Permit Information
Permit NumberBLD14-01098
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 900 N LIBERTY ST STE Unit: 202
Project NameST AL'S OFFICE #5-2ND FLR
Customer Number 
ePlanReviewNo
Description
(ST AL'S OFFICE MOB BLDG #5 – FAMILY CARE CENTER – Ste# 202) Permit to combine two tenant spaces on the second floor to create a 5,465 square foot medical office space. These two spaces were previously occupied under BLD99-03712 and BLD99-02753. Scope of work: (construct interior non-combustible non-bearing walls to create an exam room, classrooms, kitchen / break room, 4 lactation rooms, 2 mental health rooms, 2 nutrition rooms, 3 offices, meds room, waiting / reception, accessible restrooms and support areas for family care clinic), install electrical, plumbing, mechanical, suspended ceiling grid system per CISCA 0-2 with supported fixtures, interior millwork, installation of folding wall assembly, door assemblies & finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  9/18/2015 DONE
Print Statement  12/15/2014 DONE
DetailsCandy A. Nichols
First Notice 11/3/201412/1/2014 DONE
Permanent Occupancy  10/24/2014 DONE
DetailsChristina Prado
BLD-Final10/23/201410/23/201410/23/2014PPASS
DetailsMike Jordan
Jeff Phone #: ###-####. Ok for perm occ.
BLD-Final10/15/201410/16/201410/16/2014APART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Jeff Fahey ok for temp occ but ada rest rooms do not have 5 ft between sink and tolit.wall
FIRE-Final Inspection10/15/201410/15/201410/15/2014PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Final10/14/201410/15/201410/15/2014ANR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Jeff Fahey. Needs fire/life/safety final.
BLD-Ceiling Grid Inspection9/17/20149/17/20149/17/2014PPASS
DetailsJim Sly
Jeff Phone #: ###-####
BLD-Ceiling Grid Inspection9/16/20149/16/20149/16/2014PNR
DetailsMike Jordan
Jeff Phone #: ###-####
BLD-Framing/Rough-in8/11/20148/11/20148/11/2014PPASS
DetailsMike Jordan
Jeff Phone #: ###-####
BLD-Framing/Rough-in8/7/20148/7/20148/7/2014PPASS
DetailsMike Jordan
Jeff Phone #: ###-####. Interior steel stud framed walls ok.
BLD-Other7/22/20147/22/20147/22/2014PDEFR
DetailsMike Jordan
Welding inspection-Jeff Phone #: ###-####. Will review special inspection report.
Issue PAID IN FULL permit  6/11/2014 DONE
DetailsBarbara Stitt
Routing - FIRE6/4/20146/4/20146/4/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 2 06-04-14
PLANS/APPL TAKEN TO FRONT DESK  6/4/2014 DONE
DetailsTim L. Woodard
Case Summary (BLD)  6/4/2014 DONE
DetailsTim L. Woodard
Print Occupancy Form  6/4/2014 DONE
DetailsChristina Prado
Permit Ready to Issue  6/4/2014 DONE
DetailsTisha Gallop
Telephone call  6/4/2014 DONE
DetailsTisha Gallop
called Sam Burrows and left vm permit is ready and fee due and need GC form
Routing - PLAN CHECK5/30/2014 6/4/2014 PASS
DetailsTim L. Woodard
Plan assigned to (TLW)4/30/2014 6/4/2014 PASS
DetailsTim L. Woodard
Plan resubmittals received  6/2/2014 DONE
DetailsCandy A. Nichols
received 2 copis of a letter from LCA Architects for Craig Hanson-put in the fire box
Routing - FIRE5/29/2014 5/30/2014 FAIL
DetailsCraig D. Hanson
Correction Items from review not addressed. See Fire Plan Review Rev 1 05-30-14
Routing - PLAN CHECK5/29/2014 5/29/2014 PASS
DetailsTim L. Woodard
Routing - MECHANICAL5/20/2014 5/28/2014 PASS
DetailsTroy James
Plan resubmittals received  5/28/2014 DONE
rec'd two copies of reponse letter and sheets A0.1; A2.0; A2.2; A2.4; A3.0; A6.0; A8.0 - taken to tim
Routing - FIRE5/15/2014 5/20/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 05-20-14
1st review completed  5/20/2014 FAIL
DetailsCraig D. Hanson
Routing - PLAN CHECK5/5/2014 5/15/2014 FAIL
DetailsTim L. Woodard
Refer to plan review report. TLW
Routing - PUBLIC WORKS5/1/2014 5/5/2014 PASS
DetailsConnie Baumgartner
Routing - Addressing4/30/2014 5/1/2014 PASS
DetailsJason C. Taylor
Application received 4/30/20144/30/2014 DONE
Plans ACCEPTED BY PLAN TECH  4/30/2014 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  4/30/2014 DONE
DetailsTisha Gallop