First Notice | 7/7/2014 | 7/7/2014 | 8/27/2014 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 7/3/2014 | 7/7/2014 | 7/7/2014 | P | PASS |
Jim Storey
|
|
|
JR Phone #: ###-####
|
DOC - Permit Finaled | 7/7/2014 | 7/7/2014 | 7/7/2014 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 7/3/2014 | 7/7/2014 | 7/7/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. No duct smoke detectors required due to meeting the exception in IMC for smoke being unable to travel outside of the enclosed area. If walls are built exception may not apply
|
CHANGE STATUS TO (FNL) | | | 7/7/2014 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 7/3/2014 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 7/3/2014 | | DONE |
Barbara Stitt
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 6/9/2014 | | 7/2/2014 | | PASS |
Tim L. Woodard
|
|
|
Re-assigned in Adele's Absence. TLW
|
Permit Ready to Issue | | | 7/2/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - FIRE | 6/30/2014 | | 7/1/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 07-01-14
|
Plan resubmittals received | | | 6/30/2014 | | DONE |
Tim L. Woodard
|
|
|
Responce letter from architect recieve. Tenant will no longer occupy this space. Review to proceed as a "Vanilla Finish" only. A future permit required prior to occupancy. TLW
|
Routing - PLAN CHECK | 6/30/2014 | | 6/30/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 6/9/2014 | | 6/16/2014 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 6/9/2014 | 6/9/2014 | 6/12/2014 | | FAIL |
Craig D. Hanson
|
|
|
No report. Will re-evaluate when plan is resubmitted to Building with more information regarding Occupancy type and load.
|
Plan assigned to (AJS) | 5/8/2014 | 5/8/2014 | 6/9/2014 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
Re-assigned in Adele's Absence. TLW
|
Plan resubmittals received | | | 6/9/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Design Review | 5/21/2014 | | 5/22/2014 | | PASS |
Sarah Schafer
|
|
|
Approved through building permit. No CZC required.
|
Routing - PLAN CHECK | 5/21/2014 | | 5/21/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 5/8/2014 | | 5/12/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
needs TI, see change marks in e plan
|
1st review completed | | | 5/12/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 5/8/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 5/7/2014 | | DONE |
|
|
|
Application submitted via PDS Online on May 7 2014 9:46AM
|