/28/2014 | P | PART |
Tony Young
|
|
|
Adam-concrete set for 1:30 Phone #: ###-####,, work in progress,, ok
|
BLD-Footing | 8/27/2014 | 8/27/2014 | 8/27/2014 | P | NR |
Phil Shearer
|
|
|
pouring at 4 - .Adam Phone #: ###-####
|
PubWorks Subgrade Approval | 8/27/2014 | 8/27/2014 | 8/27/2014 | | DONE |
Jason C. Taylor
|
|
|
*REMOVE ALL LOOSE MATERIAL* A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 8/22/2014 | 8/22/2014 | 8/22/2014 | P | NR |
Tony Young
|
|
|
pour time 3:30 // Adam Phone #: ###-####
|
BLD-Footing | 8/21/2014 | 8/22/2014 | 8/22/2014 | A | NR |
Tony Young
|
|
|
pour time 3:30 // Adam Phone #: ###-####
|
BLD-Footing | 8/21/2014 | 8/21/2014 | 8/21/2014 | P | NR |
Tony Young
|
|
|
pour time 3:30 // Adam Phone #: ###-####
|
BLD-Footing | 8/14/2014 | 8/15/2014 | 8/15/2014 | P | CANC |
Tony Young
|
|
|
Shawn-pour time 1:00 Phone #: ###-#### //cancelled per phone call form Shawn 8/15/14 10:45am..leg
|
BLD-Foundation | 8/14/2014 | 8/15/2014 | 8/15/2014 | P | CANC |
Tony Young
|
|
|
Kent Phone #: ###-#### /// cancelled per phone call form Shawn 8/15/14 10:45am..leg
|
PubWorks Subgrade Approval | 8/15/2014 | 8/15/2014 | 8/15/2014 | | DONE |
Jason C. Taylor
|
|
|
*NO WET SOILS UNDER FOOTINGS* A letter from the applicant’s geotechnical engineer indicating that the entire footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 8/12/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/12/2014 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 8/12/2014 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 8/12/2014 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 7/18/2014 | | |
|
|
|
|
Plan assigned to (JG) | 5/9/2014 | 5/9/2014 | 7/18/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, Due 5/28 W L2 Hillside ePlan**
|
Routing - PLAN CHECK | 5/28/2014 | | 7/18/2014 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/18/2014 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 5/28/2014 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing - PLAN CHECK | 5/9/2014 | | 5/28/2014 | | FAIL |
Javier Guzman
|
|
|
Eplan review
|
Routing - FIRE | 5/9/2014 | 5/9/2014 | 5/12/2014 | | PASS |
Scott Arellano
|
|
|
Approved as shown. This structure has been evaluted for FD vehicle access.
|
Routing PW Grading-Hillside | 5/9/2014 | | 5/12/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - MECHANICAL | 5/9/2014 | | 5/12/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/9/2014 | | 5/9/2014 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/9/2014 | | 5/9/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/9/2014 | | 5/9/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 5/9/2014 | | 5/9/2014 | | PASS |
Evan Jenkins
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/9/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/9/2014 | | PASS |
Candy A. Nichols
|
|
|
4/23/14
|
Recd Pcfee & Taken To Pln CK | | | 5/9/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 4/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 22 2014 11:23AM
|