Permit NumberBLD14-01183
StatusFinaled
Name HCD INC
Site Address 4774 W STATE ST
Project NameCollister Shopping Center
Customer Number 
ePlanReviewYes
Description
(VANILLA FINISH - Collister Shopping Center) Permit to intall New roof top hvac units. Structural calcuations approving existing roofing design adequate. This building is not Fire Sprinklered. Note: An additional permit is required prior to occupancy being allowed in this space. Separate mechanical permit required. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice7/7/20147/7/20148/27/2014 DONE
DetailsJim Storey
BLD-Final7/3/20147/7/20147/7/2014PPASS
DetailsJim Storey
JR Phone #: ###-####
DOC - Permit Finaled7/7/20147/7/20147/7/2014PPASS
DetailsJim Storey
FIRE-Final Inspection7/3/20147/7/20147/7/2014PPASS
DetailsTroy Cobbley
life safety passed. No duct smoke detectors required due to meeting the exception in IMC for smoke being unable to travel outside of the enclosed area. If walls are built exception may not apply
CHANGE STATUS TO (FNL)  7/7/2014 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  7/3/2014 DONE
DetailsBarbara Stitt
Inspection Record Card- Bld  7/3/2014 DONE
DetailsBarbara Stitt
PLANS/APPL TAKEN TO FRONT DESK  7/2/2014 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)6/9/2014 7/2/2014 PASS
DetailsTim L. Woodard
Re-assigned in Adele's Absence. TLW
Permit Ready to Issue  7/2/2014 DONE
DetailsBarbara Stitt
Routing - FIRE6/30/2014 7/1/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review 07-01-14
Plan resubmittals received  6/30/2014 DONE
DetailsTim L. Woodard
Responce letter from architect recieve. Tenant will no longer occupy this space. Review to proceed as a "Vanilla Finish" only. A future permit required prior to occupancy. TLW
Routing - PLAN CHECK6/30/2014 6/30/2014 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK6/9/2014 6/16/2014 FAIL
DetailsTim L. Woodard
Routing - FIRE6/9/20146/9/20146/12/2014 FAIL
DetailsCraig D. Hanson
No report. Will re-evaluate when plan is resubmitted to Building with more information regarding Occupancy type and load.
Plan assigned to (AJS)5/8/20145/8/20146/9/2014 DEFR
DetailsAdele J Schaffeld-Griffin
Re-assigned in Adele's Absence. TLW
Plan resubmittals received  6/9/2014 DONE
DetailsTim L. Woodard
Routing - Design Review5/21/2014 5/22/2014 PASS
DetailsSarah Schafer
Approved through building permit. No CZC required.
Routing - PLAN CHECK5/21/2014 5/21/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK5/8/2014 5/12/2014 FAIL
DetailsAdele J Schaffeld-Griffin
needs TI, see change marks in e plan
1st review completed  5/12/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Intake Approval  5/8/2014 PASS
DetailsAdele J Schaffeld-Griffin
Application received  5/7/2014 DONE
Application submitted via PDS Online on May 7 2014 9:46AM