First Notice | | 12/21/2014 | 1/2/2015 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 12/11/2014 | 12/11/2014 | 12/11/2014 | | DONE |
Brian Murphy
|
|
|
as per Brian Murphy final was done 12-10-14
|
BLD-Final | 12/11/2014 | 12/11/2014 | 12/11/2014 | A | DONE |
Jim Storey
|
|
|
as per Jim Storey 301 final passed
|
Permanent Occupancy | | | 12/11/2014 | | DONE |
|
|
|
|
BLD-Final | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | PART |
Jim Storey
|
|
|
steve Phone #: ###-#### final ok pending pw
|
FIRE-Final Inspection | 12/1/2014 | 12/1/2014 | 12/1/2014 | P | PASS |
Forrest France
|
|
|
Life safety inspection passed.
|
BLD-Footing | 9/30/2014 | 9/30/2014 | 9/30/2014 | P | FAIL |
Mike Jordan
|
|
|
Craig Phone #: ###-####. Install reinforcement per approved plans. Bottom reinforcement is required to be epoxied into existing footing and requires special inspection. Noted to contractor if he still wants to place concrete in the a.m. to have special inspector inspect and verify proper construction for column pad footings against existing building.
|
BLD-Foundation | 9/10/2014 | 9/11/2014 | 9/11/2014 | A | PASS |
Mike Jordan
|
|
|
Craig Phone #: ###-####
|
BLD-Footing | 9/8/2014 | 9/8/2014 | 9/8/2014 | P | PASS |
Jim Storey
|
|
|
Craig Phone #: ###-####
|
OVERRIDE | | | 8/6/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/6/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 8/6/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 8/6/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 6/25/2014 | | 8/1/2014 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing Off Site - STRUCTURAL | 8/1/2014 | | 8/1/2014 | | PASS |
Carl D Madsen
|
|
|
Passed with conditions for the new front door awning. Redlines added to the plans sheets to provide additional engineering to the field inspector. CDM
|
Routing - PLAN CHECK | 8/1/2014 | | 8/1/2014 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 8/1/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2014 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/25/2014 | | 7/16/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/25/2014 | | 7/16/2014 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 7/16/2014 | | FAIL |
|
|
|
|
Routing PW Drainage | 6/25/2014 | | 7/14/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING Land Div | 6/25/2014 | | 7/1/2014 | | PASS |
Dave Abo
|
|
|
Parcel is a consolidation of two platted lots.
|
Route to Impact Fee Review | 6/25/2014 | 6/30/2014 | 6/30/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 6/25/2014 | 6/25/2014 | 6/30/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-30-14
|
Routing - PUBLIC WORKS | 6/25/2014 | | 6/25/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 6/25/2014 | | 6/25/2014 | | PASS |
Andy J. Long
|
|
|
ESC site map and narrative submitted and approved. Valid RP and PD provided.
|
Routing - Design Review | 6/25/2014 | | 6/25/2014 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 6/25/2014 | | PASS |
Jason Blais
|
|
|
|
Intake Approval | | | 4/29/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Prior to beginning the prescreen please re upload the approved documents in accordance with the electronic submittal standards.
All sheet size shall be a minimum of 18"x24".
All drawings shall be uploaded individually with conventional naming. A1.0 Cover Sheet
Please provide the required stamping areas. The cover sheet shall be provided with a blank space 4"x4" located 3" from the right edge in the bottom right corner. The additional drawings shall have a 4"X2" space in the same location as the cover.
The TV Steel Addition R &R Steel Company Calculations needs to be re uploaded to read left to right.
I have uploaded the electronic submittal standars and the ESC document stating additons over 600 sq feet require full ESC narrative and plans.
Please see mark ups on the check list for the additional information and plans needed to begin the pre screen.
|
Application received | | | 4/26/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 26 2014 7:06PM
|
Pending Assignment by JCM | 6/25/2014 | | | | |
John Menard
|
|
|
|