Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD14-01091
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 1109 W MAIN ST Unit: 330
Project NameESPN Potato Bowl Suite 330
Customer Number 
ePlanReviewYes
Description
(OWYHEE PLAZA - ESPN POTATO BOWL - 3RD STORY) Fire sprinklers used for story, height, and area increase. To create a 2,312 square foot office tenant space (1,079 square foot West half and 1,216 square foot East half) on the 3rd story of an existing historic building. Shell and core upgrade work was done under permit BLD13-00938. Work is to include interior nonbearing walls, a non-rated common corridor to connect exit stairways, suspended gypsum board ceilings, suspended acoustical ceilings, interior doors, interior windows, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 (including quick-response heads where not provided) and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  9/24/2014 DONE
Second Notice 9/12/20149/18/2014 DONE
final value fee is under $100
First Notice 8/18/20149/2/2014 DONE
e-mailed to Patrick Boel and Duel Christensen @ Anderson Const
BLD-Final8/7/20148/7/20148/8/2014PPASS
DetailsDave Hannah
Permanent Occupancy  8/8/2014 DONE
DetailsTisha Gallop
FIRE-Final Inspection8/6/20148/6/20148/7/2014PPASS
DetailsForrest France
Fire life safety inspection passed.
BLD-Ceiling Grid Inspection7/1/20147/2/20147/2/2014APART
DetailsDave Hannah
Jim Phone #: ###-#### ceiling above grid ok
BLD-Ceiling Grid Inspection6/27/20146/30/20146/30/2014ANR
DetailsDave Hannah
Jim Phone #: ###-####
BLD-Wall cover6/9/20146/9/20146/9/2014PPASS
DetailsDave Hannah
Jim Phone #: ###-####
BLD-Wall cover6/2/20146/3/20146/3/2014APART
DetailsDave Hannah
Jim Phone #: ###-#### ok to one side
Permit Ready to Issue  6/2/2014 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  6/2/2014 DONE
DetailsBarbara Stitt
Print Occupancy Form  6/2/2014 DONE
DetailsBarbara Stitt
1st review completed  5/9/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/9/2014 DONE
Plan assigned to (CJW)5/1/2014 5/9/2014 PASS
DetailsCarl Westfall
OWYHEE PLAZA - ESPN POTATO BOWL (9 days - May 13) Level II TI
Routing - PLAN CHECK5/1/2014 5/9/2014 PASS
DetailsCarl Westfall
Approved with "red lines".
Routing - FIRE5/1/2014 5/7/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review 05-07-14
Routing PW Sewer Rating5/6/2014 5/7/2014 PASS
DetailsConnie Baumgartner
Routing - Addressing5/1/2014 5/6/2014 PASS
DetailsEmily Dixon
Suite is on the 3rd Floor.
Routing - PUBLIC WORKS5/1/2014 5/6/2014 PASS
DetailsBeverly Mountain
Intake Approval  5/1/2014 PASS
DetailsTim L. Woodard
Application received  4/30/2014 DONE
Application submitted via PDS Online on Apr 30 2014 10:50AM