Zoning Approval | 12/31/2014 | 12/31/2014 | 12/31/2014 | | PASS |
Sarah Schafer
|
|
|
|
Permanent Occupancy | | | 12/31/2014 | | DONE |
|
|
|
|
Temporary Occupancy | 12/29/2014 | 3/29/2015 | 12/29/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 12/11/2014 | 12/12/2014 | 12/12/2014 | A | PART |
Mike Jordan
|
|
|
Tyler Phone #: ###-####. Temp occ. Will be ok for perm occ. once zoning signs perm.
|
BLD-Final | 12/10/2014 | 12/10/2014 | 12/10/2014 | P | NR |
Mike Jordan
|
|
|
Tyler Phone #: ###-####
|
FIRE-Final Inspection | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 12/5/2014 | 12/5/2014 | 12/5/2014 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for final yet but I did verify smoke alarms
|
BLD-Energy code compliance | 10/21/2014 | 10/22/2014 | 10/22/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####
|
BLD-Energy code compliance | 10/16/2014 | 10/17/2014 | 10/17/2014 | P | PASS |
Mike Jordan
|
|
|
Richard Phone #: ###-####
|
BLD-Framing/Rough-in | 10/15/2014 | 10/16/2014 | 10/16/2014 | P | CANC |
Mike Jordan
|
|
|
Richard Phone #: ###-####. Wrong permit called in.
|
BLD-Wall Bracing | 9/18/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Mike Jordan
|
|
|
Ken Phone #: ###-####. Floor to floor straps, 1st floor shear walls ok.
|
BLD-Wall Bracing | 9/16/2014 | 9/17/2014 | 9/17/2014 | A | NR |
Jim Storey
|
|
|
Ken-exterior shear nailing Phone #: ###-####
|
BLD-Wall Bracing | 9/2/2014 | 9/3/2014 | 9/3/2014 | A | PASS |
Mike Jordan
|
|
|
Timm-would like at 11:00 if possible Phone #: ###-####. 2nd. floor interior and exterior shearwalls ok.
|
BLD-Framing/Rough-in | 8/28/2014 | 8/29/2014 | 8/29/2014 | A | CANC |
Phil Shearer
|
|
|
Ken Phone #: ###-####
|
BLD-Wall Bracing | 8/29/2014 | 8/29/2014 | 8/29/2014 | A | PASS |
Phil Shearer
|
|
|
Ken Phone #: ###-####. Interior shear wall
|
BLD-Other | 8/20/2014 | 8/21/2014 | 8/21/2014 | P | PASS |
Mike Jordan
|
|
|
Rebar - Ken Phone #: ###-####. INterior thickend footings.
|
BLD-Energy code compliance | 8/13/2014 | 8/13/2014 | 8/13/2014 | A | PASS |
Mike Jordan
|
|
|
###-#### Ashley. Rigid insulation at stemwall under slab on grade.
|
BLD-Energy code compliance | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | FAIL |
Mike Jordan
|
|
|
ashley Phone #: ###-####. Remove all debries from building footprint. Rigid insulation to be attached in approved manner.
|
BLD-Foundation | 8/7/2014 | 8/11/2014 | 8/11/2014 | A | DONE |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Foundation | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 8/6/2014 | 8/7/2014 | 8/7/2014 | P | PASS |
Mike Jordan
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 7/29/2014 | 7/30/2014 | 7/30/2014 | A | PASS |
Phil Shearer
|
|
|
Jerry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/18/2014 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 7/17/2014 | | |
|
|
|
|
Route to Impact Fee Review | 7/17/2014 | 7/22/2014 | 7/17/2014 | | PASS |
James McMahon
|
|
|
|
Routing - FIRE | 7/16/2014 | 7/16/2014 | 7/17/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 07-17-14
|
Plan assigned to (SRZ) | 5/23/2014 | 5/23/2014 | 7/17/2014 | | PASS |
Sam Zahorka
|
|
|
Pending others to PASS
|
Routing - PLAN CHECK | 7/17/2014 | | 7/17/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2014 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 7/17/2014 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 7/17/2014 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (FEE) | | | 7/17/2014 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 7/17/2014 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 7/17/2014 | | |
Christina Prado
|
|
|
called Darren to advise permit is ready pending GC & RP and gave fees due
|
Permit Ready to Issue | | | 7/17/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 6/26/2014 | | 7/16/2014 | | PASS |
Sam Zahorka
|
|
|
Routed to Fire Review
|
Routing - FIRE | 6/24/2014 | 6/24/2014 | 6/26/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 06-26-14
|
Routing - PUBLIC WORKS | 6/18/2014 | | 6/23/2014 | | PASS |
Connie Baumgartner
|
|
|
Resubmittals not inserted into set yet.
