BLD-Final | 3/16/2015 | 3/17/2015 | 3/17/2015 | A | PASS |
Tony Young
|
|
|
Phone #: 2088506700 >> Inspection requested via mobile web by Chad crocker
|
DOC - Permit Finaled | 3/17/2015 | 3/17/2015 | 3/17/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 3/16/2015 | 3/16/2015 | 3/16/2015 | P | PASS |
Tony Young
|
|
|
Phone #: 2088506700 >> Inspection requested via mobile web by Chad crocker
|
PubWorks Occupancy Approval | 3/16/2015 | 3/16/2015 | 3/16/2015 | | DONE |
Brian Murphy
|
|
|
|
BLD-Grading Inspection | 3/11/2015 | 3/12/2015 | 3/12/2015 | A | PEND |
Tony Young
|
|
|
Chad Phone #: ###-####
|
BLD-Conference | 12/11/2014 | 12/11/2014 | 12/11/2014 | P | PASS |
Tony Young
|
|
|
Chad Phone #: ###-####,, soffit can light protection
|
BLD-Framing/Rough-in | 11/7/2014 | 11/10/2014 | 11/10/2014 | A | PASS |
Jim Sly
|
|
|
Chad Phone #: ###-####
|
BLD-Framing/Rough-in | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | PART |
Tony Young
|
|
|
Chad Phone #: ###-####,, need to redo shear per plan,, need sprinkler full pass (they are ok with wall insulation), other minor corrections, straps on plates, etc,, went over these with framer,, ok to insulate walls if needed
|
Plan Modification Accepted | | | 10/1/2014 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 10/1/2014 | | 10/1/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Foundation | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PASS |
Phil Shearer
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 7/8/2014 | 7/9/2014 | 7/9/2014 | A | PASS |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
PubWorks Subgrade Approval | 7/9/2014 | 7/9/2014 | 7/9/2014 | | DONE |
Jason C. Taylor
|
|
|
*ALL FOOTINGS* A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 7/8/2014 | 7/8/2014 | 7/8/2014 | P | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####,, need soils report 1st
|
BLD-Other | 6/17/2014 | 6/18/2014 | 6/18/2014 | P | PART |
Tony Young
|
|
|
basement rebar - Ryan Phone #: ###-####
|
BLD-Footing | 6/11/2014 | 6/12/2014 | 6/12/2014 | A | PART |
Tony Young
|
|
|
the approved plans are in the outhouse if no one is there // Ryan Phone #: ###-####,, basement ftgs ok
|
PubWorks Subgrade Approval | 6/12/2014 | 6/12/2014 | 6/12/2014 | | DONE |
Jason C. Taylor
|
|
|
*BASEMENT FOOTINGS ONLY**A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 5/28/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/27/2014 | | |
|
|
|
|
Plan assigned to (JG) | 5/6/2014 | 5/6/2014 | 5/27/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, Due 5/22 TH L2 Hillside**
|
Application received | | 5/2/2014 | 5/27/2014 | | DONE |
|
|
|
|
Telephone call | | | 5/27/2014 | | DONE |
Tisha Gallop
|
|
|
called Chad and left vm permit is ready and fee due.
|
Routing - PLAN CHECK | 5/21/2014 | | 5/27/2014 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 5/27/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/27/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 5/27/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 5/23/2014 | 5/23/2014 | 5/23/2014 | | PASS |
Scott Arellano
|
|
|
Approved. Attached plan review report to Tidemark case.
|
Telephone call | | | 5/23/2014 | | DONE |
Javier Guzman
|
|
|
spoke with Jake the engineer about items needed and for clarification/location of beams called on plans
|
Telephone call | | | 5/21/2014 | | DONE |
Javier Guzman
|
|
|
Jake an engineer called regarding engineering that was not sent to me which is why the 2nd plan review failed.
|
Routing PW Grading-Hillside | 5/21/2014 | | 5/21/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Plan resubmittals received | | | 5/21/2014 | | DONE |
Christina Prado
|
|
|
received two sets of revised plans sheets marked S, 1, 2, 3, 4, 5, 6, 7, 8 & 9. Various shets are duplicates showing only the engineers stamp as the change;Plans taken back to Javier for further review
|
Routing - PLAN CHECK | 5/21/2014 | | 5/21/2014 | | FAIL |
Javier Guzman
|
|
|
some items on review report not addressed
|
1st review completed | | | 5/16/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | | | 5/16/2014 | | FAIL |
Javier Guzman
|
|
|
sent review report to applicant
|
Routing - FIRE | 5/12/2014 | | 5/14/2014 | | FAIL |
Scott Arellano
|
|
|
Emailed applicant Fire Code comments with correction items. Attached plan review report to case.
|
Routing - MECHANICAL | 5/12/2014 | | 5/12/2014 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 5/6/2014 | | 5/12/2014 | | FAIL |
Troy James
|
|
|
emailed correction to teds heating
|
Routing - Erosion and Sediment | 5/12/2014 | | 5/12/2014 | | PASS |
Andy J. Long
|
|
|
ESC site map and narrative submitted. Valid PD and RP designated. Approved. Site prep inspection required.
|
Route to Impact Fee Review | 5/5/2014 | 5/8/2014 | 5/9/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 5/2/2014 | 5/7/2014 | 5/9/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 5/5/2014 | | 5/6/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 5/6/2014 | | 5/6/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLANNING | 5/6/2014 | | 5/6/2014 | | PASS |
David Moser
|
|
|
Approval as redlined, move interior garage wall back one foot to provide 20 foot deep parking space and remove shower in garage as noted. Ok as per CFH14-00020 and CZC14-00137
|
Routing PW Grading-Hillside | | | 5/6/2014 | | FAIL |
Jason C. Taylor
|
|
|
Need copies of the Geotechnical Report submitted for approval. Jason Taylor ###-####.
|
Plan resubmittals received | | | 5/6/2014 | | DONE |
Tisha Gallop
|
|
|
received two copies of Geotech report; put with plans currently in planning
|
Plans ACCEPTED BY PLAN TECH | | | 5/5/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Override - Parcel Holds | | | 5/5/2014 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/5/2014 | | |
Candy A. Nichols
|
|
|
today is the 10th day after City Zoning Ordinance
|
Intake Approval | | | 5/5/2014 | | PASS |
Candy A. Nichols
|
|
|
|