Second Notice | | 10/16/2014 | 10/24/2014 | | DONE |
|
|
|
|
Print Statement | | | 10/24/2014 | | DONE |
Tisha Gallop
|
|
|
e-mailed to Duel Christensen at Anderson Const
|
First Notice | | 9/27/2014 | 10/6/2014 | | DONE |
|
|
|
e-mailed to Duel Christensen at Anderson Construction
|
Permanent Occupancy | | | 9/24/2014 | | DONE |
|
|
|
|
BLD-Final | 9/16/2014 | 9/16/2014 | 9/17/2014 | P | PASS |
Dave Hannah
|
|
|
Duel Phone #: ###-####
|
Permanent Occupancy | | | 9/17/2014 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 9/16/2014 | 9/16/2014 | 9/16/2014 | P | PASS |
Forrest France
|
|
|
Verified noted correction items for completion. Fire life safety inspection passed.
|
FIRE-Final Inspection | 9/8/2014 | 9/8/2014 | 9/8/2014 | P | FAIL |
Forrest France
|
|
|
Items noted include; repair EM lights at five locations, repair one exit sign, provide EM lighting per plan review note at the south breakroom area, post two fire extinguishers with current certification tags, install main entry door, provide panic hardware at the elevator lobby stairway access door west side.
|
FIRE-Conference | 9/8/2014 | 9/8/2014 | 9/8/2014 | P | DONE |
Forrest France
|
|
|
Regarding plan review comments
|
BLD-Framing/Rough-in | 7/18/2014 | 7/21/2014 | 7/21/2014 | A | PASS |
Jim Storey
|
|
|
Jim (patrick ###-####) Phone #: ###-####
|
Permit Ready to Issue | | | 6/2/2014 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 6/2/2014 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 6/2/2014 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 6/2/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CDM) | 5/8/2014 | 5/8/2014 | 5/20/2014 | | PASS |
Carl D Madsen
|
|
|
Level 3 TI - ePlanReview - **GREEN TAG*** Metageek in Owyhee Place
|
Routing - FIRE | 5/6/2014 | 5/6/2014 | 5/20/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 05-20-14
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2014 | | DONE |
|
|
|
|
1st review completed | | | 5/20/2014 | | PASS |
Craig D. Hanson
|
|
|
|
Routing - PLAN CHECK | 5/6/2014 | | 5/16/2014 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLUMBING | 5/6/2014 | | 5/12/2014 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Plan assigned to (CJW) | 5/6/2014 | 5/6/2014 | 5/8/2014 | | DEFR |
Carl Westfall
|
|
|
Level 3 TI - ePlanReview - Metageek in Owyhee Place (15 days - May 26) Reassigned to Carl Madsen.
|
Routing PW Sewer Rating | 5/6/2014 | | 5/7/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | | 5/6/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 6 2014 8:07AM
|
Intake Approval | | | 5/6/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin. Plan Review Fees paid.
|
Pending Assignment by JCB | 5/6/2014 | | 5/6/2014 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 5/6/2014 | | 5/6/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/6/2014 | | 5/6/2014 | | PASS |
Beverly Mountain
|
|
|
|