|
Routing PW Drainage | 6/18/2014 | | 6/23/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 6/23/2014 | | 6/23/2014 | | PASS |
Mike Sheppard
|
|
|
|
Routing - PLAN CHECK | 6/10/2014 | | 6/18/2014 | | PEND |
Sam Zahorka
|
|
|
Pending others to PASS
|
Plan resubmittals received | | | 6/18/2014 | | DONE |
Christina Prado
|
|
|
Received five sets of revised plan sheets marked C1, C2, C3, C4 & C5 as well as one transmittal sheet and one revised Storm Drainage Calcs packet; Plans taken to Sam for review
|
Routing - PLUMBING | 5/14/2014 | | 6/18/2014 | | PASS |
Daryl Spivey
|
|
|
|
Routing - PLAN CHECK | 6/3/2014 | | 6/6/2014 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 6/3/2014 | | DONE |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 6/3/2014 | | DONE |
Christina Prado
|
|
|
Received two revised sets of plans marked G1.0 & G2.0 as well as one response letter; Plans inserted by arch rep and returned to Sam for review
|
Routing - FIRE | 5/29/2014 | | 6/3/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-03-14
|
Routing - PLAN CHECK | | | 5/29/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - PLANNING | 5/16/2014 | | 5/19/2014 | | PASS |
Josh Wilson
|
|
|
Redline on sheet A1.0- fence required on north and east property lines
|
Routing - PLANNING | 5/16/2014 | | 5/19/2014 | | PASS |
Joshua Johnson
|
|
|
Redline on sheet A1.0- fence required on north and east property lines
|
Routing - Erosion and Sediment | 5/12/2014 | | 5/14/2014 | | PASS |
Andy J. Long
|
|
|
ESC site map and narrative submitted and approved. Valid RP and PD designated.
|
Routing - PUBLIC WORKS | 5/5/2014 | | 5/12/2014 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Kyle Rosenmeyer for sewer design and Brian Murphy for drainage issues
|
Routing PW Solid Waste | | | 5/12/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Sewer Design | 5/6/2014 | | 5/12/2014 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Contract Note – “Contractor shall contact Boise Public Works 48 hours prior to construction and obtain tap permit for sewer connection.”
Contract Note – “Contractor shall CCTV existing sewer line segments immediately up and downstream of new manhole and submit records to Boise Public Works.”
Please add callout to plan and profile at intersection of the sewer extension and the westerly property line. Reading in effect “End public sewer, begin private sewer”.
Please add to profile callout for MH SW2105A1: “Manhole base shall be precast per SD-501A”
|
Routing PW Street Lights | | | 5/6/2014 | | PASS |
Mike D Hedge
|
|
|
No street lighting required.
|
Routing PW Sewer Rating | 5/6/2014 | | 5/6/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 5/5/2014 | | 5/5/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/2/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLANNING Land Div | 5/2/2014 | | 5/2/2014 | | PASS |
Dave Abo
|
|
|
|
Application received | | 5/1/2014 | 5/1/2014 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 5/1/2014 | | PASS |
Sam Zahorka
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/1/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/1/2014 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 1/10/2015 | | | |
|
|
|
|
Zoning Approval Temp | 12/11/2014 | 12/11/2014 | | | PASS |
Sarah Schafer
|
|
|
Bond placed for sod.
|
Routing PW Drainage | 5/6/2014 | | | | FAIL |
Brian McGowan
|
|
|
|